BLD-Final | 2/1/2012 | 2/1/2012 | 2/1/2012 | P | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
DOC - Permit Finaled | 2/1/2012 | 2/1/2012 | 2/1/2012 | P | PASS |
Mike Jordan
|
|
|
Residential certificate of occupancy was issued.
|
BLD-Energy code compliance | 12/14/2011 | 12/15/2011 | 12/15/2011 | P | PASS |
Mike Jordan
|
|
|
Brett ###-####
|
BLD-Framing/Rough-in | 12/15/2011 | 12/15/2011 | 12/15/2011 | P | PASS |
Mike Jordan
|
|
|
Brett ###-####
|
BLD-Framing/Rough-in | 12/13/2011 | 12/14/2011 | 12/14/2011 | P | FAIL |
Mike Jordan
|
|
|
Brett Phone #: ###-####. Provide remaining truss engineering A1 and ^ trusses. Fireblock at cei,ing level at built in closet in master bath. Tyvec needs to securley attached at knee walls with no gaps or rips around stairs. ok to insulate. correction notice posted.
|
BLD-Foundation | 11/23/2011 | 11/23/2011 | 11/23/2011 | P | PASS |
Mike Jordan
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 11/22/2011 | 11/22/2011 | 11/22/2011 | P | PASS |
Mike Jordan
|
|
|
Ryan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/3/2011 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 9/19/2011 | | |
|
|
|
|
Plan assigned to (CDM) | | 8/26/2011 | 9/19/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/19/2011 | | 9/19/2011 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/19/2011 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2011 | | DONE |
Christina Prado
|
|
|
Called and gave Tanya the fees due
|
Permit Ready to Issue | | | 9/19/2011 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 9/14/2011 | | |
|
|
|
9-14-11 received 2 sets of plans sent to Carl M
|
1st review completed | | | 9/12/2011 | | FAIL |
|
|
|
|
Case Summary (BLD) | | | 9/12/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/1/2011 | | 9/12/2011 | | FAIL |
Carl D Madsen
|
|
|
Egress window is required from bonus room area. Called Mark Waldorf with CBH 9-12-11 CDM
|
Routing - MECHANICAL | 9/2/2011 | | 9/2/2011 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/26/2011 | 8/31/2011 | 8/31/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 8/30/2011 | | 8/30/2011 | | FAIL |
Troy James
|
|
|
emailed corrections to matt
|
Routing - PLANNING | 8/29/2011 | | 8/30/2011 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | 8/26/2011 | | 8/29/2011 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 8/29/2011 | | 8/29/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/26/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 8/26/2011 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/26/2011 | | DONE |
Christina Prado
|
|
|
|
Application received | | 8/26/2011 | | | |
|
|
|
|