BLD-Final | 7/11/2012 | 7/12/2012 | 7/12/2012 | P | PASS |
Mike Jordan
|
|
|
Panic hardware installed. Ok for perm occ.
|
Permanent Occupancy | | | 7/12/2012 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 7/9/2012 | 7/11/2012 | 7/11/2012 | P | NR |
Mike Jordan
|
|
|
james Phone #: ###-####. Waiting for panic hardware on front door, on order. All other issues hace been resolved.
|
BLD-Final | 7/10/2012 | 7/10/2012 | 7/10/2012 | P | FAIL |
Mike Jordan
|
|
|
Still needs to remove locking device from rear door and provide panic hardware at main entry door. All other issues hace been resolved. Issued 48 hour notice to have remaining issues repaired.
|
BLD-Final | 7/2/2012 | 7/9/2012 | 7/9/2012 | P | FAIL |
Mike Jordan
|
|
|
Talk to Jim Sly. Needs to install grab bars and correct door hardware at main entry, back door and womens restroom. Needs to be repaired by 7-10-12 or a 48 hr. notice will be issiued.
|
BLD-Final | 6/29/2012 | 7/2/2012 | 7/2/2012 | A | DEFR |
Jim Sly
|
|
|
James Phone #: ###-#### Extend Permit 7days.....Re-insp Mon 9th PM
|
Change Expiration Date Only | | | 7/2/2012 | | DONE |
Barbara Stitt
|
|
|
Jim Sly extended expiration out till Mike Jordan is back from vacation
|
Change Expiration Date Only | | | 6/4/2012 | | DONE |
Barbara Stitt
|
|
|
Per MIke Jordan's notes on final inspection of 6-1-12 ok to extend 30 days for temp occupancy
|
BLD-Final | 6/1/2012 | 6/1/2012 | 6/1/2012 | P | PART |
Mike Jordan
|
|
|
Colton Phone #: ###-####. Ok to extend temp occ for 30 days. Mech. permit has been pulled.
|
BLD-Conference | 5/18/2012 | 5/21/2012 | 5/21/2012 | A | DONE |
Mike Jordan
|
|
|
Nees to pull permit for mechanical work done and get inspected. Will give 30 day extension after this has been completed.
|
BLD-Conference | 5/17/2012 | 5/18/2012 | 5/18/2012 | P | PASS |
Mike Jordan
|
|
|
steve call for access Phone #: ###-####
|
BLD-Framing/Rough-in | 3/26/2012 | 3/27/2012 | 3/27/2012 | P | NR |
Dave Hannah
|
|
|
adnan Phone #: ###-#### needs rough ins first they have changed the wall layout by two feet this will give them two full wemans rest room ok to put high low drinking fountain on wall in area between two wemans resroom
|
BLD-Final | 3/6/2012 | 3/7/2012 | 3/6/2012 | A | PART |
Mike Jordan
|
|
|
Ok for temp occ as per letter from building official on file.
|
Temporary Occupancy | 3/6/2012 | 6/4/2012 | 3/6/2012 | | DONE |
Christina Prado
|
|
|
|
BLD-Conference | 2/28/2012 | 2/29/2012 | 2/29/2012 | A | DONE |
Mike Jordan
|
|
|
adnan Phone #: ###-####
|
FIRE-Final Inspection | 2/27/2012 | 2/27/2012 | 2/27/2012 | P | PASS |
Forrest France
|
|
|
Correction items finished with the exception of single motion hardware at the back storage exit door. Lever set has been installed but does not meet a fail safe condition- tenant to provide approved style hardware at this location prior to structural final as agreed.
|
FIRE-Final Inspection | 1/25/2012 | 1/26/2012 | 1/26/2012 | A | FAIL |
Troy Cobbley
|
|
|
See redline notes on plans for deficiencies. They include providing a code compliant address, mounting and tagging the fire extinguishers, providing panic hardware at the main exit and providing single action hardware on the rear Storage exit door and remobing the 2x6 dead bolt/bar. There is an existing basic fire alarm system that consists of two manual pull stations and one horn. Per Scott Arellano its existance is to be noted and is ok to remain.
|
Route to Impact Fee Review | 1/20/2012 | 1/25/2012 | 1/25/2012 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement
|
Plan assigned to (DRS) | 1/9/2012 | 1/9/2012 | 1/25/2012 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 1/23/2012 | | 1/25/2012 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2012 | | PASS |
|
|
|
|
Print Occupancy Form | | | 1/25/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/25/2012 | | DONE |
|
|
|
|
Telephone call | | | 1/25/2012 | | |
|
|
|
1-25-12 called Bill permit ready and fee given . Also need ACHD
|
Print Occupancy Form | | | 1/25/2012 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/25/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 1/20/2012 | 1/20/2012 | 1/23/2012 | | PASS |
Scott Arellano
|
|
|
|
1st review completed | | | 1/23/2012 | | DONE |
|
|
|
Passed
|
Routing - PLAN CHECK | 1/10/2012 | | 1/20/2012 | | PASS |
Dan Stuart
|
|
|
Resubmittals not required.Routing to fire code analyst for review.
|
Routing - Addressing | 1/9/2012 | | 1/10/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 1/10/2012 | | 1/10/2012 | | PASS |
Dan Stuart
|
|
|
Signed off on routing slip. I updated sign off
|
Routing - PLANNING | | | 1/10/2012 | | PASS |
Sue Cummings
|
|
|
Sue Cummings - CUP11-00062
|
Plan Reviewer's activity | | | 1/9/2012 | | DONE |
Jason Blais
|
|
|
Emailed architect regarding ACHD verification of impact fees or no impact fee due needs to be provided to our Permit Counter prior to the building permit being issued.
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/9/2012 | | PASS |
Dan Stuart
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2012 | | DONE |
Christina Prado
|
|
|
|
Pending Assignment by JCB | 1/9/2012 | | 1/9/2012 | | DONE |
Jason Blais
|
|
|
|
Application received | | 10/26/2011 | | | |
|
|
|
|