Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD11-02155
StatusFinaled
Name CHEVRON PIPE LINE CO
Site Address 201 N PHILLIPPI ST
Project NameCHEVRON PIPELINE MODULAR OFFIC
Customer Number 
ePlanReviewNo
Description
CHEVRON PIPELINE MODULAR OFFICE- To replace an existing modular office building with a new 2,940 square foot, one story modular office building and related site improvements. There will be an accessible metal ramp installed to the north entry door. A compliant stair and landings are required at the west door. The Idaho State Tag Number is MOD1108-00007. All construction per the approved plans, attached plan review report, and inspectors final approvals. This building is NOT fire sprinklered. A Certificate of Occupancy with the occupant load total is to be issued when completed and approved. CUP08-00049 **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice4/1/20144/1/20144/25/2014 DONE
DetailsTom Arcoraci
DOC - Permit Finaled4/1/20144/1/20144/1/2014PPASS
DetailsTom Arcoraci
BLD-Final2/24/20122/27/20122/27/2012APASS
DetailsTom Arcoraci
Steve Phone #: ###-#### 301 ran out of time.
BLD-Final2/24/20122/24/20122/24/2012PDEFR
DetailsJim Storey
Steve Phone #: ###-#### out of time
BLD-Final2/1/20122/2/20122/2/2012PFAIL
DetailsTom Arcoraci
Steve Phone #: ###-####
FIRE-Final Inspection2/1/20122/2/20122/2/2012APASS
DetailsTroy Cobbley
life safety passed
PubWorks Occupancy Approval2/1/20122/1/20122/1/2012 DONE
DetailsTiffany Lowery
Zoning Approval2/1/20122/1/20122/1/2012 DONE
DetailsAndrea Tuning
BLD-Footing11/15/201111/17/201111/17/2011PPASS
DetailsTom Arcoraci
Steve Phone #: ###-####
OVERRIDE  11/8/2011  
Telephone call  11/8/2011 DONE
DetailsTisha Gallop
called Steve at Chevron Pipeline Co and told him need ACHD and GC. He said the parcel owner, Chevron, is going to be GC, I told him still need to fill out form when come into office.
Issue PAID IN FULL permit  11/8/2011 DONE
DetailsChristina Prado
Print Occupancy Form  11/8/2011 DONE
Permit Ready to Issue  11/8/2011 DONE
DetailsTisha Gallop
Plan assigned to (SRZ)9/16/20119/16/201111/7/2011 PASS
DetailsSam Zahorka
2nd review completed. Pending Public Works and ESC to pass.
Routing - PLAN CHECK11/7/2011 11/7/2011 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  11/7/2011 DONE
DetailsSam Zahorka
Routing - PUBLIC WORKS10/27/2011 11/7/2011 PASS
DetailsConnie Baumgartner
Routing PW Sewer Rating11/4/2011 11/4/2011 PASS
DetailsConnie Baumgartner
Routing PW Drainage11/3/2011 11/3/2011 PASS
DetailsBrian Murphy
Routing - PLAN CHECK10/25/2011 10/27/2011 PASS
DetailsSam Zahorka
Routed to Public Works.
Routing - Erosion and Sediment10/20/2011 10/25/2011 PASS
DetailsClint A Smith
ESC11-00642 plan waiver approved with condittions attached to the permit.
Routing - PLANNING10/25/2011 10/25/2011 PASS
DetailsAndrea Tuning
Case Summary (BLD)  10/20/2011 DONE
DetailsSam Zahorka
Routing - PLAN CHECK10/7/2011 10/20/2011 PASS
DetailsSam Zahorka
Plan resubmittals received  10/17/2011 DONE
DetailsChristina Prado
Received via fedex threee sets of sheets marked 01659 B, 01660 B & 01661 b. As well as fives sets of plans marked 00995 3B. Stamped and given to Sam Zahorka for review
Route to Impact Fee Review9/15/20119/20/201110/13/2011 PASS
DetailsCindy M. Gould
Routing - FIRE10/6/201110/6/201110/7/2011 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  10/7/2011 FAIL
Failed Public Works, Plan Check
Case Summary (BLD)  10/6/2011 DONE
DetailsSam Zahorka
Routing - PLAN CHECK9/26/2011 10/6/2011 FAIL
DetailsSam Zahorka
Sam Zahorka
Plan resubmittals received  10/3/2011 DONE
DetailsChristina Prado
Received three sets of plans 3B with drainage reports. Given to Sam Zahorka for review
Routing - PLANNING9/26/2011 9/26/2011 PASS
DetailsAndrea Tuning
Routing - PLUMBING9/22/2011 9/26/2011 PASS
DetailsDaryl Spivey
connections to existing, may require cross connecton protection. all new plumbing per 2003 upc.
Plan resubmittals received  9/23/2011  
Received 1 copy of ESC waiver and included in rounting plans
Routing - Erosion and Sediment9/21/2011 9/22/2011 FAIL
DetailsClint A Smith
Plan review FAILED.
Must submitt an ESC plan or apply with an ESC plan waiver letter for approval. Contacted the applicant and explained on the requirements.
Routing - PUBLIC WORKS9/16/2011 9/21/2011 FAIL
DetailsConnie Baumgartner
Failed by Brian Murphy
Routing PW Drainage9/19/2011 9/21/2011 PASS
DetailsBrian Murphy
needs drainage report
Routing PW Sewer Rating9/21/2011 9/21/2011 PASS
DetailsConnie Baumgartner
Routing - Addressing9/16/2011 9/16/2011 PASS
DetailsApril Wing
Routing - PLANNING Land Div9/16/2011 9/16/2011 PASS
DetailsTodd Tucker
Intake Approval  9/13/2011 PASS
DetailsCarl Westfall
OK to submit for permit after check is received.
Recd Pcfee & Taken To Pln CK  9/13/2011 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  9/13/2011 DONE
DetailsBarbara Stitt
Application received 9/7/20119/7/2011 DONE
DetailsBarbara Stitt