Routing PW Sewer Rating | 8/11/2011 | | 12/16/2014 | | PASS |
Beverly Mountain
|
|
|
|
Case Summary (BLD) | | | 11/17/2014 | | DONE |
|
|
|
|
Meeting | | | 11/17/2014 | | DONE |
Sam Zahorka
|
|
|
Met with Mr. Scot McGavin about a possible change to the front 280 SF room from office use to daycare. I requested him to submit a letter describing the age and number of children proposed for this room. I also requested him to submit a T.I. when he is ready to make this partial occupancy change. I walked him over to Planning and Zoning and requested he check with the City Clerk to modify his business license due to the occupant load change. Alterations for building code compliance will be required for this change. I made him aware of this and let him know a T.I. is required.
|
Plan Reviewer's activity | | | 7/25/2013 | | DONE |
Sam Zahorka
|
|
|
The basment was permitted and approved for a Single Family Dwelling under BLD1027217. This permit only changed the occupancy for the upstairs from a Business occupancy to an Educational Occupancy. The Occupancy card was revised to show the approved R-3 occupancy in the Basement. Updated occupancy card emailed to Scott Mcgavin the building owner and Gordon with Boise Fire. SRZ
|
Permanent Occupancy | | | 7/25/2013 | | DONE |
Tisha Gallop
|
|
|
reprinted cert of occ to include the R occupancy in the basement.
|
Telephone call | | | 7/25/2013 | | DONE |
Sam Zahorka
|
|
|
Called Gordon the Fire inspector and informed him of the new occupancy card that includes the approved Single Family Dwelling in the basement of this building.
|
Case Summary (BLD) | | | 12/5/2012 | | |
|
|
|
|
Third Notice | | 1/22/2012 | 1/31/2012 | | DONE |
Christina Prado
|
|
|
Done 1-31-12
|
Second Notice | | 12/30/2011 | 1/17/2012 | | DONE |
Christina Prado
|
|
|
mailed 1-18-2012
|
First Notice | | 12/19/2011 | 12/20/2011 | | DONE |
Christina Prado
|
|
|
mailed 12-21-2011
|
Plan Reviewer's activity | | | 12/9/2011 | | DONE |
Sam Zahorka
|
|
|
Received CUP11-00064 / 5405 W. Overland Road from applicant. This approval increased the occupant load to a maximum of 45. Attached the CUP to documents, issued a new certificate of occupancy with the name change and new occupant load.
|
Meeting | | | 12/9/2011 | | DONE |
Tisha Gallop
|
|
|
at issuance of permanent occupancy correct name of business is "Puentes Language Programs" dba "Puentes Spanish Preschool". Architect submitted plans with just the owner's last name with daycare.
|
Case Summary (BLD) | | | 12/9/2011 | | DONE |
Tisha Gallop
|
|
|
|
Change Expiration Date Only | | | 11/17/2011 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 11/7/2011 | 11/8/2011 | 11/8/2011 | P | PASS |
Tom Arcoraci
|
|
|
TRUDY-PLEASE CALL PRIOR TO INSPECTION Phone #: ###-####
|
BLD-Final | 9/30/2011 | 9/30/2011 | 9/30/2011 | P | PART |
Tom Arcoraci
|
|
|
ok for temp occ needs to finish bath rooms
|
FIRE-Final Inspection | 9/30/2011 | 9/30/2011 | 9/30/2011 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 9/29/2011 | 9/30/2011 | 9/30/2011 | A | FAIL |
Troy Cobbley
|
|
|
Provide smoke detector at the north exit as per plans and provide the required exit sign/emergency lighting and exit discharge lighting per plans. Per Sam the exit signs in the classrooms can be deleted since the occupant load does not exceed 10.
|
Temporary Occupancy UNPAID FEE | | | 9/30/2011 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Conference | 9/27/2011 | 9/28/2011 | 9/28/2011 | A | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with Trudy. One smoke alarm needs to be added at the bottom of the stairs. Also per Sam exit discharge lighting and interior emergency lighting is required.
