Permit Information
Permit NumberBLD11-01269
StatusFinaled
Name INLAND IDAHO LLC
Site Address 13626 W BALDCYPRESS ST
Project NameAFFINITY - SECTION C
Customer Number 
ePlanReviewNo
Description
AFFINITY AT BOISE-Section C- Section 'C' (East Wing) to construct a four story 1-hour fire rated, wood frame, 52-unit, commercial apartment building of 46,938 sq. ft.(11,685 s.f. - 1st fl / 11,751 s.f. - 2nd thru 4th fl.). There are 18 units @742 s.f.; 1 @ 759 s.f.; 12 @ 553 s.f. and 12 @ 568 s.f.. 4 @ 731 s.f.; 5 @ 762 s.f. A 2-hour combination fire wall & Horizontal exit is being constructed between the East Wing and Center Core portion for allowable area compliance. This building is fully sprinkler W/ 13R system for allowable area increase, addition of 1-story and for occupancy use compliance; alarm with notification system; 1-hour exit corridors connecting the 2-hour stair enclosure and horizontal exit; and mechanical shaft assemblies are indicated as 2-hour rated. Each floor has one exit into a rated stair enclosure and 1 exit through a horizontal exit. All work to be in accordance with the reviewed plans, red-lined notes on plans and attached plan review comments & conditions of all provided plan reviews. CUP10-00052 DRH10-00222 12/14/11 - New Sheets A2.5.1, A2.5.2, A2.5.3, A4.3, A4.5, A8.0, A8.1, A10.0 & A10.1 SUBMITTED 11/18/11 INSERTED INTO OFFICE COPY OF PLANS AND COPY OF SHEETS TO JOB SITE FOR INSTALL IN FIELD COPY.
Sheets S2.3.3, S2.5.2, S2.5.3 & S5.1 SUBMITTED 11/18/11 INSERTED INTO OFFICE COPY OF PLANS AND COPY TO FIELD FOR JOB SET.



See FIR11-00563 for fire sprinkler plan review -TRF
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 9/3/201210/25/2012 DONE
FIRE-Final Inspection8/24/20128/24/20128/24/2012PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Final8/24/20128/24/20128/24/2012PPASS
DetailsJim Sly
OK for Perm Occ.
FIRE-Alarm Testing8/24/20128/24/20128/24/2012PDONE
DetailsTroy Cobbley
Alarm testing was previously completed.
Permanent Occupancy  8/24/2012 DONE
DetailsTisha Gallop
MISC ACTIONS  8/24/2012 DONE
DetailsTisha Gallop
Name of project has changed from "Traditions at Boise" to "Affinity at Boise". See e-mail from Alan Springer attached in documents. The owner is still Traditions at Boise LLC.
Plan assigned to (DRS)8/14/20128/14/20128/23/2012 PASS
DetailsDan Stuart
plan modification
Routing - PLAN CHECK8/14/2012 8/23/2012 PASS
DetailsDan Stuart
Received letter from Mark Sanders, Architect, requesting the plan mod be voided as the door would not be installed at this time and the involved parties want to have the project finaled. If in the future it is decided to install the door a new application and plans for review and permitting will be provided.
PLANS/APPL TAKEN TO FRONT DESK  8/23/2012 PASS
DetailsDan Stuart
Plan mod to be voided and original scope of work permit to be re-established as issued.
Permit Ready to Issue  8/23/2012 DONE
DetailsChristina Prado
plan Modification voided as door will not be in in time to get final occupancy. No review was done so no fees will be due
CHANGE STATUS TO (ISS)  8/23/2012 DONE
DetailsChristina Prado
Telephone call  8/23/2012 DONE
DetailsChristina Prado
Called Mark Sanders (Architect) to advise permit will simply be put back into ISS status so contractor can move forward with occupancy. Dan did no review for the Plan Modification that was submitted 8/14/12 so no additional fees are due
PubWorks Occupancy Approval8/22/20128/22/20128/22/2012 DONE
Details
Telephone call  8/22/2012 DONE
DetailsDan Stuart
Phone call from Mark Sanders, TAO, saying that the proposed door #249 would not be available until sometime in September so the plan modification request is to be voided so that the project can be finaled per original reviewed plans. When door is available, the tenant or owner will submit an application and plan for a permit to install the door.
Plan Modification Accepted  8/14/2012 DONE
DetailsTisha Gallop
Plan modification accpeted for Bld11-01269 (Traditions at Boise LLC - Secion C, East Wing) to install door #249 between units 226 & 227; submitted on plan sheets A2.2.3, A9.0, A9.1 and revised cert of value; routed to Dan Stuart.
