Print Statement | | | 3/22/2012 | | DONE |
Rita DeYoung
|
|
|
|
First Notice | | 3/9/2012 | 3/15/2012 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/28/2012 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 2/27/2012 | 2/27/2012 | 2/27/2012 | P | PASS |
Jim Storey
|
|
|
paul - is taking card to ACHD to get signed in time for final inspection Phone #: ###-####
|
FIRE-Final Inspection | 2/27/2012 | 2/27/2012 | 2/27/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
FIRE-Alarm Testing | 2/24/2012 | 2/27/2012 | 2/27/2012 | A | DONE |
Forrest France
|
|
|
Completed testing for the two duct smoke detectors associated with the relocated RTU's.
|
BLD-Other | 2/24/2012 | 2/24/2012 | 2/24/2012 | P | PASS |
Jim Storey
|
|
|
Ceiling grid - wall clips corrected / /hvac duct corrected / foam insulation to be removed. Please schedule inspection around 2 - 2:30... Phone #: ###-#### >> Inspection requested via web by Paul Saucerman
|
BLD-Other | 2/23/2012 | 2/23/2012 | 2/23/2012 | P | FAIL |
Jim Storey
|
|
|
paul - ceiling grid Phone #: ###-#### missing wall clips/ foam insulation must meet 25/450 or be covered / hvac duct support not to sprinkler line must go to structure.
|
BLD-Conference | 2/2/2012 | 2/2/2012 | 2/2/2012 | A | PASS |
Jim Storey
|
|
|
call contractor and told him to hold on plm walls plm aproved in error.
|
BLD-Framing/Rough-in | 1/31/2012 | 2/1/2012 | 2/1/2012 | P | PASS |
Jim Storey
|
|
|
Rough framing inspection - permit plans on site and code to lock box on door is 1040. Phone #: ###-#### >> Inspection requested via web by Paul Saucerman
|
Issue PAID IN FULL permit | | | 1/19/2012 | | DONE |
|
|
|
|
Routing - FIRE | 1/12/2012 | 1/12/2012 | 1/17/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 1/17/2012 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 1/17/2012 | | 1/17/2012 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/17/2012 | | PASS |
|
|
|
|
Print Occupancy Form | | | 1/17/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/17/2012 | | |
|
|
|
|
Telephone call | | | 1/17/2012 | | DONE |
|
|
|
1-17-12 called Scott permit ready and fee given . Also need GC & ACHD ///dld
|
Plan assigned to (DRS) | 12/22/2011 | | 1/17/2012 | | PASS |
Dan Stuart
|
|
|
|
Route to Impact Fee Review | 1/12/2012 | 1/17/2012 | 1/12/2012 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 12/27/2011 | | 1/12/2012 | | PASS |
Dan Stuart
|
|
|
Resubmittals are not required. Approved as noted on plans and attached plan review comments / conditions. Routing to fire code analyst.
|
Routing - PUBLIC WORKS | 12/27/2011 | | 12/27/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/22/2011 | | 12/27/2011 | | PASS |
Terry Records
|
|
|
|
Routing PW Sewer Rating | 12/27/2011 | | 12/27/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 12/21/2011 | | 12/22/2011 | | DONE |
Jason Blais
|
|
|
|
Application received | | 12/21/2011 | 12/21/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/21/2011 | | PASS |
Carl Westfall
|
|
|
OK to submit for permit.
|
Recd Pcfee & Taken To Pln CK | | | 12/21/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/21/2011 | | DONE |
Barbara Stitt
|
|
|
|