|
Zoning Approval | 9/28/2011 | 9/28/2011 | 9/28/2011 | | PASS |
Josh Wilson
|
|
|
Ok Dave Moser and Josh Wilson
|
BLD-Framing/Rough-in | 9/20/2011 | 9/21/2011 | 9/21/2011 | A | NR |
Tom Arcoraci
|
|
|
scott Phone #: ###-####
|
BLD-Framing/Rough-in | 9/20/2011 | 9/21/2011 | 9/21/2011 | P | PART |
Tom Arcoraci
|
|
|
ok pending ok of cant beam
|
BLD-Conference | 9/15/2011 | 9/16/2011 | 9/16/2011 | P | PASS |
Tom Arcoraci
|
|
|
|
Telephone call | | | 9/12/2011 | | DONE |
|
|
|
t/c w scott - permit ready and fees given
|
Permit Ready to Issue | | | 9/12/2011 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/12/2011 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/12/2011 | | DONE |
Christina Prado
|
|
|
|
Case Summary (BLD) | | | 9/9/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/9/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 9/9/2011 | | 9/9/2011 | | PASS |
Sam Zahorka
|
|
|
|
Plan assigned to (SRZ) | 8/23/2011 | | 9/9/2011 | | PASS |
Sam Zahorka
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 9/7/2011 | | DONE |
Sam Zahorka
|
|
|
Project Dox / ePlan review - Received uploaded plan submittal sheets: SP1.0, LSP0.1, ASC0.0, A5.0, A3.0, A2.2, and 4 small docs. ACHD, Engineering letter, Structural load doc, and Day care load doc.
|
Routing - PLAN CHECK | 8/23/2011 | | 8/30/2011 | | FAIL |
Sam Zahorka
|
|
|
Corrections sent to Architect.
|
Case Summary (BLD) | | | 8/25/2011 | | DONE |
|
|
|
|
Routing - PLANNING | 8/11/2011 | | 8/23/2011 | | PASS |
David Moser
|
|
|
David Moser - CAA11-00131
|
1st review completed | | | 8/23/2011 | | FAIL |
|
|
|
Failed Plan Check
|
Plan assigned to (DRS) | 8/11/2011 | | 8/23/2011 | | DEFR |
Dan Stuart
|
|
|
Plan reassigned to Sam Zahorka.
|
Routing - PLAN CHECK | 8/11/2011 | | 8/23/2011 | | DEFR |
Dan Stuart
|
|
|
Plan reassigned to Sam Zahorka.
|
Routing - FIRE | 8/23/2011 | | 8/23/2011 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
Routing - PUBLIC WORKS | 8/11/2011 | | 8/22/2011 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 8/11/2011 | | 8/16/2011 | | PASS |
Josh Wilson
|
|
|
Josh Wilson- CZC11-00178- ok per redlines sheet SP1.0
|
Routing - Erosion and Sediment | 8/11/2011 | | 8/15/2011 | | PASS |
Steven Webb
|
|
|
ESC11-00577 plan waiver approved with conditions attached to the permit.
|
Routing - Addressing | 8/11/2011 | | 8/12/2011 | | PASS |
April Wing
|
|
|
Address changed from 5405 W Overland Rd to 1605 S Phillippi St
|
Pending Assignment by JCB | 8/10/2011 | | 8/11/2011 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 8/10/2011 | | FAIL |
Tim L. Woodard
|
|
|
Intake failed due to missing items required by the submittal checklist. TLW
|
Intake Approval | | | 8/10/2011 | | PASS |
Tim L. Woodard
|
|
|
After a discussion with Jason it was decided to approve the intake after the acitivities that are neccessary from Stan Cole are completed. This is a pilot poject and all additional items will be called by the plan reviewer during the review. TLW
|
Telephone call | | | 8/10/2011 | | DONE |
|
|
|
sent email to stan cole regarding plan check fee payment
|
Application received | | 8/8/2011 | | | |
|
|
|
|