Permit Information
Permit NumberBLD11-02134
StatusFinaled
Name LODMAN COMMERCIAL CONST MANAGEMENT
Site Address 5024 W EMERALD ST
Project NameSUBWAY
Customer Number 
ePlanReviewNo
Description
(SUBWAY) This building does not have a fire sprinkler system. To remodel an existing 1,270 square foot shell tenant space within an existing 6,800 square foot building for a new restaurant tenant. Work is to include 2 restrooms accessible to the disabled, interior nonbearing walls, kitchen equipment, suspended ceilings, gypsum board ceilings and bulkheads, and interior finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Follow up  3/30/2012 DONE
received FV 4/12/12
Third Notice 3/15/20123/15/2012 DONE
mailed to John Lodman
Third Notice 2/2/20123/1/2012 DONE
faxed to GC
Third Notice 1/8/20121/19/2012 DONE
faxed to GC
Second Notice 12/30/20111/3/2012 DONE
First Notice 12/16/201112/20/2011 DONE
DetailsChristina Prado
faxed 12-20-11
Permanent Occupancy  12/6/2011 DONE
DetailsChristina Prado
BLD-Final11/29/201111/30/201111/30/2011PPASS
DetailsTom Arcoraci
requesting temp signature pending CDHD opening inspection please. Phone #: ###-#### >> Inspection requested via web by John Lodman
FIRE-Final Inspection11/29/201111/30/201111/30/2011APASS
DetailsTroy Cobbley
life safety passed. I helped John correct the sample tubes in the duct smoke detector.
BLD-Other11/13/201111/14/201111/14/2011PPASS
DetailsTom Arcoraci
grid ceiling cover. mech and ele inspections pending. thank you. Phone #: ###-#### >> Inspection requested via web by John Lodman
FIRE-Conference11/9/201111/9/201111/9/2011PDONE
DetailsTroy Cobbley
Went over exit door hardware requirements with the general contractor.
BLD-Wall cover10/24/201110/24/201110/24/2011APASS
DetailsTom Arcoraci
Phone #: ###-#### >> Inspection requested via web by John Lodman
BLD-Conference10/14/201110/14/201110/14/2011APASS
DetailsTom Arcoraci
clarification on entry door hardware plan review comments. thank you. Phone #: ###-#### >> Inspection requested via web by John Lodman
Issue PAID IN FULL permit  10/10/2011 DONE
OVERRIDE  10/6/2011  
Route to Impact Fee Review9/28/201110/3/201110/6/2011 PASS
DetailsCindy M. Gould
Tenant improvement no impact fees
Routing - PLAN CHECK9/29/2011 10/6/2011 PASS
DetailsCarl Westfall
Drawings approved with "red lines" after resubmittal review.
Plan assigned to (CJW)9/9/2011 10/6/2011 PASS
DetailsCarl Westfall
SUBWAY (20 days - Oct 4)
Telephone call  10/6/2011 DONE
DetailsTisha Gallop
called Aaron/JGT arch. and left voicemessage with receptionist that permit is ready, fee, need ACHD and RP.
PLANS/APPL TAKEN TO FRONT DESK  10/6/2011 DONE
Print Occupancy Form  10/6/2011 DONE
Permit Ready to Issue  10/6/2011 DONE
DetailsTisha Gallop
Plan resubmittals received  9/30/2011 DONE
DetailsChristina Prado
Received two copies of plans A-1.0, A-1.1, M-1.0 & E-2.0LK and one response letter. Given to Carl Westfall for review
Routing - FIRE9/28/20119/28/20119/29/2011 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  9/29/2011 FAIL
Failed Plan Check
Routing - PLAN CHECK9/15/2011 9/28/2011 FAIL
DetailsCarl Westfall
The IBC plan review was started on September 21, 2011 and was finished on September 28, 2011. Revised drawings were required. See the plan review report.
Routing - PLUMBING9/13/2011 9/15/2011 PASS
DetailsBill VanDegrift
1. Requires a RPBP upstream of filter in potable water system.
2. Per plans and 2003 UPC.
Routing - Erosion and Sediment9/12/2011 9/13/2011 PASS
DetailsClint A Smith
ESC11-00644 plan waiver approved with conditions attached to the permit.
Routing PW Sewer Rating9/12/2011 9/12/2011 PASS
DetailsConnie Baumgartner
Routing - PUBLIC WORKS9/9/2011 9/12/2011 PASS
DetailsConnie Baumgartner
Pending Assignment by JCB9/8/2011 9/9/2011 DONE
DetailsJason Blais
Routing - Addressing9/9/2011 9/9/2011 PASS
DetailsSue Cummings
Intake Approval  9/7/2011 PASS
DetailsDan Stuart
Dan let the applicant know to contact ACHD for evaluation of impact fees. Written verification will be needed prior to building permit issuance.
Plans ACCEPTED BY PLAN TECH  9/7/2011 DONE
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  9/7/2011 DONE
DetailsBarbara Stitt
Application received 9/2/20119/2/2011 DONE
DetailsChristina Prado
Intake Approval  9/2/2011 FAIL
DetailsDan Stuart
New RTU - Need Engineers analysis and roof framing plan for new unit.
Demo of existing restroom and two new restrooms & kitchen utility lines require removal of existing concrete floor section - ESC App & Waiver Request needed.