Case Summary (BLD) | | | 9/25/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/12/2012 | | DONE |
Sam Zahorka
|
|
|
|
Third Notice | | 3/30/2012 | 3/16/2012 | | DONE |
|
|
|
|
Third Notice | | 3/15/2012 | 3/15/2012 | | DONE |
|
|
|
faxed to Todd Campbell Const
|
Third Notice | | 1/22/2012 | 3/1/2012 | | DONE |
|
|
|
faxed to Todd Campbell Const.
|
Second Notice | | 1/13/2012 | 1/17/2012 | | DONE |
Christina Prado
|
|
|
faxed 1-17-2012
|
First Notice | | 1/1/2012 | 1/3/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/22/2011 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/22/2011 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/15/2011 | 12/15/2011 | 12/15/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 12/15/2011 | 12/15/2011 | 12/15/2011 | P | PASS |
Tom Arcoraci
|
|
|
Ammon-as late as possible please Phone #: ###-#### ok for perm occ unused area ropped off at this time
|
BLD-Other | 12/12/2011 | 12/12/2011 | 12/12/2011 | P | DONE |
Tom Arcoraci
|
|
|
No access posted do not occupy.
|
BLD-Conference | 12/7/2011 | 12/8/2011 | 12/8/2011 | A | DONE |
Jim Sly
|
|
|
ammon Phone #: ###-####
|
FIRE-Final Inspection | 12/7/2011 | 12/8/2011 | 12/8/2011 | A | FAIL |
Troy Cobbley
|
|
|
Resubmitt plans showing the actual floor layout, mount and tag fire extinguisher as marked on the plans, provide approved door hardware as marked on the plans, provide missing exit signs as marked on the plans and repair the emergency light as marked on the plans.
|
CHANGE STATUS TO (ISS) | | | 12/7/2011 | | DONE |
Tisha Gallop
|
|
|
picked up and paid for plan mod
|
Plan assigned to (CJW) | 11/22/2011 | 11/22/2011 | 11/23/2011 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 11/22/2011 | | 11/23/2011 | | PASS |
Carl Westfall
|
|
|
Reviewed and approved Plan Modification.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/23/2011 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/23/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/23/2011 | | DONE |
|
|
|
|
Telephone call | | | 11/23/2011 | | DONE |
|
|
|
11-23-11 called Ammon permit ready and fee given ///dld
|
Plan Modification Accepted | | | 11/22/2011 | | DONE |
Tisha Gallop
|
|
|
Plan modification accepted for Bld11-01835 (Idaho Aquarium) for walls added in exhibition #1 to accomodate for a pump room for the display aquarium; submitted on plan sheets A2.1, A3.1 and revised cert of value; routed to Carl Westfall.
|
BLD-Framing/Rough-in | 11/8/2011 | 11/8/2011 | 11/8/2011 | P | PART |
Tom Arcoraci
|
|
|
ammon Phone #: ###-####
|
Case Summary (BLD) | | | 11/7/2011 | | |
|
|
|
|
BLD-Footing | 9/14/2011 | 9/14/2011 | 9/14/2011 | P | PART |
Mike Jordan
|
|
|
Ammon Phone #: ###-####. Informed that contractor will need special inspection.
|
Print Occupancy Form | | | 9/14/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/14/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/14/2011 | | DONE |
Tisha Gallop
|
|
|
called Todd Campbell and told him permit is ready, fees and need Mechanical initial value.
|
Issue PAID IN FULL permit | | | 9/14/2011 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 9/8/2011 | | 9/13/2011 | | PASS |
Scott Arellano
|
|
|
Attached revised IFC comments to plans
|
Routing - PLUMBING | | | 9/13/2011 | | DONE |
|
|
|
It was decided by Bill Vandegrift that plumbing plans were not required.
|
Routing - PLAN CHECK | 9/13/2011 | | 9/13/2011 | | PASS |
Carl Westfall
|
|
|
Structural calculations received on September 12. Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2011 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/4/2011 | | 9/13/2011 | | PASS |
Carl Westfall
|
|
|
IDAHO AQUARIUM
|
Routing - PLAN CHECK | 9/1/2011 | | 9/8/2011 | | FAIL |
Carl Westfall
|
|
|
Waiting for call from the Structural Engineer to discuss how the concrete slab will perform with aquarium walls attached to it.
|
Routing - PLAN CHECK | 8/31/2011 | | 9/1/2011 | | FAIL |
Carl Westfall
|
|
|
Completed the 3rd review. Need an engineered design.
|
Routing - PLAN CHECK | 8/29/2011 | | 8/31/2011 | | FAIL |
Carl Westfall
|
|
|
Completed the 2nd review. Items not resolved.
|
Routing - FIRE | 8/24/2011 | 8/24/2011 | 8/29/2011 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
Plan resubmittals received | | | 8/29/2011 | | DONE |
Christina Prado
|
|
|
Received three copies of response letter and plans A0.1, A2.1, A3.1 & A4.1. Routed to Carl Westfall for aditional review
|
1st review completed | | | 8/29/2011 | | FAIL |
|
|
|
Failed Plumbing, Plan Check, Fire
|
Route to Impact Fee Review | 8/24/2011 | 8/29/2011 | 8/24/2011 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 8/12/2011 | | 8/24/2011 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on August 22, 2011 and finished on August 24, 2011. Revised drawings and additional information were required. See the plan review report.
|
Routing - Design Review | 8/11/2011 | | 8/12/2011 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - parking ok
|
Routing - PLUMBING | 8/5/2011 | | 8/8/2011 | | FAIL |
Bill VanDegrift
|
|
|
1. Provide a complete plumbing plan showing all waste, water and vent piping with sizing and connections to existing plumbing per 2003 UPC.
|
Routing - MECHANICAL | 8/8/2011 | | 8/8/2011 | | PASS |
Troy James
|
|
|
Mechanical plan needed - ventilation?
Mechanical review not required. Ventilation system is required to remove the latent load.
|
Routing PW Sewer Rating | 8/5/2011 | | 8/5/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 8/4/2011 | | 8/5/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Plan Reviewer's activity | | | 8/4/2011 | | DONE |
Jason Blais
|
|
|
Emailed architect letting him know to contace ACHD for evaluation of impact fees. Written verification from ACHD will need to be provided prior to the building permit being issued.
|
Pending Assignment by JCB | 8/2/2011 | | 8/4/2011 | | DONE |
Jason Blais
|
|
|
|
Application received | | 8/2/2011 | 8/2/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/2/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/2/2011 | | DONE |
Tisha Gallop
|
|
|
|