Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD11-02176
StatusFinaled
Name WF CONSTRUCTION & SALES LLC
Site Address 190 E FRONT ST
Project NameAVENUE A DRIVEWAY REPLACEMENT
Customer Number 
ePlanReviewNo
Description
(ADA COUNTY--AVENUE A DRIVEWAY REPLACEMENT)Grading and drainage permit to remove concrete surface and replace surface with new asphalt as shown in plan set for the driveway leading up to 190 E Front St. All existing curbs, gutters and sidewalk to be retained and protected. All work is to be done according to plans as approved by Public Works Department. No construction is allowed and no site utilities are included in this scope of work. Reference CZC11-00195 for planning approval. //cdp
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/7/20122/2/2012 DONE
DetailsChristina Prado
Done 2/2/12
Second Notice 1/27/20122/2/2012 DONE
DetailsChristina Prado
faxed 2-2-12
First Notice1/12/20121/12/20121/17/2012 DONE
DetailsDave Hannah
BLD-Final1/12/20121/12/20121/12/2012APASS
DetailsDave Hannah
DOC - Permit Finaled1/12/20121/12/20121/12/2012PPASS
DetailsDave Hannah
BLD-Final9/16/20119/19/20119/19/2011PPART
DetailsDave Hannah
Kevin Phone #: ###-#### Or Jim ###-#### frist section ok
FIRE-Final Inspection9/16/20119/19/20119/19/2011PPASS
DetailsForrest France
Life safety passed.
Issue PAID IN FULL permit  9/14/2011 DONE
OVERRIDE  9/13/2011  
Inspection Record Card- Bld  9/13/2011 DONE
DetailsChristina Prado
Routing - FIRE9/12/2011 9/13/2011 PASS
DetailsScott Arellano
Plans are approved as shown. No seperate comments attached.
1st review completed  9/13/2011 PASS
Routing - PLAN CHECK9/13/2011 9/13/2011 PASS
DetailsChristina Prado
Case Summary (BLD)  9/13/2011 DONE
DetailsChristina Prado
PLANS/APPL TAKEN TO FRONT DESK  9/13/2011 DONE
DetailsChristina Prado
Inspection Record Card- Bld  9/13/2011 DONE
DetailsChristina Prado
Telephone call  9/13/2011 DONE
DetailsChristina Prado
Called and gave Bruce fees due
Permit Ready to Issue  9/13/2011 DONE
DetailsChristina Prado
Plan assigned to Christina  9/13/2011 DONE
DetailsChristina Prado
Route to Impact Fee Review9/12/20119/15/20119/12/2011 PASS
DetailsCindy M. Gould
No impact fees
Routing - PLANNING9/12/2011 9/12/2011 PASS
DetailsJosh Wilson
Routing - Erosion and Sediment9/9/2011 9/12/2011 PASS
DetailsClint A Smith
ESC11-00648 plan waiver applroved with conditions attached to the permit.
Routing - PLANNING Land Div9/8/2011 9/9/2011 PASS
DetailsDave Abo
Parcel over 5 acres in size.
Routing - PUBLIC WORKS9/9/2011 9/9/2011 PASS
DetailsConnie Baumgartner
Routing - Addressing9/9/2011 9/9/2011 PASS
DetailsApril Wing
Routing PW Drainage9/9/2011 9/9/2011 PASS
DetailsBrian Murphy
Plans ACCEPTED BY PLAN TECH  9/8/2011 DONE
DetailsChristina Prado
Intake Approval  9/8/2011 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  9/8/2011 DONE
DetailsChristina Prado
Per Rita, all fees ok'd to be paid when permit is ready by contractor 9/8/11
Application received 9/8/2011