FIRE-Final Inspection | 2/6/2012 | 2/7/2012 | 2/7/2012 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
Permanent Occupancy | | | 2/7/2012 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 1/26/2012 | 1/27/2012 | 1/27/2012 | A | PASS |
Dave Hannah
|
|
|
susan Phone #: ###-####
|
BLD-Framing/Rough-in | 11/22/2011 | 11/22/2011 | 11/22/2011 | P | PASS |
Dave Hannah
|
|
|
Susan-ok to cover inspecion Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 11/22/2011 | 11/22/2011 | 11/22/2011 | A | NH |
Forrest France
|
|
|
|
BLD-Framing/Rough-in | 11/18/2011 | 11/18/2011 | 11/18/2011 | A | PART |
Dave Hannah
|
|
|
patricia - please call 1/2 hr prior Phone #: ###-#### ok to insulate ok to cover int wall and ceiling
|
BLD-Framing/Rough-in | 11/17/2011 | 11/17/2011 | 11/18/2011 | P | CANC |
Dave Hannah
|
|
|
patricia - please call 1/2 hr prior Phone #: ###-####
|
BLD-Conference | 11/8/2011 | 11/8/2011 | 11/8/2011 | A | DONE |
Dave Hannah
|
|
|
Susan @ ###-#### for ADA stuff
|
Received Certificate of Value | | | 11/3/2011 | | |
|
|
|
|
Print Occupancy Form | | | 10/26/2011 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 10/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 10/26/2011 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 10/26/2011 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/11/2011 | 10/14/2011 | 10/25/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 9/28/2011 | 10/3/2011 | 10/25/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 10/13/2011 | | 10/25/2011 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/25/2011 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/28/2011 | | 10/25/2011 | | PASS |
Carl Westfall
|
|
|
R. GREY LOFTS #212 (DESEELHORST LOFT) (20 days - Oct. 24)
|
Plan resubmittals received | | | 10/17/2011 | | DONE |
|
|
|
10-17-11 received 1 transmittal,1 comments response,and 2 copies of sheets A-1,A-2 sent to Carl W.
|
Routing - FIRE | 10/11/2011 | 10/11/2011 | 10/13/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 10/13/2011 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 9/29/2011 | | 10/11/2011 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on Oct. 6 and finished on Oct. 11. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 9/28/2011 | | 9/29/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Plan Reviewer's activity | | | 9/28/2011 | | DONE |
Jason Blais
|
|
|
Emailed Joe Thompson to have him contact ACHD for evaluation of any impact fees. Our Permit Counter will need written verification prior to permit issuance.
|
Pending Assignment by JCB | 9/27/2011 | | 9/28/2011 | | DONE |
Jason Blais
|
|
|
|
Application received | | 9/27/2011 | 9/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 9/27/2011 | | PASS |
Carl Westfall
|
|
|
OK to submit for permit.
|
Recd Pcfee & Taken To Pln CK | | | 9/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 2/17/2012 | | | |
|
|
|
|
Routing - MECHANICAL | | | | | DONE |
|
|
|
According to Troy, "OK to issue withoug mechanical review at this time. I will address mechanical some time before rough inspection."
|