BLD-Final | 11/1/2012 | 11/1/2012 | 11/1/2012 | P | PASS |
Tony Young
|
|
|
c of o issued
|
DOC - Permit Finaled | 11/1/2012 | 11/1/2012 | 11/1/2012 | P | PASS |
Tony Young
|
|
|
|
BLD-Conference | 10/16/2012 | 10/17/2012 | 11/1/2012 | P | PASS |
Tony Young
|
|
|
|
Routing PW Grading-Hillside | 11/1/2012 | | 11/1/2012 | | PASS |
Jim Wyllie
|
|
|
Bonding received for completion of site work. Okay to sign Occupancy permit. Jim Wyllie (###-####)
|
BLD-Final | 9/12/2012 | 9/13/2012 | 9/13/2012 | A | NR |
Tony Young
|
|
|
Jerry Phone #: ###-####,, walk through only,, just need hillside final
|
BLD-Energy code compliance | 5/22/2012 | 5/22/2012 | 6/4/2012 | P | DONE |
Tony Young
|
|
|
CHRIS Phone #: ###-####
|
BLD-Framing/Rough-in | 5/29/2012 | 5/29/2012 | 6/4/2012 | P | DONE |
Tony Young
|
|
|
CHRIS Phone #: ###-####
|
BLD-Framing/Rough-in | 6/1/2012 | 6/1/2012 | 6/1/2012 | P | PASS |
Tony Young
|
|
|
CHRIS Phone #: ###-####,, frame above garage wall to roof deck
|
BLD-Energy code compliance | 5/24/2012 | 5/25/2012 | 5/29/2012 | P | PASS |
Tony Young
|
|
|
CHRIS Phone #: ###-####,, house ok,, need garage
|
BLD-Energy code compliance | 5/24/2012 | 5/24/2012 | 5/25/2012 | P | PASS |
Tony Young
|
|
|
CHRIS Phone #: ###-####
|
BLD-Energy code compliance | 5/21/2012 | 5/22/2012 | 5/23/2012 | A | PART |
Tony Young
|
|
|
CHRIS Phone #: ###-####,, need to seal some holes,, insulation ok
|
BLD-Framing/Rough-in | 5/8/2012 | 5/9/2012 | 5/10/2012 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, main level walls,, winder stair ?s
|
BLD-Framing/Rough-in | 5/7/2012 | 5/8/2012 | 5/10/2012 | A | PEND |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 5/9/2012 | 5/9/2012 | 5/10/2012 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, main level walls ok to insulate,, need fireblocking,, need sprinklers signed off complete prior to cover ok
|
BLD-Energy code compliance | 5/4/2012 | 5/4/2012 | 5/4/2012 | P | PART |
Tony Young
|
|
|
chris Phone #: ###-####,,, basement ok to cover,, stairs still not per code on east side
|
BLD-Energy code compliance | 4/25/2012 | 5/3/2012 | 5/4/2012 | P | PEND |
Tony Young
|
|
|
chris Phone #: ###-####,, basement area,, pending fire sprinkler pas
|
FIRE-Conference | 4/19/2012 | 4/19/2012 | 4/19/2012 | P | DONE |
Troy Cobbley
|
|
|
Fire sprinkler plans need to be resubmitted showing all changes in routing and fitting counts prior to covering by sheet rock. I spoke to Bruce the fitter, Tony Young and with Jerry with Petra about the issues but agreed that I would allow the installation of insulation, for sound proofing, above the piping. This insulation, it was agreed would be installed above the sprinkler piping and would not obstruct my view of the sprinkler piping for the future cover inspection.
|
Plan Reviewer's activity | | | 4/18/2012 | | DONE |
Sam Zahorka
|
|
|
Received a request from Steve Bayne with Franklin Building Supply for Deputy Chief Fire Marshal, Romeo Gervais' contact information. Emailed the contact information to Steve.
