FIRE-Final Inspection | 11/2/2011 | 11/3/2011 | 11/3/2011 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 11/2/2011 | 11/3/2011 | 11/3/2011 | P | PASS |
Mike Jordan
|
|
|
Dwayne Dayley Phone #: ###-####. OK for perm occ.
|
Permanent Occupancy | | | 11/3/2011 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 10/19/2011 | 10/20/2011 | 10/20/2011 | P | CANC |
Jim Storey
|
|
|
Dwayne-PLease call at least 30 mins prior to inspection Phone #: ###-#### fire insp. call and had a list of c/n needed. no insp. performed until fire is resolved.
|
FIRE-Final Inspection | 10/19/2011 | 10/20/2011 | 10/20/2011 | A | FAIL |
Troy Cobbley
|
|
|
Repair the exit signs and emergency lighting on the first floor. Provide exit signs and emergency lighting for the main lobby. Provide exit signs and emergency lighting for the second floor. Provide monitoring for the fire sprinkler monitoring panel that has been disabled. Provide sprinkler modifications for the blocked and painted sprinkler heads. Provide resubmitted plans with floor layout that matches.
|
Issue PAID IN FULL permit | | | 10/19/2011 | | DONE |
Barbara Stitt
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/17/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 10/17/2011 | | DONE |
|
|
|
|
Telephone call | | | 10/17/2011 | | DONE |
|
|
|
t/c w dwayne - permit ready
|
Permit Ready to Issue | | | 10/17/2011 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 10/5/2011 | | 10/17/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 10/10/2011 | | 10/17/2011 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 10/10/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 10/7/2011 | | 10/10/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 10/10/2011 | | 10/10/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Case Summary (BLD) | | | 10/7/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Environmental | 10/7/2011 | | 10/7/2011 | | PASS |
Walt Baumgartner
|
|
|
Machine shop operation, OK. Will get pretreatment environmental inspection once in operation.
|
Routing - PLAN CHECK | 10/5/2011 | | 10/7/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/5/2011 | | DONE |
|
|
|
ok per Tim W to take in ///dld
|
First Notice | | 11/13/2011 | | | |
|
|
|
|
Application received | | 10/5/2011 | | | |
|
|
|
|