BLD-Conference | 12/28/2015 | 12/28/2015 | 12/28/2015 | P | DONE |
Mike Jordan
|
|
|
Need to know if Apria Healthcare is occuping the space. Brittany at permits. Tenant still in space.
|
Permanent Occupancy | | | 12/28/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/28/2015 | | DONE |
|
|
|
|
BLD-Final | 12/20/2011 | 12/20/2011 | 12/20/2011 | P | PASS |
Mike Jordan
|
|
|
matt Phone #: ###-####. OK for eprm occ.
|
FIRE-Final Inspection | 12/19/2011 | 12/20/2011 | 12/20/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Other | 12/14/2011 | 12/14/2011 | 12/14/2011 | P | PASS |
Mike Jordan
|
|
|
Matt, Ceiling grid insp. Phone #: ###-#### >> Inspection requested via web by Richard Schultz
|
Telephone call | | | 12/8/2011 | | |
|
|
|
|
FIRE-Conference | 12/6/2011 | 12/7/2011 | 12/7/2011 | P | DONE |
Troy Cobbley
|
|
|
Matt and I discussed the IFC chapter 27 fire sprinkler requirements for this project.
|
BLD-Wall cover | 11/28/2011 | 11/28/2011 | 11/28/2011 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-#### >> Inspection requested via web by Richard Schultz
|
BLD-Framing/Rough-in | 11/18/2011 | 11/21/2011 | 11/21/2011 | P | PASS |
Mike Jordan
|
|
|
Call Matt, Thanks Phone #: ###-#### >> Inspection requested via web by Richard Schultz. Interior steel stud framed walls only. No grid .
|
Issue PAID IN FULL permit | | | 11/17/2011 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 9/30/2011 | | 11/16/2011 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 11/10/2011 | | 11/16/2011 | | PASS |
Dan Stuart
|
|
|
Alternate Request approved by Fire Marshall & Building Official. routing to permit desk to issue permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2011 | | PASS |
|
|
|
Approved based on attached Alternate Request approval by Fire Marshall & Building Official.
|
Print Occupancy Form | | | 11/16/2011 | | DONE |
|
|
|
|
Telephone call | | | 11/16/2011 | | DONE |
Christina Prado
|
|
|
called and gave Matt fees due and advised on GC/RCE requirements
|
Permit Ready to Issue | | | 11/16/2011 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 11/7/2011 | | 11/10/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 10/25/2011 | | 11/7/2011 | | FAIL |
Dan Stuart
|
|
|
Routed to fire code analyst for re-review.
|
Plan resubmittals received | | | 10/25/2011 | | DONE |
Christina Prado
|
|
|
received three sets of plans marked A2.0. Given to Dan Stuart for review
|
1st review completed | | | 10/25/2011 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Routing - FIRE | 10/19/2010 | | 10/25/2011 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
Plan resubmittals requested | | | 10/19/2011 | | DONE |
|
|
|
E-mailed copy of [plan review to architect for response resubmittals.
|
Routing - PLAN CHECK | 9/30/2011 | | 10/19/2011 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Plans routed to fire code analyst for review.
|
Pending Assignment by JCB | 9/30/2011 | | 9/30/2011 | | DONE |
Jason Blais
|
|
|
|
Application received | | 9/29/2011 | 9/29/2011 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/29/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/29/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 9/29/2011 | | PASS |
Dan Stuart
|
|
|
|