|
BLD-Framing/Rough-in | 4/12/2012 | 4/12/2012 | 4/13/2012 | P | NR |
Tony Young
|
|
|
jerry Phone #: ###-####,, basement area
|
BLD-Framing/Rough-in | 4/11/2012 | 4/11/2012 | 4/12/2012 | P | CANC |
Tony Young
|
|
|
jerry Phone #: ###-####,, basement area
|
BLD-Framing/Rough-in | 4/9/2012 | 4/11/2012 | 4/12/2012 | A | CANC |
Tony Young
|
|
|
jerry Phone #: ###-####,, basement area
|
BLD-Framing/Rough-in | 4/10/2012 | 4/10/2012 | 4/12/2012 | A | NR |
Tony Young
|
|
|
jerry Phone #: ###-####,, basement area,, conf only,, need trades
|
BLD-Framing/Rough-in | 4/6/2012 | 4/9/2012 | 4/9/2012 | P | NR |
Tony Young
|
|
|
jerry Phone #: ###-####,, need trades 1st,, walk through only,, need fireblocks,, need winder stairs to meet codes
|
BLD-Wall Bracing | 3/28/2012 | 3/28/2012 | 4/3/2012 | P | PASS |
Tony Young
|
|
|
shear panel and hold downs//Jerry Phone #: ###-####
|
BLD-Wall Bracing | 3/19/2012 | 3/19/2012 | 3/28/2012 | P | PASS |
Tony Young
|
|
|
shear panel and hold downs//Jerry Phone #: ###-####
|
BLD-Wall Bracing | 3/20/2012 | 3/20/2012 | 3/21/2012 | P | PASS |
Tony Young
|
|
|
shear panel and hold downs//Jerry Phone #: ###-####
|
BLD-Wall Bracing | 3/6/2012 | 3/8/2012 | 3/20/2012 | A | PART |
Tony Young
|
|
|
Marc Phone #: ###-####,, garage ok
|
Telephone call | | | 3/9/2012 | | DONE |
Sam Zahorka
|
|
|
I spoke with Jerry Frank the owner of this home about his Soffit/eve protection product. He wants to use a spray applied (Flame Stop 2) product rather than the approved 2 layers of type X sheetrock approved on his construction plans. I stated this product does not meet the 2009 IBC section 2303.2 as required by the W.U.I. section 4911. He stated he already paid the lumber yard to have the product applied and wants to further discuss with the Fire department. I called Romeo the deputy chief fire marshal and left a message to discuss this product and it's approval. Waiting for a returned telephone call.
|
Plan Reviewer's activity | | | 3/9/2012 | | DONE |
Sam Zahorka
|
|
|
Emailed The cheif deputy fire marshals response back to Jerry and Barbara about their eave/soffit product request. The proposed product will not work due to not meeting section 2303.2 of the IBC.
|
BLD-Wall Bracing | 3/5/2012 | 3/6/2012 | 3/7/2012 | P | PART |
Tony Young
|
|
|
shear panel and hold downs//Jerry Phone #: ###-####,,, hold downs ok
|
BLD-Conference | 2/9/2012 | 2/14/2012 | 2/14/2012 | P | PART |
Tony Young
|
|
|
j.c. - conference re: framing issues Phone #: ###-####,,, double wall shear ok
|
BLD-Other | 2/9/2012 | 2/10/2012 | 2/10/2012 | A | PASS |
Tony Young
|
|
|
|
BLD-Conference | 2/8/2012 | 2/9/2012 | 2/9/2012 | A | PART |
Tony Young
|
|
|
j.c. - conference re: framing issues Phone #: ###-####,, shear conference
|
BLD-Foundation | 12/23/2011 | 12/27/2011 | 12/27/2011 | A | PART |
Tony Young
|
|
|
GENE Phone #: ###-####,, basement walls,,, all rebar is tied,, ok to pour after form are placed
|
BLD-Other | 12/22/2011 | 12/23/2011 | 12/23/2011 | P | PART |
Tony Young
|
|
|
GENE Phone #: ###-####,, west half of the garage north retaining wall ok
|
BLD-Footing | 12/14/2011 | 12/15/2011 | 12/15/2011 | P | PART |
Tony Young
|
|
|
gene Phone #: ###-####,, garage footings ok
|
PubWorks Subgrade Approval | 12/14/2011 | 12/14/2011 | 12/14/2011 | | PART |
Terry Records
|
|
|
Subgrade for garage footings approved by the geotechnical engineer
|
Telephone call | | | 12/13/2011 | | DONE |
Sam Zahorka
|
|
|
Spoke with Jerry Frank about his required Class A roof assembly and 1-hour Fire Rated soffit construction. I explained the requirements with him and suggested 3/4" Fire retardant treated plywood construction under his soffit finish material. I also requested any changes from the approved plans to be submitted as plan modifications prior to construction.
|
BLD-Footing | 12/1/2011 | 12/1/2011 | 12/2/2011 | P | PEND |
Tony Young
|
|
|
Gene Ness Phone #: ###-####,, pend special inspection report
|
BLD-Footing | 11/23/2011 | 11/28/2011 | 11/28/2011 | P | PART |
Tony Young
|
|
|
Gene Phone #: ###-####,,, under slab floor footings ,, ok pending special inspections
|
BLD-Other | 11/14/2011 | 11/14/2011 | 11/15/2011 | P | PART |
Tony Young
|
|
|
rebar insp//Gene Phone #: ###-####,, south walls ok
|
BLD-Footing | 11/2/2011 | 11/3/2011 | 11/3/2011 | A | PART |
Jim Sly
|
|
|
Gene Phone #: ###-#### Footing for South walls OK.
|
BLD-Foundation | 11/2/2011 | 11/2/2011 | 11/2/2011 | P | PART |
Jim Sly
|
|
|
Re-bar inspection please-Gene Phone #: ###-#### Remainder of North and East wall OK......Contractor to verify that Geo Tech and Terry Records have approved South footing. I did not approve South footing.
