Second Notice | | 11/17/2011 | 11/21/2011 | | DONE |
|
|
|
|
First Notice | | 11/3/2011 | 11/7/2011 | | DONE |
|
|
|
|
BLD-Final | 10/21/2011 | 10/24/2011 | 10/24/2011 | A | PASS |
Tony Young
|
|
|
Bob Phone #: ###-####--No mechanical per Tony Young
|
Permanent Occupancy | | | 10/24/2011 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 10/18/2011 | 10/19/2011 | 10/19/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Conference | 10/17/2011 | 10/18/2011 | 10/18/2011 | A | DONE |
Troy Cobbley
|
|
|
Went over life safety issues with the superintendant
|
BLD-Framing/Rough-in | 10/10/2011 | 10/11/2011 | 10/11/2011 | P | PASS |
Tony Young
|
|
|
bob Phone #: ###-####
|
BLD-Framing/Rough-in | 10/7/2011 | 10/10/2011 | 10/11/2011 | P | NR |
Tony Young
|
|
|
bob Phone #: ###-####,, need elec pass
|
Telephone call | | | 10/4/2011 | | DONE |
Tisha Gallop
|
|
|
e-mailed Nick Serbian/Horizon Retail Const. on 10/3/11 need GC form before can issue permit.
|
Permit Ready to Issue | | | 10/4/2011 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 10/4/2011 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 10/4/2011 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 10/4/2011 | | DONE |
Christina Prado
|
|
|
|
Routing PW Sewer Rating | 9/29/2011 | | 9/29/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 9/29/2011 | | 9/29/2011 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLAN CHECK | 9/21/2011 | | 9/29/2011 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review. This is an ePlanReview project and revised drawings were downloaded on September 26.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (FEE) | | | 9/29/2011 | | DONE |
Tisha Gallop
|
|
|
E-mailed applicant to provide updated Certificate of Value and Contractors form.
|
Plan assigned to (CJW) | 9/6/2011 | | 9/29/2011 | | PASS |
Carl Westfall
|
|
|
CASH STORE (Electronic Plan Review) (20 days - Oct 3)
|
Routing - PLAN CHECK | 9/6/2011 | | 9/21/2011 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on September 14 and finished on September 21 (6 work days). Revised drawings were required. See the plan review report.
|
Routing - Addressing | 9/6/2011 | | 9/21/2011 | | PASS |
April Wing
|
|
|
|
1st review completed | | | 9/21/2011 | | DONE |
|
|
|
|
Routing - FIRE | 9/6/2011 | | 9/8/2011 | | PASS |
Scott Arellano
|
|
|
Plans are approved as shown. No seperate comments attached to case. Final approval will be subject to satisfactory field inspection by the PDS Fire inspector.
|
Routing - Design Review | 9/6/2011 | | 9/7/2011 | | PASS |
Andrea Tuning
|
|
|
Approved with red lined corrections to eliminate the three parking spaces located within the alley right-of-way directly to the north of the site. ANT ###-####
|
Routing PW Sewer Rating | 9/7/2011 | | 9/7/2011 | | FAIL |
Connie Baumgartner
|
|
|
Failed till resubmittals for additional restroom IF required by Tim Woodard.
|
Intake Approval | | | 9/6/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 9/6/2011 | | 9/6/2011 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 8/29/2011 | | FAIL |
Tim L. Woodard
|
|
|
Identified additional items needed before submittal. After a discussion with Jason about the plans not being to minimum 18 inch by 24 inch; we decided to offer the architect the ability to submit electronically. He indicated to me that he did want to do that. He was advised to send the application to Jason to have the case created in Project Dox
|
Application received | | 8/26/2011 | | | |
|
|
|
|