BLD-Final | 10/15/2012 | 10/15/2012 | 10/15/2012 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 10/15/2012 | 10/15/2012 | 10/15/2012 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 8/14/2012 | 8/14/2012 | 8/14/2012 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen
|
BLD-Conference | 8/10/2012 | 8/10/2012 | 8/13/2012 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen
|
BLD-Framing/Rough-in | 8/10/2012 | 8/10/2012 | 8/13/2012 | P | PART |
Dave Hannah
|
|
|
c/n on site ok to insulate
|
Plan resubmittals received | | | 8/6/2012 | | DONE |
|
|
|
new acca report
|
Routing - MECHANICAL | 8/6/2012 | | 8/6/2012 | | PASS |
Troy James
|
|
|
resubmitted new acca report
|
BLD-Wall Bracing | 7/27/2012 | 7/30/2012 | 7/30/2012 | A | PASS |
Dave Hannah
|
|
|
plans are on site now. Phone #: ###-#### >> Inspection requested via web by brandon waltman
|
BLD-Wall Bracing | 7/25/2012 | 7/27/2012 | 7/27/2012 | A | NR |
Tom Arcoraci
|
|
|
Shear inspection. Any issues please call Brandon at ###-#### Phone #: ###-#### >> Inspection requested via web by Braxton Hansen no approved plans on site
|
BLD-Foundation | 7/9/2012 | 7/10/2012 | 7/10/2012 | A | PASS |
Dave Hannah
|
|
|
CHRIS Phone #: ###-####
|
BLD-Footing | 7/6/2012 | 7/6/2012 | 7/6/2012 | P | PASS |
Dave Hannah
|
|
|
CHRIS Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/3/2012 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 6/13/2012 | | |
|
|
|
|
Plan assigned to (CDM) | 6/1/2012 | 6/1/2012 | 6/13/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/1/2012 | | 6/13/2012 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 6/13/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/13/2012 | | DONE |
|
|
|
|
Telephone call | | | 6/13/2012 | | DONE |
Christina Prado
|
|
|
Called Seth to advise permit is ready
|
Permit Ready to Issue | | | 6/13/2012 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 6/1/2012 | | DONE |
|
|
|
rec'd two new sets of plans for added rv bay, per carl only route to planning and building
|
Routing - PLANNING | 6/1/2012 | | 6/1/2012 | | PASS |
Joshua Johnson
|
|
|
|
Extend Review Timeline | | | 3/5/2012 | | DONE |
|
|
|
|
Telephone call | | | 3/2/2012 | | DONE |
|
|
|
left vm for seth re: expiration date of 3-12-12
|
Expiration Notice | 2/22/2012 | 3/14/2012 | 2/22/2012 | | DONE |
Patricia Smith
|
|
|
|
OVERRIDE | | | 10/4/2011 | | |
|
|
|
|
Plan assigned to (CDM) | | 9/14/2011 | 10/4/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/20/2011 | | 10/4/2011 | | PASS |
Carl D Madsen
|
|
|
|
Telephone call | | | 10/4/2011 | | DONE |
Tisha Gallop
|
|
|
called Seth and left vm permit is ready and fees.
|
1st review completed | | | 10/4/2011 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/4/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/4/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/4/2011 | | DONE |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 9/14/2011 | 9/19/2011 | 9/21/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | | | 9/20/2011 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/15/2011 | | 9/16/2011 | | PASS |
Joshua Johnson
|
|
|
|
Routing - Addressing | 9/14/2011 | | 9/15/2011 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 9/15/2011 | | 9/15/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/14/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 9/14/2011 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/14/2011 | | DONE |
Christina Prado
|
|
|
|
Application received | | 9/14/2011 | | | |
|
|
|
|