Third Notice | | 7/20/2012 | 7/23/2012 | | DONE |
|
|
|
|
Print Statement | | | 7/11/2012 | | DONE |
Tisha Gallop
|
|
|
|
Third Notice | | 6/12/2012 | 7/6/2012 | | DONE |
|
|
|
faxed to CM Co
|
Second Notice | | 5/26/2012 | 6/7/2012 | | DONE |
|
|
|
|
First Notice | | 4/26/2012 | 5/16/2012 | | DONE |
Christina Prado
|
|
|
faxed 5-16-12
|
Permanent Occupancy | | | 4/16/2012 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 4/12/2012 | 4/13/2012 | 4/13/2012 | A | PASS |
Dave Hannah
|
|
|
dan Phone #: ###-#### ok for perm occ--per Dave Hannah NO PLUMBING REQUIRED//BAS 4-16-12
|
FIRE-Final Inspection | 2/23/2012 | 2/23/2012 | 2/24/2012 | P | PASS |
Forrest France
|
|
|
|
FIRE-Final Inspection | 2/22/2012 | 2/22/2012 | 2/22/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed acceptable.
|
FIRE-Conference | 2/21/2012 | 2/21/2012 | 2/22/2012 | P | DONE |
Forrest France
|
|
|
Completed EM light testing, noted two non-functional lights and one exit sign. Walkthrough completed for fire sprinkler coverage. PFE's okay.
|
BLD-Framing/Rough-in | 2/13/2012 | 2/14/2012 | 2/14/2012 | A | PART |
Dave Hannah
|
|
|
Gus Phone #: ###-#### beams and columns changes need new engineering
|
BLD-Framing/Rough-in | 1/26/2012 | 1/27/2012 | 1/30/2012 | P | PART |
Dave Hannah
|
|
|
gus Phone #: ###-#### office walls ok to cover
|
Permit Ready to Issue | | | 1/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 1/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 1/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 1/6/2012 | | 1/6/2012 | | PASS |
Tim L. Woodard
|
|
|
Plans approved with resubmittals. Attached to plans is the Plan Review Report with three field verify items. TLW
|
1st review completed | | | 1/6/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/6/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Inspection Record Card- Bld | | | 1/6/2012 | | DONE |
|
|
|
|
Telephone call | | | 1/6/2012 | | DONE |
Tisha Gallop
|
|
|
called Matthew Witt; need final value for Bld10-02963 before will issue this permit. Ok'd by Rita.
|
Plan assigned to (TLW) | | | 1/6/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 1/5/2012 | | |
|
|
|
Received cover letter to Tim Woodard dated 1-4-12 from Matthew Witt, 2 copies of sheet A2.0 and taken to Tim Woodard
|
Routing - PLAN CHECK | 12/21/2011 | | 12/28/2011 | | FAIL |
Tim L. Woodard
|
|
|
Refer to attached Plan Review Report. TLW
|
1st review completed | | | 12/28/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/21/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/21/2011 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/21/2011 | | DONE |
Christina Prado
|
|
|
|
Routing - PUBLIC WORKS | 12/21/2011 | | 12/21/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/21/2011 | | 12/21/2011 | | PASS |
Terry Records
|
|
|
|
Routing PW Sewer Rating | 12/21/2011 | | 12/21/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 12/21/2011 | | | |
|
|
|
|