Permit Information
Permit NumberBLD11-01192
StatusFinaled
Name JC CONSTRUCTORS
Site Address 2076 S CENTURY WAY
Project NameOXARC INC
Customer Number 
ePlanReviewNo
Description
(OXARC INC) *** 1-12-2012 PLAN MODIFICATION TO INCLUDE: REPLACE THE EXISTING EXTERIOR METAL SIDING WITH NEW METAL SIDING; REPLACE THE EXISTING EXTERIOR CONCRETE PAD WITH A NEW PAD FOR LARGE TANKS; REPLACE THE EXISTING CONCRETE STEPS AT THE MAIN ENTRANCE WITH PRE-ENGINEERED METAL STAIRS; INSTALL NEW BOLLARDS AT THE EXISTING OVERHEAD DOOR LOCATIONS; AND INSTALL A CONCRETE SCREEN ENCLOSURE FOR THE PROPANE TANKS. SRZ*** Remodel for a new tenant in an existing 10,520 sq. ft. building per approved plans. Building is 8,000 sq. ft. with a 2,520 covered dock area. Tenant use is for retail, filling, and storage of compressed gases with some office. NOTE: This building was originally constructed in Ada County and annexed into Boise City in 2002. Work to include: demolition work including the removal of an existing mezzanine per plans; construction of interior partitions walls creating; individual office areas, open office area, warehouse space, showroom, gas filling space, extinguisher area, charging room, hydro room, break room, electrical room, janitor room, and two new fully accessible restroom; install a new dual height (hi-lo) accessible drinking fountain; installation of a new storefront entry system; installation of new slot wall system on specific walls; new sales counter; new ADA ramp and dock area; installation of new suspended acoustical ceiling system; upgrade the lighting layout; interior finishes in compliance with chapter 8 of the 2009 IBC; new mechanical, new plumbing, and new electrical work; and all other work per the approved plans, attached plan review report, and all other reviewing agencies approvals. NOTE: This building will be fully fire sprinklered for area increase. A new Certificate of Occupancy with the new occupant load total is required to be obtained after all work has been inspected and approved and prior to tenant occupying this space. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 6/26/20126/21/2012 DONE
Second Notice 6/16/20126/21/2012 DONE
First Notice 5/24/20126/6/2012 DONE
Permanent Occupancy  5/14/2012 DONE
DetailsTisha Gallop
FIRE-Final Inspection5/10/20125/11/20125/11/2012APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final5/11/20125/11/20125/11/2012PPASS
DetailsTom Arcoraci
nate Phone #: ###-####
BLD-Final4/18/20124/19/20124/19/2012ADONE
DetailsTom Arcoraci
Nate Phone #: ###-####
Temporary Occupancy4/19/20127/18/20124/19/2012 DONE
DetailsTisha Gallop
BLD-Final4/18/20124/18/20124/18/2012PPASS
DetailsTom Arcoraci
Nate Phone #: ###-#### ok for temp occ
FIRE-Final Inspection4/16/20124/17/20124/17/2012APART
DetailsTroy Cobbley
A temporary is being given for the fire life safety inspection until the bollards and parking lot is finished. This is per Romeo Gervais.
FIRE-Conference4/16/20124/16/20124/16/2012PDONE
DetailsTroy Cobbley
Met Darren and went over the signage requirement for fire dept access. I also noted that a 5,000 or 6,000 gallon carbon dioxide tank that had not been shown on the plans is now installed along the north property line. I contacted scott arellano and he was ok with the installation of the tank and no additional submittal were to be required. Darren also asked about the bollards at the north side tanks. I deferred him to the fire chief since their installation does not match IFC 318.
BLD-Final4/12/20124/12/20124/13/2012PNR
DetailsTom Arcoraci
FIRE-Final Inspection4/10/20124/12/20124/12/2012PFAIL
DetailsTroy Cobbley
(1) The vehicle protection "bollards", required per the IFC do not meet section 312.2, 1, 2 and 5 for spacing between posts, filled with concrete or 3'-0" clearance from the propane tank. (2) The LOX tank has not been installed to verify the 5'-0" clearance from the property line. (3) Provide fire dept access signage per review note #8 (4) Finish mounting the fire extinguishers. (5) Provide the missing exits signs and repair the exit discharge and interior emergency lights. (6) Mount and test the fire sprinkler exterior alarm bell (7) The fire alarm system manual pull station is mounted too high and needs to be lowered. (8) United Water has not turned on the water supply for the fire sprinkler system therefore the forward flush could not be performed or any alarms for flow tested. (9) Repair the 6" sprinkler hanger at the top of the dry pipe system that has been disconnected. There may be other items added to the list once actual testing can be performed. Per the drawings and the electrical contractor the electrical service is less than the 1,200 ampers therefore panic hardware is not required on the electrical room.
BLD-Final4/10/20124/12/20124/12/2012ANR
DetailsTom Arcoraci
nate Phone #: ###-####
BLD-Other3/14/20123/15/20123/15/2012APASS
DetailsTom Arcoraci
Grid ceiling -- Darrin Phone #: ###-####
BLD-Footing2/9/20122/10/20122/10/2012APASS
DetailsTom Arcoraci
darrin - concrete pour at 10:00 Phone #: ###-####
BLD-Conference2/1/20122/1/20122/1/2012PPASS
DetailsTom Arcoraci
eng says 2500 psi min ok for tank slab
CHANGE STATUS TO (ISS)  1/31/2012 DONE
DetailsTisha Gallop
paid and picked up approved plan mod
Plan assigned to (SRZ)1/11/20121/11/20121/27/2012 DONE
DetailsSam Zahorka
1st review completed for plan mod. Failed Fire review
PLANS/APPL TAKEN TO FRONT DESK  1/27/2012 DONE
DetailsSam Zahorka
Print Occupancy Form  1/27/2012 DONE
Telephone call  1/27/2012 DONE
DetailsChristina Prado
called and gave Jim fees due and advised plan mod is ready for pick up
Permit Ready to Issue  1/27/2012 DONE
DetailsChristina Prado
Routing - PLAN CHECK1/13/2012 1/26/2012 PEND
DetailsSam Zahorka
Received resubmittals for Fire Review. Routed to Fire plan review.
Routing - FIRE1/26/2012 1/26/2012 PASS
DetailsTim Frost
Plan resubmittals received  1/25/2012  
Received 1 copy of cover transmittal, 1 copy of letter to Tim Frost from Justin Wall dated 1-25-12, 2 copies of sheets A-0.1, S-1.1 and taken to Sam Zahorka's desk
Telephone call  1/23/2012 DONE
Emailed the following to Justin Wall

