Third Follow up | | | 5/31/2012 | | DONE |
Tisha Gallop
|
|
|
received FV 5/23/12
|
Third Notice | | 3/30/2012 | 5/17/2012 | | DONE |
|
|
|
faxed to GC
|
Third Notice | | 3/15/2012 | 3/15/2012 | | DONE |
|
|
|
faxed to ESI
|
Third Notice | | 2/7/2012 | 3/1/2012 | | DONE |
|
|
|
faxed to ESI
|
Second Notice | | 1/27/2012 | 2/2/2012 | | DONE |
|
|
|
|
First Notice | | 1/16/2012 | 1/17/2012 | | DONE |
|
|
|
|
BLD-Final | 1/5/2012 | 1/6/2012 | 1/6/2012 | A | PASS |
Dave Hannah
|
|
|
bob Phone #: ###-####
|
Permanent Occupancy | | | 1/6/2012 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 12/13/2011 | 12/14/2011 | 12/14/2011 | A | PART |
Dave Hannah
|
|
|
bob Phone #: ###-#### ok for temp occ needs to install office wall and ada restroom signage
|
FIRE-Final Inspection | 12/13/2011 | 12/14/2011 | 12/14/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. The restroom and rear exit door hardware has been corrected. Building inspector will need to verify the door hardware/wall assembly for the office when installed as per discussion.
|
BLD-Final | 12/12/2011 | 12/13/2011 | 12/14/2011 | P | CANC |
Dave Hannah
|
|
|
bob Phone #: ###-####
|
Temporary Occupancy | 12/14/2011 | 3/13/2012 | 12/14/2011 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 12/12/2011 | 12/13/2011 | 12/13/2011 | P | FAIL |
Troy Cobbley
|
|
|
Repair or remove the non functioning emergency light. Dave will address the hardware issues at the rear exit door, restroom door and the missing glass wall/door office partition.
|
BLD-Framing/Rough-in | 11/30/2011 | 12/1/2011 | 12/1/2011 | A | PASS |
Dave Hannah
|
|
|
bob Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/22/2011 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 11/14/2011 | | DONE |
|
|
|
|
Telephone call | | | 11/14/2011 | | DONE |
Christina Prado
|
|
|
Called and gave Eric fees due and advised GC/RCE is needed
|
Permit Ready to Issue | | | 11/14/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 11/10/2011 | | 11/10/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 11/10/2011 | | 11/10/2011 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 11/10/2011 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 11/10/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 11/3/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 11/3/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | 10/28/2011 | | | |
|
|
|
|