BLD-Final | 5/30/2012 | 5/30/2012 | 5/30/2012 | P | PASS |
Dave Hannah
|
|
|
dave, i had a moist spot under the vapor barrier, so i rolled the plastic back in a small section and put a fan on it to dry t out. I will re lay the small section tomorrow. thanks Phone #: ###-#### >> Inspection requested via web by John Dyche
|
DOC - Permit Finaled | 5/30/2012 | 5/30/2012 | 5/30/2012 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 4/4/2012 | 4/5/2012 | 4/5/2012 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Tony Luchini
|
BLD-Framing/Rough-in | 4/2/2012 | 4/3/2012 | 4/4/2012 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Tony Luchini ok to insulate two idem correction notice on site
|
Plan resubmittals received | | | 3/20/2012 | | DONE |
|
|
|
new acca report
|
Routing - MECHANICAL | 3/20/2012 | | 3/20/2012 | | PASS |
Troy James
|
|
|
resubmitted new manual j report
|
BLD-Foundation | 1/10/2012 | 1/11/2012 | 1/11/2012 | A | PASS |
Dave Hannah
|
|
|
bill Phone #: ###-####
|
BLD-Foundation | 1/6/2012 | 1/10/2012 | 1/10/2012 | A | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 1/6/2012 | 1/9/2012 | 1/10/2012 | P | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/3/2012 | | DONE |
|
|
|
|
Route to Impact Fee Review | 12/2/2011 | 12/7/2011 | 12/22/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Inspection Record Card- Bld | | | 12/22/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/22/2011 | | DONE |
|
|
|
|
Telephone call | | | 12/22/2011 | | |
|
|
|
12-22-11 called Tahoe Homes permit ready and fee given ///dld
|
Plan assigned to (CDM) | 12/2/2011 | 12/2/2011 | 12/21/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/8/2011 | | 12/21/2011 | | PASS |
Carl D Madsen
|
|
|
Carl Madsen
|
1st review completed | | | 12/21/2011 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/21/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2011 | | |
|
|
|
|
Routing - MECHANICAL | 12/7/2011 | | 12/8/2011 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 12/6/2011 | | 12/7/2011 | | FAIL |
Troy James
|
|
|
temp rise too high emailed travis
|
Routing - PLANNING | 12/6/2011 | | 12/6/2011 | | PASS |
Joshua Johnson
|
|
|
|
Routing - PUBLIC WORKS | 12/6/2011 | | 12/6/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/2/2011 | | 12/5/2011 | | PASS |
Terry Records
|
|
|
|
Application received | | 12/2/2011 | 12/2/2011 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/2/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/2/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/2/2011 | | PASS |
Barbara Stitt
|
|
|
|