Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD11-01743
StatusFinaled
Name MORGAN CONSTRUCTION
Site Address 782 S AMERICANA BLVD
Project NameSummit Dental Office
Customer Number 
ePlanReviewNo
Description
Summit Dental Office - PLAN MOD Resubmittal 10-12-11 new structural plan sheets S0.01, S1.01, S4.01, S5.01, S5.02, S6.01, S6.02, GEOTECH FOUNDATION RECOMMENDATIONS CHANGING CAISONS TO MICRO PILE FOUNDATION SUPPORT SYSTEM. DRS To construct a new 7,950 square foot, two story wood framed dental office building and related site improvements. First Floor: 7,465 sq. ft., Second Floor: 485 sq. ft.. This building will be fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/24/201210/5/2012 DONE
Second Notice 9/3/20129/19/2012 DONE
DetailsChristina Prado
faxed 9-19
First Notice 8/5/20128/24/2012 DONE
Routing - PLUMBING7/27/2012 7/27/2012 PASS
DetailsBill VanDegrift
recieved copy of revised med gas system
Permanent Occupancy  7/26/2012 DONE
BLD-Final7/24/20127/25/20127/25/2012APART
DetailsDave Hannah
As late as possible Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey ok for temp occ ok for perm occ after plumbing gos perm
Zoning Approval7/25/20127/25/20127/25/2012 PASS
DetailsJosh Wilson
PubWorks Occupancy Approval7/23/20127/23/20127/23/2012 DONE
DetailsTiffany Lowery
FIRE-Final Inspection7/19/20127/20/20127/20/2012APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection7/18/20127/19/20127/19/2012PFAIL
DetailsTroy Cobbley
Provide signage on the riser/facp door and provide the missing exit signs as per the approved plans. One exit sign did not function.
FIRE-Final Inspection7/18/20127/18/20127/18/2012APART
DetailsForrest France
Project related fire alarm and sprinkler permits finaled.
BLD-Conference7/17/20127/17/20127/18/2012PDONE
DetailsDave Hannah
Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey
BLD-Conference6/21/20126/22/20126/25/2012PPASS
DetailsDave Hannah
As early as possible Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey ceiling grid ok to cover
BLD-Conference6/20/20126/21/20126/21/2012ADONE
DetailsDave Hannah
As early as possible Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey talked about ada sales counter
FIRE-Sprinkler Rough-in6/14/20126/14/20126/14/2012PPART
DetailsForrest France
Overhead fire sprinkler work at the grid ceilings approved for cover.
BLD-Other6/1/20126/4/20126/4/2012ANR
DetailsDave Hannah
Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey
FIRE-Conference5/15/20125/15/20125/15/2012PDONE
DetailsForrest France
Regarding door at the sprinkler riser room.
FIRE-Sprinkler Rough-in4/27/20124/27/20124/27/2012APART
DetailsForrest France
Okay to cover sprinklered concealed spaces as discussed.
BLD-Footing4/27/20124/27/20124/27/2012PPASS
DetailsDave Hannah
As early as possible Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey
BLD-Conference4/26/20124/26/20124/26/2012APASS
DetailsDave Hannah
Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey
BLD-Energy code compliance4/12/20124/13/20124/13/2012APASS
DetailsDave Hannah
Call prior to going Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey ok to cover walls
BLD-Conference3/23/20123/26/20123/26/2012ADONE
DetailsDave Hannah
Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey
BLD-Framing/Rough-in3/16/20123/19/20123/20/2012APART
DetailsDave Hannah
Jason Ivey Phone #: ###-#### >> Inspection requested via web by Mattie Botero ok to insulate ceiling trusses and roof framing ok
FIRE-Sprinkler Rough-in3/19/20123/19/20123/19/2012APART
DetailsForrest France
Dry system rough-in inspection completed. Discussed protection for combustible concealed spaces and allowable exceptions per NFPA 13.
BLD-Framing/Rough-in3/3/20123/5/20123/5/2012APART
DetailsDave Hannah
Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey ok to cover ext
BLD-Framing/Rough-in2/26/20122/27/20122/27/2012PPART
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Scott Hawker. Roof nailing only ok to cover.
