Permit Information
Permit NumberBLD11-01987
StatusFinaled
Name WILLIAMS SCOTSMAN INC
Site Address 301 N ROOSEVELT ST
Project NameVILLAGE CHARTER SCHOOL
Customer Number 
ePlanReviewNo
Description
***GREEN TAG*** (THE VILLAGE CHARTER SCHOOL - RELOCATE/CHANGE OCCUPANCY PORTABLE #2 BUILDING) - Relocate a 1,420 square foot portable school classroom, that was last approved by the State of Idaho Tag #10478CC as a Type V-B Construction, "E" occupancy use group, to this new location AND CHANGE THE OCCUPANCY to an A3 occupancy for use as a P.E. and Band room. Scope of work includes set up and anchoring per engineering & plans; to construct a new wood ramp, platform, stairs, handrails and edge protection systems providing shared accessibility access compliance for two relocatable classrooms; provide panic hardware; provide a second door with header per engineering; mechanical work and electrical work. See BLD11-01985 for 1st relocatable. There are no plumbing facilities in this unit. An existing accessible route from this relocated unit to the existing Multi-Purpose Building will provide access to existing restrooms facilities for students and staff. All work per the approved plans, Engineering, and all other reviewing agencies approvals. A new Certificate of Occupancy with the new occupant load total is to be issued when completed and approved. The occupant load for this building is 95 and shall be posted in a conspicuous place per IBC section 1004.3. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 10/1/201210/17/2012 DONE
Print Statement  10/17/2012 DONE
DetailsTisha Gallop
mailed
Second Notice 8/11/20129/26/2012 DONE
faxed
First Notice 7/26/20128/1/2012 DONE
Permanent Occupancy  7/16/2012 DONE
DetailsBarbara Stitt
BLD-Final7/11/20127/11/20127/11/2012PPASS
DetailsTom Arcoraci
mike please call 20 min before going out Phone #: ###-####
Change Expiration Date Only  6/6/2012 DONE
DetailsBarbara Stitt
Ok per Jason to extend temp occupancy 1 month//6-5-12//BAS
BLD-Aging Inspection6/5/20126/5/20126/5/2012 PEND
DetailsTom Arcoraci
Zoning Approval5/22/20125/22/20125/22/2012 PASS
DetailsSue Cummings
Change Expiration Date Only  4/13/2012 DONE
DetailsBarbara Stitt
BLD-Aging Inspection4/3/20124/3/20124/3/2012 PASS
DetailsTom Arcoraci
Temporary Occupancy3/21/20126/19/20123/21/2012 DONE
DetailsBarbara Stitt
Temp occupancy extension granted per Jason Blais see scaned documents//BAS
Override - Parcel Holds  3/21/2012  
BLD-Aging Inspection1/31/20121/31/20122/1/2012 PEND
DetailsTom Arcoraci
on temp
Temporary Occupancy12/21/20114/23/201212/21/2011 DONE
DetailsBarbara Stitt
Override - Parcel Holds  12/21/2011  
Change Expiration Date Only  12/8/2011 DONE
DetailsBarbara Stitt
FIRE-Final Inspection11/30/201111/30/201111/30/2011PPASS
DetailsTroy Cobbley
life safety passed
Override - Parcel Holds11/30/20111/1/190011/30/2011  
this is for the fire final only
Change Expiration Date Only  11/17/2011  
DetailsBarbara Stitt
BLD-Final11/3/201111/3/201111/3/2011AFAIL
DetailsBob Archibald
Need ACHD fees paid before final occupancy
Override - Parcel Holds  11/3/2011  
BLD-Other10/25/201110/25/201110/25/2011PPASS
DetailsTom Arcoraci
teresa - ramp Phone #: ###-####
BLD-Final10/25/201110/25/201110/25/2011PPART
DetailsTom Arcoraci
ok for temp occ c/n posted for handrail issue
Temporary Occupancy10/25/20111/23/201210/25/2011 DONE
DetailsBarbara Stitt
Override - Parcel Holds10/25/20111/1/190010/25/2011  
other - ramp
Override - Parcel Holds  10/25/2011  
Override - Parcel Holds  10/25/2011  
FIRE-Final Inspection10/24/201110/24/201110/24/2011PPART
DetailsTroy Cobbley
A temporary occupancy was given until the exit discharge lights have been installed and tested.
