BLD-Final | 11/9/2011 | 11/10/2011 | 11/10/2011 | P | PASS |
Jim Sly
|
|
|
nancy Phone #: ###-####
|
DOC - Permit Finaled | 11/10/2011 | 11/10/2011 | 11/10/2011 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 11/8/2011 | 11/9/2011 | 11/9/2011 | P | CANC |
Jim Sly
|
|
|
Nancy Phone #: ###-####////failed MEC
|
BLD-Energy code compliance | 9/22/2011 | 9/23/2011 | 9/23/2011 | A | PASS |
Jim Sly
|
|
|
nancy - as early as possible please Phone #: ###-####
|
BLD-Framing/Rough-in | 9/16/2011 | 9/16/2011 | 9/16/2011 | P | PASS |
Jim Sly
|
|
|
nancy - please call 1/2 hr prior - late afternoon please Phone #: ###-####
|
BLD-Framing/Rough-in | 8/29/2011 | 8/29/2011 | 8/29/2011 | P | FAIL |
Jim Sly
|
|
|
I previously passed framing by mistake......Need all trade rough-ins approved prior to frame inspection.
|
BLD-Framing/Rough-in | 8/25/2011 | 8/26/2011 | 8/29/2011 | P | PASS |
Jim Sly
|
|
|
Nancy-Phone #: ###-####
|
Routing - MECHANICAL | 8/29/2011 | | 8/29/2011 | | PASS |
Troy James
|
|
|
resubmitted plans for manual j
|
BLD-Footing | 7/21/2011 | 7/22/2011 | 7/22/2011 | A | PASS |
Tom Arcoraci
|
|
|
kevin Phone #: ###-####
|
Plan assigned to (PEP) | 7/20/2011 | 7/20/2011 | 7/21/2011 | | DONE |
Perry Paine
|
|
|
|
Route to Impact Fee Review | 6/30/2011 | 7/6/2011 | 7/21/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (CDM) | 6/29/2011 | 6/29/2011 | 7/21/2011 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 7/12/2011 | | 7/21/2011 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 7/21/2011 | | |
|
|
|
|
1st review completed | | | 7/21/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2011 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/21/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/21/2011 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/21/2011 | | DONE |
|
|
|
|
Routing - PLANNING | 7/20/2011 | | 7/20/2011 | | PASS |
David Moser
|
|
|
No reduced site plan provided
|
Routing - MECHANICAL | 7/12/2011 | | 7/12/2011 | | FAIL |
Dixie Fellows
|
|
|
resubmitall not correct..called ival and he will resubmit
|
Routing - MECHANICAL | 7/12/2011 | | 7/12/2011 | | PASS |
Troy James
|
|
|
corrections done
|
Routing - MECHANICAL | 7/5/2011 | | 7/8/2011 | | FAIL |
Troy James
|
|
|
2nd floor manual J drawing doesn't match the plans..need epd for furnace.. furnace and ac are oversized
|
Routing - MECHANICAL | 7/7/2011 | | 7/7/2011 | | FAIL |
Dixie Fellows
|
|
|
orientation doesn't match plans
|
Plan resubmittals received | | | 7/6/2011 | | DONE |
Tisha Gallop
|
|
|
received full new set plans that are to scale. replaced existing plans in mechanical review.
|
Routing - PLANNING | 7/5/2011 | | 7/5/2011 | | FAIL |
David Moser
|
|
|
Failed; need scaled site plan and building drawings
|
Routing - PUBLIC WORKS | | | 7/5/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 6/30/2011 | 7/1/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 7/1/2011 | | 7/1/2011 | | PASS |
Terry Records
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/30/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/30/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 6/29/2011 | | PASS |
Tisha Gallop
|
|
|
|