Letter of compliance/Occupancy | | | 8/8/2012 | | DONE |
|
|
|
|
BLD-Grading Inspection | 8/6/2012 | 8/6/2012 | 8/6/2012 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved.
|
BLD-Final | 7/30/2012 | 7/30/2012 | 7/31/2012 | P | PEND |
Dave Hannah
|
|
|
chad Phone #: ###-#### ok for occ after terry records finals
|
BLD-Conference | 7/26/2012 | 7/27/2012 | 7/27/2012 | A | DONE |
Dave Hannah
|
|
|
Chad Phone #: ###-####
|
BLD-Energy code compliance | 4/10/2012 | 4/10/2012 | 4/10/2012 | P | DONE |
Dave Hannah
|
|
|
rollo Phone #: ###-####
|
BLD-Energy code compliance | 4/5/2012 | 4/9/2012 | 4/10/2012 | P | PASS |
Dave Hannah
|
|
|
Chad Phone #: ###-####
|
BLD-Framing/Rough-in | 4/5/2012 | 4/5/2012 | 4/5/2012 | P | PASS |
Dave Hannah
|
|
|
chad Phone #: ###-####
|
BLD-Other | 4/3/2012 | 4/4/2012 | 4/4/2012 | A | PASS |
Dave Hannah
|
|
|
chad Phone #: ###-#### sheet rock soffits and ligth cans ok
|
BLD-Other | 4/3/2012 | 4/3/2012 | 4/3/2012 | P | PART |
Dave Hannah
|
|
|
chad Phone #: ###-#### can light boxs and sheetrock soffits ok on that they have finished
|
BLD-Wall Bracing | 4/2/2012 | 4/2/2012 | 4/2/2012 | P | PASS |
Dave Hannah
|
|
|
shear insp//Chad Phone #: ###-####
|
BLD-Foundation | 2/14/2012 | 2/14/2012 | 2/14/2012 | A | PASS |
Dave Hannah
|
|
|
sean - wall insp Phone #: ###-####
|
BLD-Foundation | 2/13/2012 | 2/13/2012 | 2/14/2012 | P | PART |
Dave Hannah
|
|
|
sean - wall insp Phone #: ###-####
|
BLD-Footing | 2/9/2012 | 2/9/2012 | 2/10/2012 | P | PASS |
Dave Hannah
|
|
|
shawn Phone #: ###-####
|
PubWorks Subgrade Approval | 2/9/2012 | 2/9/2012 | 2/9/2012 | | DONE |
Terry Records
|
|
|
Footing subgrade approved by the geotechnical engineer
|
BLD-Footing | 2/7/2012 | 2/8/2012 | 2/8/2012 | P | NR |
Mike Jordan
|
|
|
shawn - pouring at 3 Phone #: ###-####. No record of geo-tech report being approved by Tedrry Records. Contractor was contacted. Will turn in report to terry for approval.
|
Plan Modification Accepted | | | 2/7/2012 | | DONE |
Scott Arellano
|
|
|
Per City Council ruling on Boulder Heights subdivision #1 dated 1/31/2012, subdivision plat note 19 has been eliminated. No general fire sprinkler requirement in Boulder heights subdivision phase #1 as per the Boise Fire Marshal.
|
Issue PAID IN FULL permit | | | 12/12/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CDM) | 11/14/2011 | 11/14/2011 | 12/5/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 11/21/2011 | | 12/5/2011 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 12/5/2011 | | DONE |
|
|
|
|
1st review completed | | | 12/5/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/5/2011 | | DONE |
|
|
|
|
Telephone call | | | 12/5/2011 | | DONE |
Christina Prado
|
|
|
Called and left message giving fees due and advising permit is ready
|
Permit Ready to Issue | | | 12/5/2011 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 11/25/2011 | | 11/25/2011 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 11/14/2011 | 11/17/2011 | 11/23/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 11/22/2011 | | 11/22/2011 | | FAIL |
Troy James
|
|
|
emailed corrections
|
Routing PW Grading-Hillside | 11/21/2011 | | 11/21/2011 | | PASS |
Terry Records
|
|
|
|
Routing - FIRE | 11/18/2011 | | 11/21/2011 | | PASS |
Scott Arellano
|
|
|
Per Subdivision Plat note #19, all homes in Boulder Heights Estates Subdivision Phase #1 shall be equipped with an automatic fire sprinkler system,designed in accordance with NFPA 13D.
|
Routing - Erosion and Sediment | 11/17/2011 | | 11/18/2011 | | PASS |
Clint A Smith
|
|
|
ESC11-00816 plan approved with conditions attached to the permit.
|
Routing - MECHANICAL | 11/15/2011 | | 11/17/2011 | | FAIL |
Troy James
|
|
|
emailed corrections to austin
|
Plan resubmittals received | | | 11/16/2011 | | DONE |
Tisha Gallop
|
|
|
received two copies of revised sheet 3 (engineered basement & foundation plan) and rescheck. Put with plans at Terry Records desk.
|
Routing - PLANNING | 11/14/2011 | | 11/15/2011 | | PASS |
Cody Riddle
|
|
|
CFH11-00020 Cody
|
Application received | | 11/14/2011 | 11/14/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | | | 11/14/2011 | | FAIL |
Terry Records
|
|
|
Foundation plan must be revised so that elevations of footings and walls are in the same datum as grading plan.
|
Routing - Addressing | 11/14/2011 | | 11/14/2011 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 11/14/2011 | | 11/14/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/14/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/14/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 11/14/2011 | | PASS |
Tisha Gallop
|
|
|
|