Override - Parcel Holds  10/24/2011  
BLD-Conference9/26/20119/26/20119/26/2011PPASS
DetailsTom Arcoraci
PubWorks Occupancy Approval9/16/20119/16/20119/16/2011 DONE
DetailsTiffany Lowery
Override - Parcel Holds  9/16/2011  
Plan assigned to (SRZ)8/19/20118/19/20119/13/2011 PASS
DetailsSam Zahorka
Routing - PLANNING9/9/2011 9/13/2011 PASS
DetailsSue Cummings
Needs a cross access agreement with neighboring church. Please do not issue final occupancy until the cross access agreement is approved.
PLANS/APPL TAKEN TO FRONT DESK  9/13/2011 DONE
DetailsSam Zahorka
Print Occupancy Form  9/13/2011 DONE
Telephone call  9/13/2011 DONE
DetailsChristina Prado
Called Glenn and gave fees due
Override - Parcel Holds  9/13/2011  
Permit Ready to Issue  9/13/2011 DONE
DetailsChristina Prado
Override - Parcel Holds  9/13/2011  
Issue PAID IN FULL permit  9/13/2011 DONE
DetailsTisha Gallop
Routing - PLAN CHECK9/8/2011 9/9/2011 PASS
DetailsSam Zahorka
Case Summary (BLD)  9/9/2011 DONE
DetailsSam Zahorka
Route to Impact Fee Review8/22/20118/25/20119/8/2011 PASS
DetailsCindy M. Gould
Routing - PLAN CHECK9/1/2011 9/8/2011 PASS
DetailsSam Zahorka
Routing - PLAN CHECK9/6/2011 9/8/2011 PASS
DetailsSam Zahorka
Routing - PUBLIC WORKS9/8/2011 9/8/2011 PASS
DetailsBeverly Mountain
Routing PW Drainage9/8/2011 9/8/2011 PASS
DetailsBrian Murphy
Plan resubmittals received  9/7/2011 DONE
DetailsChristina Prado
Received another 5 sets of revised Grading & Drainage sheets C1 and 1 sets of calcs. Taken to Sam Zahorka for review
Routing - PUBLIC WORKS9/2/2011 9/6/2011 FAIL
DetailsConnie Baumgartner
Corrections for Brian Murphy
Routing PW Drainage9/2/2011 9/5/2011 FAIL
DetailsBrian Murphy
SLOPES NOT 3 TO 1
Plan resubmittals received  9/2/2011 DONE
DetailsChristina Prado
Received 5 sets of plans C1 and one copy of Drainage Calcs & Geotech investigation report. sheet given to Sam Zahorka
Routing - FIRE8/31/2011 9/1/2011 PASS
DetailsScott Arellano
Attached revised IFC comments to plans
1st review completed  8/31/2011 FAIL
Failed Public Works, Fire
Routing - PLAN CHECK8/31/2011 8/31/2011 PASS
DetailsSam Zahorka
Plan resubmittals received  8/31/2011 DONE
DetailsChristina Prado
Received two copies of plans A-0.0 & A-1.0. And on transmittal letter. Inserted bt arch rep and taken back to Sam for review
Routing - FIRE8/30/2011 8/31/2011 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Routing - PLAN CHECK  8/30/2011 PASS
DetailsSam Zahorka
Routing PW Sewer Rating8/22/2011 8/23/2011 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment8/23/2011 8/23/2011 PASS
DetailsSteven Webb
ESC11-00604 plan waiver approved with conditions attached to the permit.
Routing - PUBLIC WORKS8/22/2011 8/23/2011 FAIL
DetailsConnie Baumgartner
Application received 8/19/20118/22/2011 DONE
DetailsTisha Gallop
Routing - PLANNING Land Div8/22/2011 8/22/2011 PASS
DetailsDave Abo
Lot 2, Mike Simunich Subdivision No. 2
Routing - Addressing8/22/2011 8/22/2011 PASS
DetailsApril Wing
Plans ACCEPTED BY PLAN TECH  8/19/2011 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  8/19/2011 DONE
DetailsTisha Gallop
Routing - PLANNING8/23/2011 8/23/2001 FAIL
DetailsSue Cummings
Cup11-00057