BLD-Final8/6/20128/10/20128/10/2012APART
DetailsJim Sly
ROB Phone #: ###-####
Temp Occ OK for 1st and 2nd floors bldg C (tower 3)
FIRE-Final Inspection8/9/20128/10/20128/10/2012APART
DetailsTroy Cobbley
Life safety has passed in area "C" first and second floors. To final this building the signage needs to be provided at the fire control room doors and the fire alarm permit finaled.
FIRE-Final Inspection8/6/20128/9/20128/9/2012PFAIL
DetailsTroy Cobbley
Second floor of area "C" life safety passed but the first floor still has sprinkler pendants taped off and smoke alarms with covers on so it could not pass
BLD-Final8/2/20128/3/20128/3/2012PPART
DetailsJim Sly
occ for 3rd flr//Rob Phone #: ###-####
Temp Occ. OK for 3rd floor ....Tower 3.
FIRE-Final Inspection8/2/20128/3/20128/3/2012APASS
DetailsTroy Cobbley
Life safety passed for the 3rd floor of area "C"
BLD-Final7/27/20127/27/20127/27/2012PPART
DetailsJim Sly
4th Floor Temp Occupancy Inspection Phone #: ###-#### >> Inspection requested via web by Rob Fraser
OK for Temp Occ. of 4th floor only.
BLD-Final7/25/20127/27/20127/27/2012ANR
DetailsJim Sly
Inspection for 3rd and 4th floors of Tower 3. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
FIRE-Final Inspection7/27/20127/27/20127/27/2012PPART
DetailsTroy Cobbley
The life safety for the 4th floor Area "C" passed.
BLD-Final7/25/20127/26/20127/27/2012PNR
DetailsJim Sly
Final inspection for 4th floor Tower 3. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
FIRE-Alarm Testing7/24/20127/24/20127/24/2012PDONE
DetailsTroy Cobbley
Todays test was for the smoke alarms for the third floors of Area "C". The smoke alarms passed testing. The fourth floor could not be tested due to capet work in the corridor.
Zoning Approval7/13/20127/13/20127/13/2012 PASS
DetailsJosh Wilson
FIRE-Conference6/27/20126/28/20126/28/2012ADONE
DetailsTroy Cobbley
Todays inspection was for fire life safety for 3rd and 4th floors of Tower 1 and Tower 2. Items needing completed are smoke alarm testing for tower 2 for both the third and fourth floors due to covers still being in place on the smoke alarms. Also there are still protective tape on several sprinkler heads. A smoke alarm in one bedroom of room 302 did not activate the other smoke alarms.
PubWorks Occupancy Approval6/11/20126/11/20126/11/2012 DONE
DetailsTiffany Lowery
FIRE-Conference5/21/20125/21/20125/21/2012PDONE
DetailsTroy Cobbley
Rod and I went over life safety requirements. I went over the three options for fire dept access designation. The fire hydrant in the northwest corner of the property needs the 5" outlet turned to where it is accessible to the fire dept. A knox box needs to be provided. It appears that exit sign/emergency lights, if placed per plans, will be adequate. The "area of refuge" is noted in the fire dept review as being placed in the stairwells with the requirements for communication. Per Rod the "area of refuge" is in the main corridor. I deferred that any changes will need to be requested through Scott Arellano in plan review. I suggested that the architect become involved.
BLD-Framing/Rough-in4/27/20124/30/20124/30/2012APASS
DetailsJim Sly
Cover inspection for 1st floor units of Tower 3. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
FIRE-Conference4/27/20124/27/20124/27/2012PDONE
DetailsTroy Cobbley
The standpipe hose valves located on all of the floors at the fire wall per the sprinkler plans were to be mounted recessed in the corridor walls. They have been installed surface mounted on the walls and are possibly encroaching into the egress path. After speaking to Dan Stuart, I spoke to the job site superintendant about having the architect submit to the plan reviewer for approval of this installation.
BLD-Conference4/23/20124/24/20124/25/2012PPASS
DetailsJim Sly
Cover inspection for 1st, 2nd, 3rd, 4th floors for corridor rated ceilings. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Conference4/23/20124/24/20124/24/2012AFAIL
DetailsJim Sly
Cover inspection for 1st, 2nd, 3rd, and 4th floor corridor rated ceilings. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Need to complete fire caulking.
