Information based on query as of Friday, July 5, 2024.
Permit Information
Permit NumberBLD11-02349
StatusFinaled
Name KREIZENBECK CONSTRUCTORS
Site Address 11724 W EXECUTIVE DR
Project NameKREIZENBECK CONSTRUCTORS
Customer Number 
ePlanReviewNo
Description
(KREIZENBECK CONSTRUCTORS – Executive Center) Permit to build out offices into existing warehouse space. Newly created space will be used for offices and accessory uses. Work to include: construction of interior nonbearing walls to define four new offices and a storage room, installation of new doors and hardware as indicated on plans, installation of new electrical, installation of new mechanical ducting, and installation of interior finishes in compliance with chapter 8 of the IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 1/22/20121/17/2012 DONE
This permit finaled on the web by Brandon Byington
Second Notice 1/13/20121/17/2012 DONE
First Notice 12/23/20111/3/2012 DONE
Permanent Occupancy  12/13/2011 DONE
DetailsChristina Prado
BLD-Final12/8/201112/8/201112/8/2011PPASS
DetailsMike Jordan
Mike Phone #: ###-####. ok for perm occ.
FIRE-Final Inspection12/7/201112/8/201112/8/2011APASS
DetailsTroy Cobbley
life safety passed
BLD-Energy code compliance11/28/201111/28/201111/28/2011PPASS
DetailsMike Jordan
Mike please call before going out Phone #: ###-####
BLD-Framing/Rough-in11/18/201111/21/201111/21/2011APASS
DetailsMike Jordan
mike - late morning - please call 1/2 hr prior so he can meet you there Phone #: ###-####. Interior steel stud walls only. No grid.
Plan assigned to (TLW)9/29/2011 11/17/2011 PASS
DetailsTim L. Woodard
Routing - PLANNING11/8/2011 11/17/2011 PASS
DetailsSue Cummings
Needs to wait until the appeal period has lapsed. Please do not issue until 11/17/11. Passed! 11/17/11 SAC
Routing - PLAN CHECK11/9/2011 11/17/2011 PASS
DetailsTim L. Woodard
Approved with resubmittals recieved on 10-7-11 via email and Planning approval above. TLW
PLANS/APPL TAKEN TO FRONT DESK  11/17/2011 DONE
DetailsTim L. Woodard
Case Summary (BLD)  11/17/2011 DONE
DetailsTim L. Woodard
Print Occupancy Form  11/17/2011 DONE
Telephone call  11/17/2011 DONE
DetailsChristina Prado
Called and gave Mike fees due
Permit Ready to Issue  11/17/2011 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  11/17/2011 DONE
DetailsTisha Gallop
Routing - PLAN CHECK9/29/2011 10/6/2011 PASS
DetailsTim L. Woodard
Refer to redlines and plan review report. TLW
1st review completed  10/6/2011 DONE
DetailsTim L. Woodard
Routing - PLANNING10/6/2011 10/6/2011 FAIL
DetailsTim L. Woodard
Checked with front desk planner Colleen Carrol. This zone requires a CU for greater than 20 % office. TLW
Plans ACCEPTED BY PLAN TECH  9/29/2011 DONE
DetailsChristina Prado
Intake Approval  9/29/2011 PASS
DetailsTim L. Woodard
Recd Pcfee & Taken To Pln CK  9/29/2011 DONE
DetailsChristina Prado
Application received 9/29/2011