BLD-Final | 10/25/2011 | 10/25/2011 | 10/27/2011 | P | DONE |
Tony Young
|
|
|
dave - please call for access Phone #: ###-####
|
BLD-Final | 10/25/2011 | 10/26/2011 | 10/26/2011 | A | PASS |
Tony Young
|
|
|
dave - please call for access Phone #: ###-####
|
DOC - Permit Finaled | 10/26/2011 | 10/26/2011 | 10/26/2011 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Grading Inspection | 10/24/2011 | 10/24/2011 | 10/24/2011 | P | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Energy code compliance | 8/24/2011 | 8/24/2011 | 8/24/2011 | P | PASS |
Tony Young
|
|
|
Dave-Please call prior to inspection-also please look at the correction notice items Phone #: ###-####
|
BLD-Framing/Rough-in | 8/19/2011 | 8/22/2011 | 8/22/2011 | P | FAIL |
Mike Jordan
|
|
|
dave Phone #: ###-####. Provide TBE at bearing joint 1 on AG11. Justify boared thru bootom chord of AG1 truss. Complete foam sealing and fire blocking. ok to insuolate after fire has passed.
|
BLD-Wall cover | 8/12/2011 | 8/12/2011 | 8/12/2011 | P | PASS |
Tom Arcoraci
|
|
|
dave - cover for exterior soffetts Phone #: ###-####
|
BLD-Wall cover | 8/9/2011 | 8/9/2011 | 8/9/2011 | P | PASS |
Tony Young
|
|
|
Sheer inspection-Dave Phone #: ###-####,, exterior ok to cover
|
BLD-Framing/Rough-in | 8/8/2011 | 8/9/2011 | 8/9/2011 | A | PART |
Tony Young
|
|
|
Sheer inspection-Dave Phone #: ###-####,, shear ok on exterior
|
BLD-Other | 7/29/2011 | 8/8/2011 | 8/8/2011 | A | CANC |
Tony Young
|
|
|
Sheer Wall---Dave Phone####-####-contractor called and rescheduled
|
BLD-Foundation | 7/14/2011 | 7/15/2011 | 7/15/2011 | A | PASS |
Jim Storey
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 7/14/2011 | 7/14/2011 | 7/15/2011 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####,, some rebar is tied for the stem walls,, work in progress,, (note... some of the footings were dug down below the surface,, most are 10-12" thick)
|
BLD-Foundation | 7/14/2011 | 7/14/2011 | 7/15/2011 | P | NR |
Tony Young
|
|
|
mana Phone #: ###-####
|
BLD-Foundation | 7/13/2011 | 7/14/2011 | 7/14/2011 | A | NR |
Tony Young
|
|
|
Mana Phone #: ###-####
|
BLD-Footing | 7/13/2011 | 7/13/2011 | 7/13/2011 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####,, work in progress
|
BLD-Final | 7/8/2011 | 7/8/2011 | 7/8/2011 | P | CANC |
Jim Sly
|
|
|
Brian Phone #: ###-####
|
BLD-Foundation | 7/8/2011 | 7/8/2011 | 7/8/2011 | P | PART |
Jim Sly
|
|
|
Verified rebar in CMU retaining wall.......starting to fully grout wall.
|
BLD-Footing | 7/7/2011 | 7/7/2011 | 7/7/2011 | P | PART |
Tony Young
|
|
|
Dave Phone #: ###-####,, retaining wall ftgs on east p/line,, work in progress
|
BLD-Footing | 7/6/2011 | 7/7/2011 | 7/7/2011 | A | NR |
Tony Young
|
|
|
Dave Phone #: ###-####
|
PubWorks Subgrade Approval | 7/7/2011 | 7/7/2011 | 7/7/2011 | | DONE |
Terry Records
|
|
|
Footing subgrade for house approved by the geotechnical engineer
|
PubWorks Subgrade Approval | 7/6/2011 | 7/6/2011 | 7/6/2011 | | DONE |
Terry Records
|
|
|
Footing subgrade for retaining wall on east side approved by the geotechnical engineer
|
Permit Ready to Issue | | | 6/24/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 6/24/2011 | | DONE |
Tisha Gallop
|
|
|
called David and told him permit is ready and fees.
|
Issue PAID IN FULL permit | | | 6/24/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CDM) | | 6/8/2011 | 6/23/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Erosion and Sediment | 6/22/2011 | | 6/23/2011 | | PASS |
Clint A Smith
|
|
|
ESC 11-00347 plan approved with conditions attached to the permit.
|
Routing - PLAN CHECK | 6/23/2011 | | 6/23/2011 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/23/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/17/2011 | | 6/22/2011 | | FAIL |
Carl D Madsen
|
|
|
Stair modifications are required. Called David with Canyon Crest Homes, he will come down and make the required alterations to the plans. 6-22-11 CDM
|
1st review completed | | | 6/22/2011 | | FAIL |
|
|
|
ESC ans Structural failed
|
Case Summary (BLD) | | | 6/22/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/22/2011 | | DONE |
Christina Prado
|
|
|
received ESC control plans from Srata. NOTE: Plan designer info on signature page
|
Routing - FIRE | 6/16/2011 | | 6/17/2011 | | PASS |
Scott Arellano
|
|
|
Fire Protection:
A residential modified 13D sprinkler system IS required. In addition to the requirements of NFPA 13D there shall be one additional row of sprinklers at the separation wall between the garage and living space.
|
Route to Impact Fee Review | 6/8/2011 | 6/13/2011 | 6/16/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Erosion and Sediment | 6/15/2011 | | 6/16/2011 | | FAIL |
Steven Webb
|
|
|
ESC11-00347 plan failed. Did not include plan designer information, potential pollutants and Concrete clean out details within the ESC plan. Faxed a copy of the to corrections needed to Strata.
|
Routing - MECHANICAL | 6/14/2011 | | 6/15/2011 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/14/2011 | | 6/14/2011 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - PUBLIC WORKS | 6/14/2011 | | 6/14/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | | | 6/13/2011 | | PASS |
Terry Records
|
|
|
Approved as Category 1
|
Routing - Addressing | 6/8/2011 | | 6/13/2011 | | PASS |
Terry Records
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/8/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/8/2011 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/8/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/7/2011 | | FAIL |
Tisha Gallop
|
|
|
|
Application received | | 6/7/2011 | | | |
|
|
|
|