Per our phone conversation of today. The drawings need to annotated to say 6000 Gal and a dimension indication 5'-0" minimum from the propertly line.

In regards to the 1000 Gal propane tank.

The tank is required to be at least 10' from the property line and 25' from any other propane tank over 125 gal. (Ref: IFC: Table 3804.3 footnote f)

The propane tank must be protected from damage since it is located in a parking area. (Ref: 3807.4) See Section 312 excerpt (below) for protection requirements.

__________________________________
SECTION 312
VEHICLE IMPACT PROTECTION
312.1 General.
Vehicle impact protection required by this code shall be provided by posts that comply with Section 312.2 or by other approved physical barriers that comply with Section 312.3

312.2 Posts.
Guard posts shall comply with all of the following requirements:
1. Constructed of steel not less than 4 inches (102 mm) in diameter and concrete filled.
2. Spaced not more than 4 feet (1219 mm) between posts on center.
3. Set not less than 3 feet (914 mm) deep in a concrete footing of not less than a 15-inch (381 mm) diameter.
4. Set with the top of the posts not less than 3 feet (914 mm) above ground.
5. Located not less than 3 feet (914 mm) from the protected object.

312.3 Other barriers.
Physical barriers shall be a minimum of 36 inches (914 mm) in height and shall resist a force of 12,000 pounds (53 375 N) applied 36 inches (914 mm) above the adjacent ground surface.
__________________________________

Plan assigned to (SRZ)1/11/20121/11/20121/17/2012 FAIL
DetailsSam Zahorka
Plan Modification. Pending Statement of Special Inspection and Fire to PASS.
Telephone call  1/17/2012 DONE
DetailsSam Zahorka
Left message with the architect Justin Wall. Plan modification submittal failed Fire plan review. I did receive the Statement of Special Inspection application. Permit issuance pending Fire plan review to pass.
Plan Reviewer's activity  1/17/2012 DONE
Emailed copy of Fire Review to jwall@grboise.com
Routing - FIRE1/12/2012 1/13/2012 FAIL
DetailsTim Frost
1st review completed  1/13/2012 FAIL
Failed - Fire
Routing - PLAN CHECK1/11/2012 1/12/2012 FAIL
DetailsSam Zahorka
Statement of special inspections required prior to plan mod issuance.
Case Summary (BLD)  1/12/2012 DONE
DetailsSam Zahorka
Routing - PLANNING1/11/2012 1/11/2012 PASS
DetailsAndrea Tuning
CZC12-00002 Andrea
Plan Modification Accepted  1/10/2012 DONE
DetailsTisha Gallop
Plan Modification accepted for Bld11-01192 (Oxarc Inc) to Replace the existing metal siding with new metal siding onall sides of building. Replace existing exterior concrete pad with new pad for large tanks. Replace existing concrete steps at main entrance with pre-engineered metal stairs. Install bollards at existing overhead door locations. Install concrete screen enclosure for propane tanks. Submitted on plan sheets CVR, A0.1, A1.1, A3.1, A3.3, S1.1, revised cert of value and structural calculations. Reference CZC12-00002. Routed to Sam Zahorka.
Issue PAID IN FULL permit  9/14/2011 DONE
DetailsBarbara Stitt
Print Occupancy Form  9/14/2011 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  9/14/2011 DONE
DetailsBarbara Stitt
Telephone call  8/19/2011 DONE
DetailsChristina Prado
Called and left a message for Peter giving fees due and ACHD Requirement prior to issuance of permit
Permit Ready to Issue  8/19/2011 DONE
DetailsChristina Prado
Routing - FIRE8/12/2011 8/18/2011 PASS
DetailsTim Frost
Please, see attached review
Routing - PLAN CHECK8/18/2011 8/18/2011 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  8/18/2011 DONE
DetailsSam Zahorka
Print Occupancy Form  8/18/2011 DONE
Plan assigned to (SRZ)6/2/2011 8/18/2011 PASS
DetailsSam Zahorka
1st review completed. Pending Corrections.
Routing - PLAN CHECK7/29/2011 8/12/2011 PEND
DetailsSam Zahorka
Plan resubmittals received  8/10/2011 DONE
received 1 letter of transmittal, 1 comments,and 2 copies of sheets A-0.1,A-1.1 sent to Sam Z.
Plan Reviewer's activity  8/2/2011 DONE
Sent the following email to Justin Wall in response to his email with questions.

