First Notice | 3/10/2014 | 3/10/2014 | 4/3/2014 | | DONE |
Jim Sly
|
|
|
old project
|
BLD-Final | 3/10/2014 | 3/10/2014 | 3/10/2014 | A | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 3/10/2014 | 3/10/2014 | 3/10/2014 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 5/3/2013 | 5/6/2013 | 5/6/2013 | A | PASS |
Jim Sly
|
|
|
bill Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 1/24/2013 | 1/25/2013 | 1/25/2013 | A | CANC |
Troy Cobbley
|
|
|
No life safety sign off required.
|
Zoning Approval | 1/25/2013 | 1/25/2013 | 1/25/2013 | | PASS |
Josh Wilson
|
|
|
|
BLD-Conference | 1/17/2013 | 1/18/2013 | 1/22/2013 | P | DONE |
Jim Sly
|
|
|
Bill Matter Phone #: ###-#### Need Zoning approval.
|
Print Occupancy Form | | | 1/16/2013 | | DONE |
Tisha Gallop
|
|
|
printed off insp record card when issued permit, supposed to have occ card.
|
BLD-Framing/Rough-in | 1/12/2012 | 1/13/2012 | 1/13/2012 | A | PASS |
Jim Sly
|
|
|
bill Phone #: ###-####
|
Plan assigned to (DRS) | 11/18/2011 | 11/18/2011 | 12/20/2011 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLANNING | 12/19/2011 | | 12/20/2011 | | PASS |
Josh Wilson
|
|
|
Changed steel latiice to red wood 2 x6 on edge and all wood frame roof structure on the steel supports. Ok JGW
|
Routing - PLAN CHECK | 12/20/2011 | | 12/20/2011 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2011 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 12/20/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/20/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 12/20/2011 | | DONE |
Tisha Gallop
|
|
|
called Matter Arch. and told Liz permit is ready and fees.
|
Issue PAID IN FULL permit | | | 12/20/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 12/13/2011 | | 12/19/2011 | | PASS |
Dan Stuart
|
|
|
Routing to Planning for review of proposed exterior changes to original submittals, i.e. 2 x 6 red wood lattice & wood roof structure.
|
Plan resubmittals received | | | 12/19/2011 | | DONE |
Tisha Gallop
|
|
|
received transmittal and three copies of plan sheets A0.0, A0.1, A0.2, A1, A2, A3, A4, A5; taken to Dan Stuart.
|
Routing Off Site - STRUCTURAL | 12/16/2011 | | 12/16/2011 | | PASS |
Dan Stuart
|
|
|
E-mailed copies of structural design engineer, Steve Cornwell, response to our Structural Plan review of 12/5/11 for re-review.
12/16/11- received e-mail response from structural plan review engineer approving the resubmittal details provided with no further action needed.
|
Telephone call | | | 12/16/2011 | | DONE |
|
|
|
With Bill Matter - Changing roof structure to wood truss system and lattice from tube steel to 2 x 6 redwood on edge at 6" o.c. Sending e-mail response for consideration before preparing resubmittal replacement plan drawings with changes.
|
1st review completed | | | 12/13/2011 | | FAIL |
|
|
|
Failed Structural, Plan Check
|
Routing - FIRE | 12/10/2011 | | 12/13/2011 | | PASS |
Scott Arellano
|
|
|
No seperate comments attached.
|
Routing - PLAN CHECK | 11/18/2011 | | 12/10/2011 | | FAIL |
Dan Stuart
|
|
|
Plans failed in outside structural plan review and building plan review due to lack of connections & fastener information on the plans.
|
Plan resubmittals requested | | | 12/6/2011 | | DONE |
|
|
|
Copy of strucural plan review e-mailed to architect for response & resubmittals.
|
Routing Off Site - STRUCTURAL | 11/18/2011 | | 12/5/2011 | | FAIL |
Dan Stuart
|
|
|
Structural Plan Review failed. Resubmittals required.
|
Application received | | 11/14/2011 | 11/18/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 11/18/2011 | | PASS |
|
|
|
Provide lnadscaping details on plans, provided zoning certificate app for phasing the work under DRH09-00246 & CUP09-00072 per Sarah Shafer & provide special inspection form #310 Project Start Up for Special Inspection with MTI listed as special inspection agency. To permit desk to take in.
|
Plans ACCEPTED BY PLAN TECH | | | 11/18/2011 | | DONE |
Tisha Gallop
|
|
|
Per Dan Stuart route to Planning, Fire and Plan Check.
|
Recd Pcfee & Taken To Pln CK | | | 11/18/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 11/18/2011 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Routing - PLANNING | 11/18/2011 | | 11/18/2011 | | PASS |
Josh Wilson
|
|
|
DRH09-00246
|
Intake Approval | | | 11/14/2011 | | FAIL |
|
|
|
Provide completed form #310 project start up for special inspection - welding and Landscaping plan for Planning based on DRH09-00246 and zoning certificate if planning approved data is changed per discussion with Sarah Schafer. Colleen Carroll provided zoning cert app. Brian Murphy reviewed for roof runoff - nothing required.
|