Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD11-01367
StatusFinaled
Name RAINIER CONSTRUCTION
Site Address 5012 N QUAIL SUMMIT WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
This project is for an addition of a 530s.f. addition to an existing single family dwelling. there is to be basement ladder accessed storage off of the garage area; a bedroom on the main level and the upper level making an existing upper level smaller and adding a new code complying stair to acces this new expanded upper level. R-1C ok per Colleen Carroll. Separate electrical, plumbing, mechanical and ESC permits are required along with an ESC Plan Waiver Request. A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at 384-3946. All per the approved plans as marked energy option "Prescriptive Componant Method" Engineering calculations with Engineer's details along with the plan review notes. pep
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/14/201111/18/201111/18/2011PDONE
DetailsTony Young
charlie Phone #: ###-####
DOC - Permit Finaled11/18/201111/18/201111/18/2011PPASS
DetailsTony Young
BLD-Final11/14/201111/14/201111/14/2011PPASS
DetailsTony Young
charlie Phone #: ###-####,,, patio soffit area not complete at owners request,, final ok as per reviewed plans
BLD-Energy code compliance8/24/20118/25/20118/26/2011ADONE
DetailsTony Young
duane Phone #: ###-####
BLD-Energy code compliance8/25/20118/25/20118/25/2011PPASS
DetailsTony Young
duane Phone #: ###-####
BLD-Framing/Rough-in8/23/20118/24/20118/24/2011APASS
DetailsTony Young
duane Phone #: ###-####,, ok to insulate
BLD-Foundation7/5/20117/5/20117/5/2011PPASS
DetailsTony Young
john Phone #: ###-####
BLD-Foundation6/27/20116/28/20116/28/2011PPASS
DetailsJim Storey
Greg Phone #: ###-####
BLD-Foundation6/23/20116/24/20116/25/2011PPART
DetailsTony Young
greg Phone #: ###-####,, basement sides and south wall ok
BLD-Footing6/22/20116/22/20116/22/2011PPART
DetailsTony Young
charlie Phone #: ###-####,, basement and piers ok,, work in progress
BLD-Footing6/21/20116/22/20116/22/2011ANR
DetailsTony Young
charlie Phone #: ###-####,, need soil report approval 1st
PubWorks Subgrade Approval6/22/20116/22/20116/22/2011 DONE
DetailsTerry Records
Footing subgrade approved
Routing Walk-In (PW Hillside)6/16/20116/16/20116/17/2011PDONE
DetailsPerry Paine
A letter from the applicant's geotechnical engineer indicationg that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection.
Routing Walk-In (BLD)6/16/20116/16/20116/17/2011PDONE
DetailsPerry Paine
Plan assigned to (PEP)6/16/20116/16/20116/17/2011 PASS
DetailsPerry Paine
Case Summary (BLD)  6/17/2011  
Inspection Record Card- Bld  6/17/2011  
1st review completed  6/17/2011 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/17/2011 DONE
Issue PAID IN FULL permit  6/17/2011 DONE
DetailsBarbara Stitt
Routing Walk-In (Zoning)6/16/20116/16/20116/16/2011PPASS
DetailsColleen T Carroll
Application received 6/16/20116/16/2011 DONE
DetailsBarbara Stitt