BLD-Aging Inspection | 11/25/2015 | 11/25/2015 | 11/30/2015 | | FAIL |
Jim Storey
|
|
|
doc expierd
|
DOC - Permit Expired | 11/30/2015 | 11/30/2015 | 11/30/2015 | A | PASS |
Jim Storey
|
|
|
ncfi
|
Issue PAID IN FULL permit | | | 6/8/2012 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 3/13/2012 | | DONE |
|
|
|
|
Meeting | | | 3/9/2012 | | DONE |
Tisha Gallop
|
|
|
received extension request, taken to JCB for review
|
Telephone call | | | 3/5/2012 | | DONE |
|
|
|
t/c w matt - reminded him that this permit will expire on the 13th - he said he would relay the information to the owner and see if he wants to submit an extension request
|
Expiration Notice | 2/23/2012 | 3/15/2012 | 2/23/2012 | | DONE |
Patricia Smith
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2011 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 10/24/2011 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 10/24/2011 | | DONE |
Christina Prado
|
|
|
Left message for Matt giving fees due and advising GC/RCE & RP required prior to issuance
|
Permit Ready to Issue | | | 10/24/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (LEG) Tisha | 9/15/2011 | | 10/24/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2011 | | 10/20/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 10/19/2011 | | 10/20/2011 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 10/20/2011 | | DONE |
Christina Prado
|
|
|
Received three copies of plan C-2, two inserted and the third placed inside set. Per Brian Murphy engineer will submit final 2 sets at a later time. Plan Routed back to Brian Murphy for review
|
Plan resubmittals received | | | 10/20/2011 | | DONE |
Christina Prado
|
|
|
Received final two c-2 forms and gave to Brian Murphy
|
Plan resubmittals received | | | 10/18/2011 | | DONE |
Tisha Gallop
|
|
|
received letter from Matt Munger/Eng. regarding Test Pit. Put with plans and rerouted to PW.
|
Routing - PLAN CHECK | 9/26/2011 | | 10/18/2011 | | PEND |
Tisha Gallop
|
|
|
received resubmittal; routed to PW
|
Telephone call | | | 9/27/2011 | | DONE |
Tisha Gallop
|
|
|
called Matt and told him need to resubmit with O & M.
|
1st review completed | | | 9/26/2011 | | FAIL |
|
|
|
Failed Public Works.
|
Routing - FIRE | 9/22/2011 | | 9/26/2011 | | PASS |
Scott Arellano
|
|
|
No comments attached. Plans are approved as shown.
|
Routing - PUBLIC WORKS | 9/16/2011 | | 9/22/2011 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Brian Murphy
|
Routing - Erosion and Sediment | 9/22/2011 | | 9/22/2011 | | PASS |
Clint A Smith
|
|
|
ESC11-00669 plan approved with conditions attached to the permit.
|
Routing - PLANNING | 9/22/2011 | | 9/22/2011 | | PASS |
Cody Riddle
|
|
|
|
Routing PW Drainage | 9/19/2011 | | 9/22/2011 | | FAIL |
Brian Murphy
|
|
|
NEED O AND M
|
Application received | | 9/15/2011 | 9/16/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING Land Div | 9/16/2011 | | 9/16/2011 | | PASS |
Dave Abo
|
|
|
Lot 1, Block 1 of Broadway Place Subdivision.
|
Case Summary (BLD) | | | 9/16/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 9/16/2011 | | 9/16/2011 | | PASS |
April Wing
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/15/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/15/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 9/15/2011 | | PASS |
Tisha Gallop
|
|
|
|