Third Follow up | | | 3/30/2012 | | DONE |
|
|
|
received FV 4/12/12
|
Third Notice | | 3/15/2012 | 3/15/2012 | | DONE |
|
|
|
mailed to John Lodman
|
Third Notice | | 2/2/2012 | 3/1/2012 | | DONE |
|
|
|
faxed to GC
|
Third Notice | | 1/8/2012 | 1/19/2012 | | DONE |
|
|
|
faxed to GC
|
Second Notice | | 12/30/2011 | 1/3/2012 | | DONE |
|
|
|
|
First Notice | | 12/16/2011 | 12/20/2011 | | DONE |
Christina Prado
|
|
|
faxed 12-20-11
|
Permanent Occupancy | | | 12/6/2011 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 11/29/2011 | 11/30/2011 | 11/30/2011 | P | PASS |
Tom Arcoraci
|
|
|
requesting temp signature pending CDHD opening inspection please. Phone #: ###-#### >> Inspection requested via web by John Lodman
|
FIRE-Final Inspection | 11/29/2011 | 11/30/2011 | 11/30/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. I helped John correct the sample tubes in the duct smoke detector.
|
BLD-Other | 11/13/2011 | 11/14/2011 | 11/14/2011 | P | PASS |
Tom Arcoraci
|
|
|
grid ceiling cover. mech and ele inspections pending. thank you. Phone #: ###-#### >> Inspection requested via web by John Lodman
|
FIRE-Conference | 11/9/2011 | 11/9/2011 | 11/9/2011 | P | DONE |
Troy Cobbley
|
|
|
Went over exit door hardware requirements with the general contractor.
|
BLD-Wall cover | 10/24/2011 | 10/24/2011 | 10/24/2011 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by John Lodman
|
BLD-Conference | 10/14/2011 | 10/14/2011 | 10/14/2011 | A | PASS |
Tom Arcoraci
|
|
|
clarification on entry door hardware plan review comments. thank you. Phone #: ###-#### >> Inspection requested via web by John Lodman
|
Issue PAID IN FULL permit | | | 10/10/2011 | | DONE |
|
|
|
|
OVERRIDE | | | 10/6/2011 | | |
|
|
|
|
Route to Impact Fee Review | 9/28/2011 | 10/3/2011 | 10/6/2011 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 9/29/2011 | | 10/6/2011 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines" after resubmittal review.
|
Plan assigned to (CJW) | 9/9/2011 | | 10/6/2011 | | PASS |
Carl Westfall
|
|
|
SUBWAY (20 days - Oct 4)
|
Telephone call | | | 10/6/2011 | | DONE |
Tisha Gallop
|
|
|
called Aaron/JGT arch. and left voicemessage with receptionist that permit is ready, fee, need ACHD and RP.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2011 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/6/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/6/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 9/30/2011 | | DONE |
Christina Prado
|
|
|
Received two copies of plans A-1.0, A-1.1, M-1.0 & E-2.0LK and one response letter. Given to Carl Westfall for review
|
Routing - FIRE | 9/28/2011 | 9/28/2011 | 9/29/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 9/29/2011 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 9/15/2011 | | 9/28/2011 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on September 21, 2011 and was finished on September 28, 2011. Revised drawings were required. See the plan review report.
|
Routing - PLUMBING | 9/13/2011 | | 9/15/2011 | | PASS |
Bill VanDegrift
|
|
|
1. Requires a RPBP upstream of filter in potable water system.
2. Per plans and 2003 UPC.
|
Routing - Erosion and Sediment | 9/12/2011 | | 9/13/2011 | | PASS |
Clint A Smith
|
|
|
ESC11-00644 plan waiver approved with conditions attached to the permit.
|
Routing PW Sewer Rating | 9/12/2011 | | 9/12/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 9/9/2011 | | 9/12/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 9/8/2011 | | 9/9/2011 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 9/9/2011 | | 9/9/2011 | | PASS |
Sue Cummings
|
|
|
|
Intake Approval | | | 9/7/2011 | | PASS |
Dan Stuart
|
|
|
Dan let the applicant know to contact ACHD for evaluation of impact fees. Written verification will be needed prior to building permit issuance.
|
Plans ACCEPTED BY PLAN TECH | | | 9/7/2011 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/7/2011 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | 9/2/2011 | 9/2/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 9/2/2011 | | FAIL |
Dan Stuart
|
|
|
New RTU - Need Engineers analysis and roof framing plan for new unit.
Demo of existing restroom and two new restrooms & kitchen utility lines require removal of existing concrete floor section - ESC App & Waiver Request needed.
|