BLD-Final | 12/28/2011 | 12/28/2011 | 12/28/2011 | P | PART |
Dave Hannah
|
|
|
Brian Phone #: ###-#### ok for temp occ ok for perm after they install doors and hardwear
|
FIRE-Final Inspection | 12/27/2011 | 12/28/2011 | 12/28/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory. Missing office doors and hardware to be installed prior to structural final as discussed.
|
BLD-Framing/Rough-in | 12/21/2011 | 12/22/2011 | 12/22/2011 | A | PASS |
Tom Arcoraci
|
|
|
Derek Phone #: ###-####
|
BLD-Wall cover | 12/21/2011 | 12/21/2011 | 12/21/2011 | P | PART |
Mike Jordan
|
|
|
Derek Phone #: ###-####. Needs to provide approved plans.
|
Print Occupancy Form | | | 12/19/2011 | | DONE |
|
|
|
|
Telephone call | | | 12/19/2011 | | DONE |
Christina Prado
|
|
|
Called and left message with Derek giving fees due
|
Permit Ready to Issue | | | 12/19/2011 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 12/19/2011 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 12/16/2011 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/16/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 12/16/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | | | 12/16/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 12/12/2011 | | 12/16/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 12/9/2011 | | 12/12/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/12/2011 | | 12/12/2011 | | PASS |
Terry Records
|
|
|
|
Routing PW Sewer Rating | 12/12/2011 | | 12/12/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 12/9/2011 | 12/9/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/9/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/9/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/9/2011 | | DONE |
Christina Prado
|
|
|
|