Permit Information
Permit NumberBLD11-01593
StatusFinaled
Name SPRING CREEK CONTRACTORS
Site Address 684 E BRAEMERE RD
Project Name 
Customer Number 
ePlanReviewNo
Description
This project is for the addition of 220s.f. to an existing detached accessary structure and the placement of 79l.f. of fully engineered retaing wall with R-1B Approved by Colleen Carroll. Hillside drainage approved by Brian Murphy for Terry Records. ESC approved by Steve Webb. All per the approved plans as marked. WUI "A" zone apples. pep
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/16/201112/19/201112/19/2011PDONE
DetailsTony Young
Phone #: ###-#### >> Inspection requested via web by Andrew Zior
DOC - Permit Finaled12/19/201112/19/201112/19/2011PPASS
DetailsTony Young
done
BLD-Framing/Rough-in8/24/20118/25/20118/25/2011APART
DetailsTony Young
frank Phone #: ###-####,, exterior ok to cover,, needs elec for inside
BLD-Other8/18/20118/19/20118/19/2011APART
DetailsTony Young
miles - stemwall Phone #: ###-####,, landscape walls and steps,, misc. ok,, work in progress
BLD-Other8/18/20118/18/20118/18/2011PNR
DetailsMike Jordan
miles - stemwall Phone #: ###-####. No plans on site.
BLD-Footing8/15/20118/16/20118/16/2011APART
DetailsTony Young
miles - rebar - early morning please Phone #: ###-####
BLD-Footing8/9/20118/9/20118/9/2011PPART
DetailsTony Young
miles - rebar Phone #: ###-####,, work in progress on storage room walls, replacement retaining wall,,(less than 4'),, new stair supports,, ok to pour when ready
BLD-Footing8/3/20118/3/20118/4/2011PPART
DetailsTony Young
Miles if possible between 2 & 3 Phone #: ###-####
BLD-Footing8/3/20118/4/20118/4/2011APART
DetailsTony Young
Miles if possible between 2 & 3 Phone #: ###-####,, work in progress
PubWorks Subgrade Approval8/4/20118/4/20118/4/2011 PASS
DetailsTerry Records
footing subgrade approved by the geotechnical engineer
BLD-Concrete7/27/20117/28/20117/28/2011APART
DetailsTony Young
Rebar--miles Phone #: ###-####,, almost done on retaining wall,, ok
BLD-Other7/26/20117/27/20117/27/2011APART
DetailsTony Young
Rebar--miles Phone #: ###-####,, retaining wall,, work in progress
PubWorks Subgrade Approval7/22/20117/22/20117/22/2011 DONE
DetailsTerry Records
Footing subgrade approved by the geotechnical engineer
BLD-Footing7/19/20117/20/20117/20/2011APART
DetailsTony Young
late am//Miles Phone #: ###-####,, footings ok pending soils report
Routing Walk-In (BLD)7/12/20117/12/20117/12/2011PDONE
DetailsPerry Paine
Plan assigned to (PEP)7/12/20117/12/20117/12/2011 PASS
DetailsPerry Paine
Routing Walk-In (BLD)7/11/20117/11/20117/12/2011ADONE
DetailsChristina Prado
Routing - Erosion and Sediment7/11/2011 7/12/2011 PASS
DetailsSteven Webb
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC11-00473
Routing - PLAN CHECK7/12/2011 7/12/2011 PASS
DetailsPerry Paine
Perry
Case Summary (BLD)  7/12/2011  
Inspection Record Card- Bld  7/12/2011  
1st review completed  7/12/2011 DONE
PLANS/APPL TAKEN TO FRONT DESK  7/12/2011  
Permit Ready to Issue  7/12/2011 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  7/12/2011 DONE
DetailsTisha Gallop
Routing Walk-In (BLD)7/8/20117/8/20117/11/2011PDONE
DetailsTisha Gallop
Routing Walk-In (PW Hillside)7/8/20117/8/20117/8/2011PPASS
Details
Footing subgrade must be approved by the applicants geotechnical engineer prior to scheduling footing inspection
Routing Walk-In (Zoning)7/8/20117/8/20117/8/2011PPASS
DetailsColleen T Carroll
Application received 7/8/2011