Second Notice | | 4/8/2012 | 4/16/2012 | | DONE |
Christina Prado
|
|
|
complete 4-10-12
|
First Notice | 3/15/2012 | 3/26/2012 | 3/29/2012 | | DONE |
Mike Jordan
|
|
|
faxed 3-29-2012
|
BLD-Final | 3/14/2012 | 3/15/2012 | 3/15/2012 | A | PASS |
Mike Jordan
|
|
|
Stu Phone #: ###-####
|
DOC - Permit Finaled | 3/15/2012 | 3/15/2012 | 3/15/2012 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 3/13/2012 | 3/14/2012 | 3/14/2012 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. wire shelving is provided
|
FIRE-Final Inspection | 3/12/2012 | 3/13/2012 | 3/13/2012 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the Demo/shell permit has been inspected/finaled. I will be meeting Joe with J and B Construction in the morning.
|
FIRE-Conference | 3/6/2012 | 3/7/2012 | 3/7/2012 | A | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with general contractor. There is an issue with solid shelving on the large storage racks. Also per Tim Frost racking was not addressed with the sprinkler plans but what I described to him over the phone he was ok with as long as the storage did not exceed 12' in height.
|
Issue PAID IN FULL permit | | | 1/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2012 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 1/6/2012 | | DONE |
Sam Zahorka
|
|
|
|
Inspection Record Card- Bld | | | 1/6/2012 | | DONE |
|
|
|
|
Telephone call | | | 1/6/2012 | | DONE |
Christina Prado
|
|
|
Called and gave Steven fees due
|
Permit Ready to Issue | | | 1/6/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 12/22/2011 | | 1/6/2012 | | PASS |
Sam Zahorka
|
|
|
Level 2 TI (Racking)
1st review completed.
|
Plan resubmittals received | | | 1/5/2012 | | DONE |
Tisha Gallop
|
|
|
received one copy of Statement of Special Inspections; taken to Sam Zahorka.
|
Telephone call | | | 1/3/2012 | | DONE |
Sam Zahorka
|
|
|
Spoke with the engineer and emailed Statement of Special Inspection form. He stated he would fill out and email back to me.
|
Routing - PLAN CHECK | 12/28/2011 | | 12/29/2011 | | PASS |
Sam Zahorka
|
|
|
Pending the submittal of the Statement of Special Inspection #310 for Special Inspection.
|
Routing - PLAN CHECK | 12/22/2011 | | 12/28/2011 | | PASS |
Sam Zahorka
|
|
|
|
Routing - FIRE | 12/28/2011 | | 12/28/2011 | | PASS |
Scott Arellano
|
|
|
Total High Piled Storage (HPS) is less than 500 square feet. No separate HPS comments attached.
|
1st review completed | | | 12/28/2011 | | PASS |
|
|
|
|
Application received | | 12/22/2011 | 12/22/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/22/2011 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/22/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/22/2011 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCB | 12/22/2011 | | 12/22/2011 | | DONE |
Jason Blais
|
|
|
|