Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD11-01286
StatusFinaled
Name HELLMANN CONSTRUCTION CO INC
Site Address 212 S 16TH ST
Project NameBOISE FIRE STATION #5
Customer Number 
ePlanReviewNo
Description
(BOISE FIRE STATION #5) To repair a portion of the exterior decorative concrete damage by a vehicle on an existing fire station building per approved plans and attached engineering. Work to include: Saw cut and remove the damaged concrete; replace with concrete and reinforcement to match the original concrete dimensions and the size and locations of reinforcing; secure the new concrete and reinforcing with an epoxy tie system per engineering. All work per the approved plans, attached engineering, and structural inspectors final approvals. NOTE: Special Inspection required for Epoxy connections. A certificate of completion shall be issued when work is completed and a final inspection has occurred. Planning & Zoning approval done under CZC11-00139. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 3/15/20143/10/2014 DONE
DetailsChristina Prado
completed 3-10-14
First Notice1/31/20141/31/20143/5/2014 DONE
DetailsDave Hannah
Faxed 3-5-14
BLD-Aging Inspection1/30/20141/31/20141/31/2014APASS
DetailsDave Hannah
DOC - Permit Finaled1/31/20141/31/20141/31/2014APASS
DetailsDave Hannah
BLD-Final11/29/201111/30/201112/2/2011APASS
DetailsDave Hannah
Martin Knoelk Phone #: ###-####
Fees Due Hold11/30/2011 12/2/2011 PASS
DetailsPatricia Smith
Issue & PRINT to be Invoiced  11/29/2011 DONE
DetailsTisha Gallop
gave acct # to Rita to be JV's
Telephone call  11/28/2011 DONE
t/c w mitch - reminded him that this permit will expire on the 6th of December - he said he would get in touch with the appropriate person to get it taken care of
Expiration Notice11/18/201112/12/201111/18/2011 DONE
DetailsPatricia Smith
Inspection Record Card- Bld  6/20/2011 DONE
Permit Ready to Issue  6/20/2011  
Telephone call  6/20/2011 DONE
6-20-11 called Mitch permit ready and fee given ///dld
Plan assigned to (SRZ)6/10/2011 6/17/2011 PASS
DetailsSam Zahorka
Routing - PLAN CHECK6/17/2011 6/17/2011 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  6/17/2011 DONE
DetailsSam Zahorka
1st review completed  6/16/2011 DONE
DetailsSam Zahorka
Telephone call  6/16/2011 DONE
DetailsSam Zahorka
Left Message with Robert ST. Michell, Engineer of record for this project. Need Statment of Special Inspection as required per IBC section 1704.1.1.
Plan Reviewer's activity  6/16/2011 DONE
DetailsSam Zahorka
Need Statment of Special Inspection as required per IBC section 1704.1.1 prioir to permit issuance. Emailed application #310 to Engineer.
Case Summary (BLD)  6/16/2011 DONE
DetailsSam Zahorka
Routing - PLAN CHECK6/13/2011 6/16/2011 FAIL
DetailsSam Zahorka
Pending Statment of Special Inspection as required per IBC section 1704.1.1 prior to permit issuance. Emailed application #310 to Engineer.
Routing - Design Review6/10/2011 6/13/2011 PASS
DetailsSarah Schafer
Sarah Schafer - CZC11-00139
Pending Assignment by JCB6/10/2011 6/10/2011 DONE
DetailsJason Blais
Application received 6/9/20116/9/2011 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  6/9/2011 DONE
DetailsBarbara Stitt
Intake Approval  6/9/2011 PASS
DetailsSam Zahorka