DOC - Permit Finaled | | | 3/11/2013 | | DONE |
|
|
|
per bob
|
BLD-Final | 1/25/2012 | 1/25/2012 | 1/25/2012 | A | PASS |
Dave Hannah
|
|
|
paul Phone #: ###-####
|
BLD-Final | 1/23/2012 | 1/24/2012 | 1/25/2012 | A | CANC |
Dave Hannah
|
|
|
paul Phone #: ###-####
|
FIRE-Conference | 11/14/2011 | 11/15/2011 | 1/24/2012 | A | DONE |
Forrest France
|
|
|
Regarding coverage at the ATM room.
|
FIRE-Final Inspection | 1/23/2012 | 1/23/2012 | 1/24/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety passed pending fire extinguisher at the break room is provided with at wall bracket and the project related fire sprinkler permit is requested for final inspection status.
|
BLD-Other | 11/18/2011 | 11/18/2011 | 11/18/2011 | P | PASS |
Dave Hannah
|
|
|
paul - exterior ceiling inspection Phone #: ###-#### ok to cover ext
|
BLD-Framing/Rough-in | 10/27/2011 | 10/28/2011 | 10/28/2011 | A | PASS |
Dave Hannah
|
|
|
mike Phone #: ###-####
|
BLD-Framing/Rough-in | 10/10/2011 | 10/11/2011 | 10/11/2011 | A | PASS |
Dave Hannah
|
|
|
paul Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/26/2011 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 9/22/2011 | | 9/22/2011 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 9/22/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Inspection Record Card- Bld | | | 9/22/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/22/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/22/2011 | | DONE |
Tisha Gallop
|
|
|
called Steve Christiansen and left vm permit is ready and fees.
|
Plan assigned to (TLW) | 8/29/2011 | | 9/22/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 9/19/2011 | | DONE |
Christina Prado
|
|
|
Received one copy of response letter, calcs and two sets of plans A2.0, A2.1 & A3.0. Plans given to Tim Woodard for additional review
|
1st review completed | | | 9/8/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 8/31/2011 | | 9/8/2011 | | FAIL |
Tim L. Woodard
|
|
|
Corrections sent to the architect. TLW
|
Routing - PUBLIC WORKS | 8/29/2011 | | 8/31/2011 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 8/30/2011 | | 8/30/2011 | | PASS |
Terry Records
|
|
|
|
Routing PW Sewer Rating | 8/30/2011 | | 8/30/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 8/29/2011 | 8/29/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/29/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/29/2011 | | DONE |
Tisha Gallop
|
|
|
|