BLD-Final | 11/22/2011 | 11/22/2011 | 11/22/2011 | P | PASS |
Tom Arcoraci
|
|
|
Andy Phone #: ###-####
|
DOC - Permit Finaled | 11/22/2011 | 11/22/2011 | 11/22/2011 | P | PASS |
Tom Arcoraci
|
|
|
|
Zoning Approval | 11/7/2011 | 11/7/2011 | 11/7/2011 | | PASS |
Sarah Schafer
|
|
|
|
BLD-Energy code compliance | 10/6/2011 | 10/7/2011 | 10/7/2011 | A | PASS |
Tom Arcoraci
|
|
|
Andy Phone #: ###-####
|
BLD-Framing/Rough-in | 10/5/2011 | 10/5/2011 | 10/5/2011 | P | PASS |
Tom Arcoraci
|
|
|
andy Phone #: ###-####
|
BLD-Foundation | 8/30/2011 | 8/31/2011 | 8/31/2011 | P | PASS |
Tom Arcoraci
|
|
|
shane Phone #: ###-####
|
BLD-Footing | 8/29/2011 | 8/30/2011 | 8/30/2011 | P | PASS |
Tom Arcoraci
|
|
|
shane Phone #: ###-####
|
BLD-Footing | 8/29/2011 | 8/29/2011 | 8/29/2011 | P | NR |
Tom Arcoraci
|
|
|
Wes ###-#### or Andy ###-####
|
OVERRIDE | | | 8/29/2011 | | |
|
|
|
|
Plan assigned to (CDM) | 8/9/2011 | 8/9/2011 | 8/29/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/24/2011 | | 8/29/2011 | | PASS |
Carl D Madsen
|
|
|
|
Issue PAID IN FULL permit | | | 8/29/2011 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 8/29/2011 | | DONE |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 8/29/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/29/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/26/2011 | | DONE |
|
|
|
8-26-11 2 copies of sheet A5 sent to Carl M.
|
Routing - PLANNING | 8/24/2011 | | 8/24/2011 | | PASS |
Andrea Tuning
|
|
|
The plans have been redlined.
|
1st review completed | | | 8/23/2011 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/16/2011 | | 8/23/2011 | | FAIL |
Carl D Madsen
|
|
|
Exterior deck section detail required. Call Andy Thompson 8-23-11 CDM
|
Route to Impact Fee Review | 8/8/2011 | 8/11/2011 | 8/17/2011 | | PASS |
Cindy M. Gould
|
|
|
Credit given for fees paid on PRK08-00202
|
Routing - MECHANICAL | 8/16/2011 | | 8/16/2011 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 8/15/2011 | | 8/15/2011 | | FAIL |
Troy James
|
|
|
emailed corrections to ultimate heating
|
Routing - Addressing | 8/9/2011 | | 8/10/2011 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 8/10/2011 | | 8/10/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 8/10/2011 | | 8/10/2011 | | FAIL |
Andrea Tuning
|
|
|
The applicant has not met the conditions of approval per DRH11-00169/170. Satff is unable to "redline" plans that are already redlined and not to scale. Staff contacted the applicant on 8-10-11 and explained a new site and landscape plan must be submitted that includes all of the required conditions of approval and does not contain redlines.
|
Plans ACCEPTED BY PLAN TECH | | | 8/9/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 8/9/2011 | | PASS |
Barbara Stitt
|
|
|
|
Application received | | 8/8/2011 | 8/8/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 8/8/2011 | | FAIL |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/8/2011 | | DONE |
Barbara Stitt
|
|
|
|
Routing - MECHANICAL | 8/10/2011 | | | | FAIL |
Troy James
|
|
|
waiting on manual J resubmittal
|