Print Statement | | | 3/16/2012 | | DONE |
|
|
|
|
Second Notice | | 2/26/2012 | 3/1/2012 | | DONE |
|
|
|
|
First Notice | | 2/6/2012 | 2/16/2012 | | DONE |
|
|
|
|
Zoning Approval | 1/27/2012 | 1/27/2012 | 1/27/2012 | | PASS |
David Moser
|
|
|
|
Permanent Occupancy | | | 1/27/2012 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 1/25/2012 | 1/26/2012 | 1/26/2012 | A | PASS |
Forrest France
|
|
|
Fire life safety passed. Contractor to post max. occupant sign prior to structural final.
|
BLD-Final | 1/25/2012 | 1/26/2012 | 1/26/2012 | P | PASS |
Dave Hannah
|
|
|
Doug Phone #: ###-####
|
FIRE-Conference | 1/25/2012 | 1/25/2012 | 1/25/2012 | P | DONE |
Forrest France
|
|
|
Regarding project related fire alarm and sprinkler permit finals.
|
FIRE-Sprinkler Rough-in | 1/12/2012 | 1/12/2012 | 1/12/2012 | P | PART |
Forrest France
|
|
|
Fire sprinkler work okay to cover at the storage room, coat room, and vestibule ceilings.
|
Routing - PLANNING Land Div | 1/9/2012 | | 1/9/2012 | | PASS |
Todd Tucker
|
|
|
ROS11-00039 Parcel Consolidation has been recorded and finaled. Certificate of Occupancy may be issued.
|
FIRE-Sprinkler Rough-in | 1/4/2012 | 1/4/2012 | 1/4/2012 | P | PART |
Forrest France
|
|
|
Fire sprinkler work at the banquet room soffit and grid ceilings and the prep room okayed for cover.
|
BLD-Framing/Rough-in | 11/14/2011 | 11/14/2011 | 11/15/2011 | P | PART |
Dave Hannah
|
|
|
doug Phone #: ###-#### needs to patch columns were fire proofing has been damaged and install 45deg kickers ok to cover soffits
|
Issue PAID IN FULL permit | | | 11/3/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/1/2011 | | 11/2/2011 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2011 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/2/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/2/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 11/2/2011 | | DONE |
Tisha Gallop
|
|
|
called Scott Stom and left vm permit is ready, fees, and need ACHD
|
Plan assigned to (CJW) | 9/29/2011 | | 11/2/2011 | | PASS |
Carl Westfall
|
|
|
COTTONWOOD GRILL - BANQUET ROOM EXPANSION (20 days - Oct. 26)
|
Routing - PLANNING Land Div | 10/31/2011 | | 11/2/2011 | | PASS |
Todd Tucker
|
|
|
Parcels need to be consolidated per Density Reduction Survey (4368). A new deed with a legal description for the parcels combined must be recorded with Ada County. A Certificate of Occupancy cannot be issued until the parcels have been combined.
|
1st review completed | | | 11/1/2011 | | FAIL |
|
|
|
Failed Plan Check and Land Division
|
Route to Impact Fee Review | 10/25/2011 | 10/28/2011 | 10/31/2011 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 10/28/2011 | | 10/31/2011 | | |
|
|
|
Routed to Land Division.
|
Plan resubmittals received | | | 10/31/2011 | | DONE |
Christina Prado
|
|
|
Received one transmittal letter; one response letter and two sets of plans marked G0.1, A0.1, A1.2, A3.1, and A3.2. Plans given to Carl Westfall for review.
|
Routing - FIRE | 10/25/2011 | 10/25/2011 | 10/28/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans. A manual Fire Alarm system is required in this Assembly Occcupancy.
|
Routing - PLAN CHECK | 10/4/2011 | | 10/25/2011 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on October 17, 2011 and finished on October 25, 2011. Revised drawings were required. See the plan review report.
|
Plan resubmittals received | | | 10/12/2011 | | DONE |
Christina Prado
|
|
|
Received two sets of plans marked G0.1, A1.2, A3.3 & A3.4 as well as one transmittal sheet. Given to Carl Westfall for review
|
Plan resubmittals received | | | 10/11/2011 | | DONE |
|
|
|
10-11-11 received 1 transmittal letter & 2 copies of sheets A1.2,A3.2 sent to Carl W.
|
Routing - PLUMBING | 10/3/2011 | | 10/4/2011 | | PASS |
Bill VanDegrift
|
|
|
Per plans and 2003 UPC.
|
Routing - PLANNING | 10/4/2011 | | 10/4/2011 | | PASS |
David Moser
|
|
|
David Moser - CUP11-00070
|
Routing - PUBLIC WORKS | 9/30/2011 | | 10/3/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 9/30/2011 | | 9/30/2011 | | PASS |
Terry Records
|
|
|
|
Routing PW Sewer Rating | 9/30/2011 | | 9/30/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 9/30/2011 | | 9/30/2011 | | PASS |
Walt Baumgartner
|
|
|
Addition of banquet room, existing GI serves kitchen, OK
|
Plan Reviewer's activity | | | 9/29/2011 | | DONE |
Jason Blais
|
|
|
Emailed architect to contact ACHD for evaluation of any impact fees. Written verification from ACHD needs to be provided to our Permit Counter prior to permit issuance.
|
Plans ACCEPTED BY PLAN TECH | | | 9/29/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 9/29/2011 | | PASS |
Dan Stuart
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/29/2011 | | DONE |
Christina Prado
|
|
|
|
Pending Assignment by JCB | 9/29/2011 | | 9/29/2011 | | DONE |
Jason Blais
|
|
|
|
Application received | | 9/29/2011 | | | |
|
|
|
|