First Notice | | 12/1/2011 | 11/21/2011 | | DONE |
Tisha Gallop
|
|
|
received final cert of value. Verified with Jeff Tonkin (HC Comapany) value is correct, job cost did go up considerably on this project.
|
Permanent Occupancy | | | 11/21/2011 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 11/14/2011 | | DONE |
|
|
|
|
BLD-Final | 10/31/2011 | 10/31/2011 | 10/31/2011 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 10/28/2011 | 10/31/2011 | 10/31/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 10/31/2011 | 10/31/2011 | 10/31/2011 | A | CANC |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 9/26/2011 | 9/27/2011 | 9/28/2011 | A | PASS |
Dave Hannah
|
|
|
east side ok to cover
|
FIRE-Sprinkler Rough-in | 8/19/2011 | 8/19/2011 | 8/19/2011 | P | DONE |
Forrest France
|
|
|
Troy Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 8/19/2011 | 8/19/2011 | 8/19/2011 | A | NR |
Forrest France
|
|
|
Inspection for new heads at the sheetrock ceiling servery entry area- noted new partition and doors not yet installed may create overspacing at adjacent pendents. Project lacks fire sprinkler plans including shop drawings at this time.
|
FIRE-Sprinkler Rough-in | 8/17/2011 | 8/17/2011 | 8/17/2011 | P | PART |
Forrest France
|
|
|
Six pendent heads at the coffee bar sheetrock ceiling inspected prior to cover.
|
Issue PAID IN FULL permit | | | 8/8/2011 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 8/4/2011 | | DONE |
|
|
|
|
Telephone call | | | 8/4/2011 | | DONE |
|
|
|
left vm for dan - permit ready and fees given - also need rp name
|
Permit Ready to Issue | | | 8/4/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/3/2011 | | DONE |
Tisha Gallop
|
|
|
Received 2 copies of Sheets M2.01 & M3.01. Took to Dan Stuart
|
Routing - MECHANICAL | 8/3/2011 | | 8/3/2011 | | PASS |
Troy James
|
|
|
Reviewed new plan sheets M2.01 & M3.01 with Troy to see if his mechanical plan review concerns had been addressed. They have. Plans routing to permit desk to issue.
|
Routing - PLAN CHECK | 8/3/2011 | | 8/3/2011 | | PASS |
Dan Stuart
|
|
|
Received copies of Sheets M2.01 & M3.01 and hand carried to Troy james, Mech Plan Review for approval. Plans approved. Inserted into plans and routed one set to permit desk to be issued.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/2011 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 6/21/2011 | | 8/3/2011 | | PASS |
Dan Stuart
|
|
|
|
Routing - FIRE | 7/27/2011 | | 8/2/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 8/2/2011 | | FAIL |
|
|
|
Failed Plan Check and Mechanical
|
Routing - PLAN CHECK | 8/2/2011 | | 8/2/2011 | | FAIL |
Dan Stuart
|
|
|
Only received one copy of Sheets M2.01 & M3.01 and no response to mechanical Plan Reviewers comments. I called Jared at DC Engineering in Missoula Montana to request missing plans and data.
|
Plan resubmittals received | | | 8/2/2011 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheet M02.01; taken to Dan Stuart.
|
Telephone call | | | 8/2/2011 | | DONE |
|
|
|
Call DC Engineering in Missoula Montana and talked with Jared. Only one copy of plan resubmittal Sheets M2.01 & M3.01 were turned in. I need a second copy. The plan sheets submitted do not appear to have included corrections required by mechanical plan reviewer Troy James in review of 7/7/11. jared said he would check to make sure they had a copy of the corrections and work on plans required. If they do not have acopy of the mechanical review Jared will call me back for a copy.
|
Routing - PLAN CHECK | 7/12/2011 | | 7/27/2011 | | PASS |
Dan Stuart
|
|
|
Data from architect provided for 1-hour roof / ceiling assembly using ESR-1222 report for Donn DXL listed assembly. Plans were red-lined to reflect code compliance requirements and a plan review report was attached to each plan and are considered a part of the reviewed plans for code compliance. Routed plans to fire code analyst for review.
|
Additional plans submitted | | | 7/27/2011 | | DONE |
|
|
|
7/25/11 - Received cover letter and 8-1/2" x 12" SKA-9 & SKA-10 for 1-hour roof / ceiling assembly proposed, ESR-1222. Scanned and attached to permit & plns.
|
Print Pending Permit.LaserJet4 | | | 7/27/2011 | | |
|
|
|
|
Case Summary (BLD) | | | 7/27/2011 | | |
|
|
|
|
Routing - PLAN CHECK | 7/7/2011 | | 7/12/2011 | | FAIL |
Dan Stuart
|
|
|
Plans submitted do not address maintaining the Type II-1 hour construction for the A2.1 occupancy under the UBC with a 1-hour occupancy separation between the A2.1 & the B occupancies. The other option under the 2009 IBC would be constrcution of a 2-hour fire barrier separation between the A2 & B occupancies as part of an unlimited area building per section 507 IBC.
Cannot proceed with plan review or route plans to fire department plan review until the method of code compliance is addressed with plan resubmittals.
I e-mailed a copy of the A2.1 permits & approved history of the HP construction reviewed and approved by Bob Garrison, head plan reviewer at time of HP complex build out.
|
Routing - MECHANICAL | 6/30/2011 | | 7/7/2011 | | FAIL |
Troy James
|
|
|
emailed corrections to applicant and agent
|
Routing - PLUMBING | 6/28/2011 | | 6/30/2011 | | PASS |
Bill VanDegrift
|
|
|
1. Provide adequate backflow protection for expresso equipment.
2. Filtered water to ice machine needs separate RPBP.
3. Per plans and 2003 UPC.
|
Routing - Erosion and Sediment | 6/27/2011 | | 6/28/2011 | | PASS |
Steven Webb
|
|
|
ESC11-00405 plan waiver approved with conditions attached to the permit.
|
Routing PW Sewer Rating | 6/27/2011 | | 6/27/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 6/21/2011 | | 6/27/2011 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Environmental | 6/24/2011 | | 6/24/2011 | | PASS |
Walt Baumgartner
|
|
|
Rvw'd by M Hunter, 1500 gallon GI noted on plans, ok
|
Routing - Addressing | 6/23/2011 | | 6/23/2011 | | PASS |
Terry Records
|
|
|
|
Pending Assignment by JCB | 6/20/2011 | | 6/21/2011 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 6/21/2011 | | DONE |
Jason Blais
|
|
|
Called Dan Hayes of HC Company to have him provide an ESC Application and Waiver Letter.
|
Plan resubmittals received | | | 6/21/2011 | | DONE |
Jason Blais
|
|
|
Received ESC application and Plan Waiver Letter.
|
Application received | | 6/15/2011 | 6/17/2011 | | DONE |
Darla L Downs
|
|
|
|
Intake Approval | | | 6/17/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/17/2011 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/17/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 6/15/2011 | | FAIL |
|
|
|
Need the QF Sheets stamped and signed by design professional. Will also submit CV & App for demo permit at same time.
|