Second Notice | | 5/31/2012 | 6/7/2012 | | DONE |
|
|
|
|
First Notice | | 4/27/2012 | 5/17/2012 | | DONE |
|
|
|
faxed to GC
|
BLD-Final | 4/17/2012 | 4/17/2012 | 4/17/2012 | P | PASS |
Dave Hannah
|
|
|
Deven-Please call prior to inspection Phone #: ###-#### ok for perm occ
|
Permanent Occupancy | | | 4/17/2012 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 2/28/2012 | 2/29/2012 | 2/29/2012 | A | PART |
Dave Hannah
|
|
|
First thing -- Craig Phone #: ###-#### ok for temp occ needs to fix ada rest room and finish mec
|
FIRE-Final Inspection | 2/28/2012 | 2/29/2012 | 2/29/2012 | A | PASS |
Forrest France
|
|
|
Correction items verified for completion. Fire life safety inspection passed. * NOTE: Per general contractor and fire sprinkler contractor survey, head count in the building remains below 100. Therefore, conditions per the UFC under which the structure was built still apply regarding offsite monitoring.
|
FIRE-Final Inspection | 2/28/2012 | 2/28/2012 | 2/28/2012 | P | NR |
Forrest France
|
|
|
Pending ceiling tile installation, address numbers, project related FIR permit final. Exits and EM lights tested okay.
|
BLD-Other | 2/27/2012 | 2/27/2012 | 2/28/2012 | P | PASS |
Dave Hannah
|
|
|
Above ceiling --- Craig Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 2/16/2012 | 2/16/2012 | 2/16/2012 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler modifications at the grid ceilings approved for cover. Noted sprinkler head count in the building may now exceed 100.
|
BLD-Framing/Rough-in | 1/18/2012 | 1/19/2012 | 1/20/2012 | A | PASS |
Dave Hannah
|
|
|
deven Phone #: ###-#### ok to cover after elec and plumbing rough ins are completed
|
OVERRIDE | | | 1/18/2012 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/11/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 1/10/2012 | | DONE |
Darla L Downs
|
|
|
|
Routing - PLAN CHECK | 12/23/2011 | | 1/10/2012 | | PASS |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 1/10/2012 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2012 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 1/10/2012 | | DONE |
|
|
|
|
Telephone call | | | 1/10/2012 | | |
|
|
|
1-10-12 called Mike permit ready and fee given ,Also need RP & revised cert of value /// dld
|
CHANGE STATUS TO (ISS) | | | 1/10/2012 | | DONE |
Darla L Downs
|
|
|
|
Plan assigned to (SRZ) | 12/6/2011 | | 1/10/2012 | | PASS |
Sam Zahorka
|
|
|
Palm Beach Tan - December 23rd
1st review completed.
|
Plan resubmittals received | | | 1/6/2012 | | |
|
|
|
Received thru the mail a cover transmittal, plan review response comments from Lippe and Associates, Plan review comments from CamargoCopeland Architects LLP, 2 copes of sheets A0.0, A0.1, A2.1, A2.2, A2.5, A6.0, E1.0, E2.0 and taken to Sam Zahorka
|
Routing - PLAN CHECK | 12/12/2011 | | 12/23/2011 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - FIRE | 12/23/2011 | | 12/23/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Case Summary (BLD) | | | 12/23/2011 | | DONE |
Sam Zahorka
|
|
|
|
1st review completed | | | 12/23/2011 | | FAIL |
Scott Arellano
|
|
|
Failed Plan Check
|
Routing - PLUMBING | 12/9/2011 | | 12/12/2011 | | PASS |
Bill VanDegrift
|
|
|
1. Spray on tanning booths will be required to have a rpbp on potable water supply serving the 3 booths. ( 2 mystic and 1 versa).
2. All other plumbing to be installed per plans and 2003 UPC.
|
Routing - Design Review | 12/12/2011 | | 12/12/2011 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - minor exterior storefront window/door changes (front and rear) - Approved the storefront door swap as part of the building permit. SMS
|
Routing - Erosion and Sediment | 12/8/2011 | | 12/9/2011 | | PASS |
Clint A Smith
|
|
|
ESC11-00866 plan waiver approved with conditions attached to the permit.
|
Routing - Addressing | 12/7/2011 | | 12/8/2011 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 12/8/2011 | | 12/8/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 12/8/2011 | | 12/8/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Plan Reviewer's activity | | | 12/7/2011 | | DONE |
Jason Blais
|
|
|
Sent email to architect to have him contact ACHD for evaluation of any impact fees. Written verification from ACHD will need to be provided to our Permit Counter prior to the building permit being issued.
|
Pending Assignment by JCB | 12/5/2011 | | 12/6/2011 | | DONE |
Jason Blais
|
|
|
|
Application received | | 11/30/2011 | 12/5/2011 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/5/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/5/2011 | | PASS |
Dan Stuart
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/5/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 11/30/2011 | | FAIL |
|
|
|
Need 1) ESC App & Waiver request, fireflow sheet, 2) area of concrete floor to be demoed, 3) CISCA 0-2 details & notes, 4) Vertical grab bars, 5) location of fire extinguishers and 6) completed Statement of special Inspections form #310 (gave copy to Mike to get completed).
|