Print Statement | | | 3/8/2012 | | DONE |
|
|
|
|
Second Notice | | 2/27/2012 | 3/1/2012 | | DONE |
|
|
|
|
First Notice | | 2/12/2012 | 2/17/2012 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/2/2012 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 11/21/2011 | 11/22/2011 | 11/22/2011 | A | PASS |
Dave Hannah
|
|
|
matthew Phone #: ###-####
|
BLD-Final | 11/7/2011 | 11/8/2011 | 11/8/2011 | A | PART |
Dave Hannah
|
|
|
Matthew Phone #: ###-#### ok for temp occ needs to finish plumbing
|
BLD-Final | 11/3/2011 | 11/4/2011 | 11/4/2011 | A | PART |
Dave Hannah
|
|
|
matthew Phone #: ###-#### needs to get fire final and finish plumbing
|
FIRE-Final Inspection | 11/3/2011 | 11/4/2011 | 11/4/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety passed pending signage at the main entry/exit and removal of the manual thumbturn. To be completed prior to structural final as discussed.
|
FIRE-Final Inspection | 11/2/2011 | 11/3/2011 | 11/3/2011 | A | NR |
Forrest France
|
|
|
Missing signage at the main entry/exit, remove manual thumbturn at the storefront door, post permanent suite address, missing SD at the electrical room for the new fire alarm NAC panel.
|
BLD-Framing/Rough-in | 10/19/2011 | 10/20/2011 | 10/20/2011 | A | PASS |
Dave Hannah
|
|
|
perry - ceiling grid Phone #: ###-####
|
BLD-Framing/Rough-in | 10/4/2011 | 10/4/2011 | 10/5/2011 | P | PART |
Dave Hannah
|
|
|
perry Phone #: ###-#### ok to cover plumbing wall
|
BLD-Framing/Rough-in | 9/8/2011 | 9/8/2011 | 9/9/2011 | P | DONE |
Dave Hannah
|
|
|
Perry Phone #: ###-####
|
BLD-Framing/Rough-in | 9/8/2011 | 9/9/2011 | 9/9/2011 | A | PART |
Dave Hannah
|
|
|
Perry Phone #: ###-#### ok to cover all but plumbing walls
|
Issue PAID IN FULL permit | | | 9/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (TLW) | | | 8/31/2011 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 8/31/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 8/31/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/31/2011 | | DONE |
|
|
|
|
Telephone call | | | 8/31/2011 | | DONE |
|
|
|
8-31-11 called left message for Matthew permit ready and fee given ///dld
|
Routing - PLAN CHECK | 8/30/2011 | | 8/30/2011 | | PASS |
Tim L. Woodard
|
|
|
Approved.
|
Plan resubmittals received | | | 8/25/2011 | | DONE |
Christina Prado
|
|
|
Received on response leter and three sets of plans A5.0. Given to Tim Woodard for additional review
|
Plan resubmittals received | | | 8/23/2011 | | |
|
|
|
Received 1 cover letter, from Matthew Witt dated 8-16-11 to Tim Woodard, 3 copies of sheet A2.0 and taken to Tim Woodard//BAS
|
1st review completed | | | 8/9/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 8/4/2011 | | 8/9/2011 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 8/2/2011 | | 8/4/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 8/3/2011 | | 8/4/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 8/3/2011 | | 8/3/2011 | | PASS |
Terry Records
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/2/2011 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/2/2011 | | DONE |
Christina Prado
|
|
|
|
Application received | | 8/2/2011 | | | |
|
|
|
|