|
PubWorks Subgrade Approval | 11/2/2011 | 11/2/2011 | 11/2/2011 | | PART |
Terry Records
|
|
|
Footing subgrade for south wall approved by the geotech. There may be other footings requiring subgrade approval.
|
BLD-Foundation | 10/31/2011 | 11/1/2011 | 11/1/2011 | A | PART |
Dave Hannah
|
|
|
gene Phone #: ###-#### high wall ok to close up
|
BLD-Other | 10/28/2011 | 10/31/2011 | 10/31/2011 | A | PASS |
Jim Storey
|
|
|
rebar insp//Gene Phone #: ###-####
|
BLD-Footing | 10/18/2011 | 10/20/2011 | 10/20/2011 | A | PART |
Tony Young
|
|
|
After 3pm---Frank Phone #: ###-####,, pending special inspection report
|
PubWorks Subgrade Approval | 10/17/2011 | 10/17/2011 | 10/17/2011 | | PART |
Terry Records
|
|
|
Footing subgrade for north east and west footings approved by the geotechnical engineer.
|
Issue PAID IN FULL permit | | | 10/14/2011 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 9/29/2011 | 9/29/2011 | 10/12/2011 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 10/6/2011 | | 10/12/2011 | | PASS |
Sam Zahorka
|
|
|
Passed with red-lines and comments.
|
Case Summary (BLD) | | | 10/12/2011 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/2011 | | DONE |
Sam Zahorka
|
|
|
|
Inspection Record Card- Bld | | | 10/12/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/12/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 10/12/2011 | | DONE |
Barbara Stitt
|
|
|
Left a voice message for Jerry with Petra that permit is ready & fees due on 10-12-11 @ 3:50pm//BAS
|
Plan resubmittals received | | | 10/11/2011 | | |
|
|
|
Received two sets of plans marked S0.1, S1.1,S2.1, S2.2, S2.3, S2.4, S2.5, S3.1, S3.2, S4.1 & S5.1 as well as one transmittal sheet.Plans givent o Sam Z for review
|
Routing - MECHANICAL | 9/30/2011 | | 10/6/2011 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 9/30/2011 | | DONE |
Sam Zahorka
|
|
|
Failed Mechanical and Plan check.
|
Routing - PLAN CHECK | 9/29/2011 | | 9/30/2011 | | FAIL |
Sam Zahorka
|
|
|
Wildland Urban Interface Fire Code issues. Called the architect and left a message. Waiting for response.
|
Routing - MECHANICAL | 9/29/2011 | | 9/30/2011 | | FAIL |
Troy James
|
|
|
emailed and talked to chance at western heating his corrections
|
Plan assigned to (CDM) | | 9/8/2011 | 9/29/2011 | | DEFR |
Carl D Madsen
|
|
|
Defferred to Sam Zahorka
|
Routing - PLAN CHECK | 9/19/2011 | | 9/29/2011 | | PEND |
Carl D Madsen
|
|
|
Defferred to Sam Zahorka
|
Routing PW Grading-Hillside | 9/27/2011 | | 9/27/2011 | | PASS |
Terry Records
|
|
|
|
Plan resubmittals received | | | 9/23/2011 | | DONE |
Christina Prado
|
|
|
Received three sets of plans 1thru 3 as well as one response letter. plans given to Carl Madsen for review
|
Route to Impact Fee Review | 9/9/2011 | 9/14/2011 | 9/21/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 9/19/2011 | | 9/19/2011 | | PASS |
Tim Frost
|
|
|
NFPA 13D sprinkler system is required. The plot plan shows a 2" fire main supply the building on sheet 2 of 3. Cannot be reached with 150' hose.
|
Routing - Erosion and Sediment | 9/15/2011 | | 9/16/2011 | | PASS |
Clint A Smith
|
|
|
ESC10-00657 will also be used under this BLD permit.
|
Routing PW Grading-Hillside | 9/13/2011 | | 9/15/2011 | | FAIL |
Terry Records
|
|
|
Seepage bed needs geotechnical approval
|
Routing - PLANNING | 9/12/2011 | | 9/13/2011 | | PASS |
Cody Riddle
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2011 | | 9/12/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 9/12/2011 | | 9/12/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | | | 9/9/2011 | | PEND |
|
|
|
|
Routing - Addressing | 9/8/2011 | | 9/9/2011 | | PASS |
Terry Records
|
|
|
|
Intake Approval | | | 9/8/2011 | | FAIL |
Christina Prado
|
|
|
Needs ResCheck
|
Plans ACCEPTED BY PLAN TECH | | | 9/8/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 9/8/2011 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/8/2011 | | DONE |
Christina Prado
|
|
|
|
Application received | | 9/8/2011 | | | |
|
|
|
|