BLD-Wall cover4/19/20124/19/20124/20/2012PNR
DetailsJim Sly
Inspection for cover for 1st, 2nd, 3rd, 4th floor corridor ceilings for Tower 3 (Building C). Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Framing/Rough-in4/12/20124/13/20124/15/2012PPASS
DetailsJim Sly
Inspection for all units on 3rd and 2nd floor in Building C - "Tower 3" for cover. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Framing/Rough-in4/11/20124/11/20124/11/2012PCANC
DetailsJim Sly
Rob phone
BLD-Energy code compliance4/10/20124/10/20124/11/2012APASS
DetailsJim Sly
Fire caulking and energy compliance inspection for cover: Units 435, 436, 437, 438, 439, 440. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Energy code compliance4/9/20124/10/20124/10/2012PNR
DetailsMike Jordan
Fire caulking and energy compliance inspection for cover: Units 435, 436, 437, 438, 439, 440. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Framing/Rough-in4/3/20124/4/20124/4/2012APASS
DetailsJim Sly
corridor 5 rm# 479//Rob Phone #: ###-####
BLD-Other3/20/20123/20/20123/20/2012PPASS
DetailsJim Sly
rob - cover inspection for unit 428, 429, 430, 431, 432, 433, and 434 - also 184 and 186 Phone #: ###-####
Override - Parcel Holds3/20/20121/1/19003/20/2012  
cover insp
Plan resubmittals received  3/19/2012  
Received 2 copies of sheets M3.3 & M4.1 and taken to Troy James
MISC ACTIONS  12/19/2011 DONE
Fire alarm review comments attached to BLD11-01267
Plan resubmittals received  11/18/2011 DONE
DetailsTisha Gallop
received Architects response, Engineer response, two copies of plan sheets A2.5.1, A2.5.2, A2.5.3, A4.3, A4.5, A8.0, A8.1, A10.0, A10.1 and three copies of plan sheets S2.3.3, S2.5.2, S2.5.3, S5.1; taken to Dan Stuart
CHANGE STATUS TO (ISS)  11/9/2011 DONE
DetailsTisha Gallop
Status accidentally changed to REV when Dan Stuart put routing activity on 10/13/11. This was not plan mod, just minor change to plans noted, per Dan this permit should be in issued status.
Routing - PLAN CHECK10/12/2011 10/13/2011 PASS
DetailsDan Stuart
New plan sheet A8.0 removing the lines shown in the stair enclosures and the reference note for an area of refuge in the stair enclosures as the building is fully sprinklered per Sec. 1007.3, exception 3, and the architect has declared that the required two-way communication system per Section 1007.8, is being installed at the elevator landings. See Sheets E3.2.2, E3.2.3, E3.3.2, E3.3.3, E3.4.2 & E3.4.3. New sheet inserted into plans and approved copy sent to job site for their plan set, with Jim Sly, Structural Inspector.
BLD-Foundation10/3/201110/3/201110/3/2011PPART
DetailsMike Jordan
frazier - wall - pouring at 2 Phone #: ###-####. Work in progress on stemwalls. Will have special inspection.
Issue PAID IN FULL permit  9/9/2011 DONE
(F) Reprint permit  9/9/2011 DONE
Permit Ready to Issue  8/24/2011 DONE
DetailsTisha Gallop
Print Occupancy Form  8/23/2011 DONE
Route to Impact Fee Review8/1/20118/4/20118/22/2011 PASS
DetailsCindy M. Gould
Plan assigned to (DRS)6/10/2011 8/22/2011 PASS
DetailsDan Stuart
PLANS/APPL TAKEN TO FRONT DESK  8/22/2011 DONE
Routing - PLAN CHECK8/11/2011 8/20/2011 PASS
DetailsDan Stuart
Reviewed plans include required compliance with all attached plan review comments and conditions of all plan reviewing agencies and all red-lined notes added to plans by reviewing agencies.
Plan resubmittals received  8/16/2011 DONE
DetailsTisha Gallop
received three copies of response, structural calcs, and plan sheets S1.1, S2.1.3, S2.2.2, S2.2.3, S3.2; one set routed to outside engineering and two copies taken to Dan Stuart.
Telephone call  8/16/2011 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Routing Off Site - STRUCTURAL8/16/2011 8/16/2011 PASS
DetailsDan Stuart
See BLD11-01267 for final approval letter.
Routing - PLANNING Land Div8/12/2011 8/15/2011 PASS
DetailsTodd Tucker
Routing - Design Review8/8/2011 8/11/2011 PASS
DetailsJosh Wilson
Ok per DRH10-00222 and DRH11-00173
Plan resubmittals received  8/10/2011 DONE
DetailsTisha Gallop
received response and three copies of plan sheets A0.0, A1.0, A2.1.1, A2.1.2, A2.1.3, A2.2.2, A2.2.3, A2.3.1, A2.3.3, A2.4.1, A2.4.3, A2.5.1, A7.2, A8.1, A9.0, A9.1, A9.3, A10.0, A10.1, M2.5.2, M2.5.3, P0.0, E2.1.2, E2.1.3, E2.2.2, E2.3.2, E2.3.3, E2.4.2, E2.4.3, E3.1.2, E3.1.3, E5.0; taken to Dan Stuart.
