BLD-Final | 12/16/2011 | 12/16/2011 | 12/16/2011 | P | PASS |
Tom Arcoraci
|
|
|
justin Phone #: ###-####
|
DOC - Permit Finaled | 12/16/2011 | 12/16/2011 | 12/16/2011 | P | PASS |
Tom Arcoraci
|
|
|
|
Routing - MECHANICAL | 12/13/2011 | | 12/13/2011 | | PASS |
Troy James
|
|
|
another acca report submitted
|
Routing - MECHANICAL | 12/7/2011 | | 12/7/2011 | | PASS |
Troy James
|
|
|
resubmitted manaul j
|
Plan resubmittals received | | | 12/7/2011 | | DONE |
|
|
|
resubmitted manaual j report
|
Zoning Approval | 11/30/2011 | 11/30/2011 | 11/30/2011 | | DONE |
Josh Wilson
|
|
|
|
BLD-Energy code compliance | 9/15/2011 | 9/16/2011 | 9/16/2011 | A | PASS |
Mike Jordan
|
|
|
justin Phone #: ###-####ok to rock. Aslo spoke to bill vandegrift regarding mechanical equiorment not m,atching design. Noted that contractor will beable to fix, work is in crawl space, by final.
|
BLD-Framing/Rough-in | 9/13/2011 | 9/14/2011 | 9/14/2011 | A | PASS |
Jim Sly
|
|
|
Late morning--- Justin Phone #: ###-####
|
BLD-Framing/Rough-in | 9/9/2011 | 9/9/2011 | 9/9/2011 | P | NR |
Mike Jordan
|
|
|
justin Phone #: ###-####. Needs mechanical rough in inspection.
|
BLD-Foundation | 8/15/2011 | 8/16/2011 | 8/16/2011 | P | PASS |
Tom Arcoraci
|
|
|
bill Phone #: ###-####
|
BLD-Foundation | 7/29/2011 | 8/2/2011 | 8/2/2011 | P | PASS |
Tom Arcoraci
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 7/29/2011 | 8/1/2011 | 8/1/2011 | P | PASS |
Tom Arcoraci
|
|
|
Bill Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/15/2011 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 7/13/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/13/2011 | | DONE |
|
|
|
|
Telephone call | | | 7/13/2011 | | DONE |
Christina Prado
|
|
|
Called and spoke with Kristine, gave fees due minus ACHD, she stated fees already paid and has voucher. Also advised Rp expired, she will bring proof of class registration
|
Permit Ready to Issue | | | 7/13/2011 | | DONE |
Christina Prado
|
|
|
|
Routing - Addressing | 6/22/2011 | | 7/13/2011 | | PASS |
Terry Records
|
|
|
|
Plan assigned to (CDM) | 6/22/2011 | 6/22/2011 | 7/12/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 7/12/2011 | | 7/12/2011 | | PASS |
Troy James
|
|
|
corrections made
|
Routing - PLAN CHECK | 7/12/2011 | | 7/12/2011 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2011 | | |
|
|
|
|
Case Summary (BLD) | | | 7/8/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/1/2011 | | 7/7/2011 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 7/7/2011 | | FAIL |
|
|
|
Failed pending Mechanical 7-7-11 CDM
|
Route to Impact Fee Review | 6/20/2011 | 6/23/2011 | 6/27/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 6/23/2011 | | 6/24/2011 | | FAIL |
Troy James
|
|
|
left message, no email address, same problems as bld11-01391
|
Routing - PUBLIC WORKS | 6/22/2011 | | 6/23/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 6/23/2011 | | 6/23/2011 | | PASS |
Josh Wilson
|
|
|
|
Intake Approval | | | 6/22/2011 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/22/2011 | | DONE |
|
|
|
|
Application received | | 6/20/2011 | | | |
|
|
|
|