Hi Justin,

I failed to mention in my previous review that you are only allowed 4 control areas (inside). I thought you would the move the storage into the parking lot as previously discussed. Please, keep in mind that you already have at least one control area in the gas filling room. Therefore, you could have 3 more control areas on the covered dock. The 3 control areas must be separated by fire barriers per IFC 2703.8.3 and have floors that comply with 2703.8.3.4. It is very hard to point out all of the pertinent code sections. I would suggest that you get a FPE involved with the project to help you with the design. All of the IFC and IBC of course applies. However, you may want to pay specific attention to chapters 27, 35 and 40 of the IFC.
Plan Reviewer's activity  7/29/2011 DONE
Emailed review to RP
Routing - PUBLIC WORKS7/28/2011 7/29/2011 PASS
DetailsConnie Baumgartner
Additional drinking fountain added.
Routing - FIRE7/29/2011 7/29/2011 FAIL
DetailsTim Frost
Email review to RP
Case Summary (BLD)  7/28/2011 DONE
DetailsSam Zahorka
Routing - PLAN CHECK6/30/2011 7/28/2011 PEND
DetailsSam Zahorka
Pending Fire to pass and Public Works.
Plan resubmittals received  7/26/2011 DONE
7-26-11 received 1 letter of transmittal,1 comments,and 2 copies of sheet A1.1 sent to Sam Z.
Plan resubmittals received  7/26/2011 DONE
7-25-11 received 1 letter of transmittal,1 comment,1 response,and 2 copies of sheets CVR,A-1.1,A-6.1,P-2.0,E-2.0L,E-3.2 taken to Sam Z
Plan Reviewer's activity  7/12/2011 DONE
Emailed review to Justin Wall jwall@grboise.com
1st review completed  6/30/2011 DONE
Failed - Plan Check, Fire
Routing - FIRE6/27/2011 6/30/2011 FAIL
DetailsTim Frost
Please, see attached review.
Case Summary (BLD)  6/27/2011 DONE
DetailsSam Zahorka
Routing - PLAN CHECK6/9/2011 6/27/2011 FAIL
DetailsSam Zahorka
Pending Fire reviews evaluation of proposed hazardous material storage.
Plan Reviewer's activity  6/16/2011 DONE
DetailsJason Blais
ACHD has indicated they would like to see this project for review. Applicant required to submit plans to ACHD for evaluation. Sarah Schafer communicated this to Allison of Glancey Rockwell. Written verification from ACHD will need to be provided prior to permit issuance.
Routing - Design Review6/8/2011 6/9/2011 PASS
DetailsSarah Schafer
Ok per CZC11-00132. Retail showroom is less than 25% of floor area and allowed as accessory use to primary allowed use.
Routing - PLUMBING6/6/2011 6/8/2011 PASS
DetailsBill VanDegrift
Per plans and 2003 UPC.
Routing - Erosion and Sediment6/3/2011 6/6/2011 PASS
DetailsSteven Webb
ESC plan is approved according to the ESC Blueprint and ESC Permit conditions. ESC11-00333
Routing PW Sewer Rating6/3/2011 6/3/2011 PASS
DetailsConnie Baumgartner
Routing - PUBLIC WORKS6/2/2011 6/3/2011 PASS
DetailsConnie Baumgartner
Pending Assignment by JCB6/1/2011 6/2/2011 DONE
DetailsJason Blais
Routing - Addressing6/2/2011 6/2/2011 PASS
DetailsTerry Records
Plans ACCEPTED BY PLAN TECH  6/1/2011 DONE
DetailsChristina Prado
Intake Approval  6/1/2011 PASS
DetailsCarl D Madsen
Recd Pcfee & Taken To Pln CK  6/1/2011 DONE
DetailsChristina Prado
Application received 6/1/2011