Routing - PLUMBING8/5/2011 8/8/2011 PASS
DetailsDaryl Spivey
Per plans and 2003 UPC.
Routing - FIRE8/1/20118/1/20118/5/2011 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  8/5/2011 FAIL
Failed Public Works, Structural, Plumbing, Planning, Plan Check
Routing - PLAN CHECK8/5/2011 8/5/2011 PEND
DetailsDan Stuart
Plans routed back to plumbing for review of resubmittals.
Routing - PLAN CHECK7/25/2011 8/1/2011 FAIL
DetailsDan Stuart
Resubmittals reequired. copy of plan review e-mailed to architect. Routing to fire code analyst for review.
Plan resubmittals requested  8/1/2011 DONE
Copy of plan review e-mailed to architect.
Plan resubmittals received  7/25/2011 DONE
DetailsTisha Gallop
received response to plumbing plan review and two copies of plan sheets C1,C2, C3, C4, C5, C6, C7, C8 C9, P0.1, P1.0, P2.6, P2.7, P2.8, P2.0.1, P2.0.2, P2.0.3, P2.1.3; taken to Dan Stuart
Routing - MECHANICAL7/18/2011 7/19/2011 PASS
DetailsTroy James
Mechanical review not required on 4 story building per Bill Van DeGrift- 7-19-11//BAS
Plan resubmittals received  7/18/2011  
Received 2 copies of sheets M3.0, M3.1, M3.2, M3.3, M4.0, M5.0, M5.1 and inserted into plans
Routing - PUBLIC WORKS7/13/2011 7/18/2011 PASS
DetailsBeverly Mountain
Brian Murphy re-review
Routing PW Drainage7/15/2011 7/15/2011 PASS
DetailsBrian Murphy
Routing - PLAN CHECK6/22/2011 7/13/2011 PEND
DetailsDan Stuart
Route to PW for Brian Murphy re-review.
Routing - PLANNING6/20/2011 6/22/2011 FAIL
DetailsJosh Wilson
Plans are not consistent with DRH10-00222
Plan resubmittals received  6/21/2011  
DetailsBarbara Stitt
Received 1 cover transmital and 5 copies of civil plans inserted into plans//BAS
Routing - PLUMBING6/15/2011 6/20/2011 FAIL
DetailsBill VanDegrift
Refer to bld11-01267
Routing - PLANNING  6/20/2011 PASS
DetailsCody Riddle
CUP10-00052-Cody Riddle
Routing - PLANNING Land Div6/14/2011 6/15/2011 FAIL
DetailsTodd Tucker
Do not issue Building Permit until the Property Line Adjustment Record of Survey (ROS11-00018) has been recorded and the existing irrigation and utility easement has been vacated.
Routing - Erosion and Sediment6/15/2011 6/15/2011 PASS
DetailsSteven Webb
ESC11-00348 plan approved with conditions attached to the permit.
Routing PW Sewer Design6/15/2011 6/15/2011 PASS
DetailsJavier Guzman
Sewer Tap Permit Required
Routing - PUBLIC WORKS6/10/2011 6/14/2011 FAIL
DetailsBeverly Mountain
Failed by Brian Murphy ###-####
Failed by Peter McCullough ###-####
Routing PW Sewer Rating6/14/2011 6/14/2011 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste6/14/2011 6/14/2011 PASS
DetailsPeter J. McCullough
Routing PW Street Lights6/14/2011 6/14/2011 PASS
DetailsMike D Hedge
Routing PW Drainage6/13/2011 6/13/2011 FAIL
DetailsBrian Murphy
NEEDS REVISION
Routing - Addressing6/10/2011 6/13/2011 PASS
DetailsTerry Records
See Documents for Apts #
Pending Assignment by JCM6/10/2011 6/10/2011 DONE
DetailsJohn Menard
Plans ACCEPTED BY PLAN TECH  6/10/2011 DONE
DetailsBarbara Stitt
Intake Approval  6/10/2011 PASS
DetailsDan Stuart
Application received 6/8/20116/8/2011 DONE
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  6/8/2011 DONE
DetailsBarbara Stitt
Intake Approval  6/8/2011 FAIL
DetailsDan Stuart