BLD-Foundation1/23/20121/23/20121/23/2012PPART
DetailsDave Hannah
Russ Phone #: ###-#### ok to pour columns
BLD-Footing1/11/20121/11/20121/11/2012PPASS
DetailsDave Hannah
Call prior to going Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey column ftgs ok to pour
BLD-Conference1/9/20121/10/20121/10/2012ADONE
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Scott Hawker
BLD-Foundation1/9/20121/10/20121/10/2012ACANC
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Scott Hawker
BLD-Footing1/9/20121/10/20121/10/2012APASS
DetailsDave Hannah
As early as possible Phone #: 2085712169 >> Inspection requested via mobile web by jason ivey column pads ok
BLD-Foundation11/16/201111/16/201111/16/2011PPASS
DetailsDave Hannah
ivey - pouring at noon Phone #: ###-#### ok to place concrete for foundation and int pads
BLD-Foundation11/10/201111/14/201111/14/2011APART
DetailsDave Hannah
Jeff Phone #: ###-#### crews are still tieing rebar that they have in is ok spec inspection will sign off the finished project
BLD-Footing11/4/201111/4/201111/4/2011PPART
DetailsDave Hannah
Jeff Phone #: ###-####
Override - Parcel Holds  11/3/2011  
Print Pending Permit.LaserJet4  11/3/2011  
PLANS/APPL TAKEN TO FRONT DESK  11/3/2011 PASS
Details
Plan Mod plan review changing use of concrete caisons to micro piles approved.
Print Occupancy Form  11/3/2011 DONE
Override - Parcel Holds  11/3/2011  
Permit Ready to Issue  11/3/2011 DONE
DetailsChristina Prado
CHANGE STATUS TO (ISS)  11/3/2011 DONE
DetailsChristina Prado
Routing - PLAN CHECK10/12/2011 11/1/2011 PASS
DetailsDan Stuart
11-1-11 - Received PDF copy of new Micro Pile Schedule 3/S4.01 and attached to plans over old schedule. New sheet included minimum depth for each micro pile.
10/13/11 - Reviewed resubmitted plans. Three full sets of structural drawings were submitted. In review to insert new sheets into original plans show that only Sheets S0.01, S1.01, S4.01, S5.01, S5.02, S6.01 & S6.02 WERE THE ONLY SHEETS WITH CHANGES FOR REVISION 2. Removed sheets without changes and inserted only plan sheets with changes.
10/20/11 - Received Addendum #3 - Foundation Recommendation report from MTI, David O. Cram, P.E. Addendum indicated soil type and coresponding soil-grout bond stress for layer thickness. Copy of report e-mailed to outside structural plan reviewer.
10/26/11 - Insufficient infromation provided per discussion with structural plan review engineer. Sent copy of e-mail for additional information to design architect on 10-26-11 for response.
10/28/11 - Received geotech design data for micro pile number and minimum depth of pile for each support. Forwarded copy to outside structural engineer for review.
11/1/11 - Received letter from contract strcutural engineer approving submitted design data for use of micro piles.
Routing Off Site - STRUCTURAL10/28/2011 11/1/2011 PASS
DetailsDan Stuart
Final report from outsource strcutural plan review approved submitted geotech data for Micro Piles.
Telephone call  11/1/2011 DONE
Call to Dan Tonning, Lochsa Engineering, to request a new Table 3/S4.01 to include the minimum depth of each micro pile based on the geotech report provided on 10/28/11.
Plan resubmittals received  11/1/2011 DONE
Received e-mail with new Detail 3/S4.01 specifying minimum depth of each micro-pile in the Micro Pile Schedule.
Plan resubmittals received  10/28/2011 DONE
DetailsTisha Gallop
received three copies of response and revised calcs; taken to Dan Stuart
Plan Reviewer's activity  10/28/2011 DONE
Sent PDF copy of Geo Tech Structural Design Data Resubmittals of 10-28-11, in response to outside structural plan review of 10-25-11, to structural plan review engineer for re-review.
Plan resubmittals requested  10/25/2011 DONE
Attached cover letter and forwarded e-mail copy of strcutural plan review comments to architect Steve Simmons for response.
Plan resubmittals received  10/20/2011  
Received 1 copy of cover transmittal from LCA Architects dated 10-20-11, 3 copies of calcs for addedum of foundation, taken to Dan Stuart
Plan resubmittals requested  10/14/2011 DONE
E-mailed copy of Plan Mod Structural Review comments to architect.
Telephone call  10/14/2011 DONE
Called and talked with Steve Simmons, architect, to let him know I had sent a copy of outside strcutural review comments for the Plan mod to him this morning. I ask him for a copy of the last resubmittal response to the original strcutural plan review for our records.
Routing Off Site - STRUCTURAL10/12/2011 10/13/2011 FAIL
DetailsChristina Prado
Called action couriers for pick up.
10-13-11 Received structural plan review comments for plan mod. Resubmittals requireed. Copy of review e-mailed to architect.
Telephone call  10/13/2011 DONE
Called contractor Scott Hawker, Morgan Construction and ask for new certificate of value to show the indicated cost reduction of $30,000.00 shown on plan mod application. Scott indicated to leave the original C.V. and at the end of the job when the audit is done they will address at that time if there are changes.
Plan Modification Accepted  10/12/2011 DONE
DetailsChristina Prado
Received three sets of plans marked S0.01, S1.01, S4.01, S5.01, S5.02, S6.01, S6.02, the actual structural plan sheets with changes. drs As well as three sets of structural calcs. Taken to Dan Stuart for review.
Issue PAID IN FULL permit  9/15/2011 DONE
DetailsChristina Prado
Routing - PLAN CHECK9/9/2011 9/12/2011 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  9/12/2011 DONE
DetailsJohn Menard
Print Occupancy Form  9/12/2011 DONE
Permit Ready to Issue  9/12/2011 DONE
DetailsTisha Gallop
Telephone call  9/12/2011 DONE
DetailsTisha Gallop
called Steve Simmons and told him permit fees are due and need ACHD.
Plan assigned to (JCM)7/25/2011 9/12/2011 PASS
DetailsJohn Menard
Routing - PLAN CHECK9/6/2011 9/9/2011  
DetailsJohn Menard
Plan resubmittals received  9/9/2011 DONE
9-9-11 received 2 copies of sheets L-2., C5.2 inserted by Scott Wendell
Routing - Design Review9/9/2011 9/9/2011 PASS
DetailsJosh Wilson
New exterior door ok per resubmittals. JGW 9-9-11
Route to Impact Fee Review8/31/20119/6/20119/8/2011 PASS
DetailsCindy M. Gould
Plan Reviewer's activity  9/8/2011 PASS
DetailsJohn Menard
Reviewed and approved plan revisions. JCM
Plan resubmittals received  9/7/2011 DONE
DetailsChristina Prado
Received one copy of transmittal letter and DRH letter and two sets of plans- A0.1, A0.3, A2.1, A2.2, A3.0, A4.2, A5.0 & E2.1L. Inserted by Arch Rep and given to John Menard for review
Routing - FIRE8/31/20118/31/20119/6/2011 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  9/6/2011 FAIL
Failed Public Works,Plan Check
Plan resubmittals requested  8/31/2011 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Plan Reviewer's activity  8/31/2011 PASS
DetailsJohn Menard
Reviewed and approved structural revisions. JCM
Routing - PLAN CHECK8/23/2011 8/31/2011 FAIL
DetailsJohn Menard
Plan resubmittals received  8/24/2011  
Received 1 copy of response letter dated 8-23-11 from Dan Tonning, 1 copy of structural cals, dated 8-15-11, 1 copy of addendum #1 Fondation Recommendations, 1 copy of Addendum #2 Foundations Recomendations, 3 copies of sheets S0.01, S0.02, S1.01, S4.01, S5.01 Inserted into plans by architects office then taken back to John Menards office/BAS
Routing PW Drainage8/22/2011 8/23/2011 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS8/17/2011 8/23/2011 PASS
DetailsBeverly Mountain
Plan resubmittals requested  8/17/2011 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Routing - PLAN CHECK8/11/2011 8/17/2011  
DetailsJohn Menard
Plan resubmittals received  8/16/2011 DONE
DetailsChristina Prado
Received two sets of storm calcs and five sets of plans C4.2, C5.1, C5.2 & C6.1. Inserted by engineer and taken back to John Menard for review
Routing Off Site - STRUCTURAL7/25/2011 8/15/2011 FAIL
DetailsJohn Menard
7-25-11 called Action Couriers for pick up
Routing - PLANNING8/10/2011 8/11/2011 PASS
DetailsJosh Wilson
OK per DRH11-00072. See redlines sheet L-2.
Routing - PLUMBING8/9/2011 8/10/2011 PASS
DetailsDaryl Spivey
Per plans and 2003 UPC.
Routing - Erosion and Sediment8/8/2011 8/9/2011 PASS
DetailsSteven Webb
ESC plan is approved according to the ESC plan and permit conditions. ESC11-00522
Routing PW Sewer Rating8/5/2011 8/8/2011 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste  8/8/2011 PASS
DetailsPeter J. McCullough
Routing - PUBLIC WORKS7/26/2011 8/8/2011 FAIL
DetailsConnie Baumgartner
Failed by Brian Murphy ###-####
Routing PW Street Lights8/5/2011 8/5/2011 PASS
DetailsMike D Hedge
Plan resubmittals received  8/5/2011  
Received 2 copies of sheets E0.0 & E1.0 and inserted into plans by public works
Routing PW Sewer Design7/26/2011 7/27/2011 PASS
DetailsJon R. Gunnerson
Sewer Tap permit required
Routing - Addressing7/26/2011 7/26/2011 PASS
DetailsTerry Records
Plan routing begun/NEW & ADDTN  7/26/2011 DONE
Routing - PLANNING Land Div7/26/2011 7/26/2011 PASS
DetailsDave Abo
Parcel B on ROS10-00031 (Minor Land Division)
Recd Pcfee & Taken To Pln CK  7/25/2011  
Pending Assignment by JCM7/25/2011 7/25/2011 DONE
DetailsJohn Menard
Routing PW Drainage  8/5/2001 FAIL
DetailsBrian Murphy
GROUND WATER SEPERATION
Application received 7/25/2011