Permit Information
Permit NumberBLD11-03016
StatusFinaled
Name PINNACLE INVESTMENTS LTD
Site Address 2039 W AIRPORT WAY
Project NameHERTZ CARWASH ADDITION
Customer Number 
ePlanReviewNo
Description
HERTZ CARWASH ADDITION - ***2/14/2012 PLAN MODIFICATION TO INCLUDE: ADD A FUEL ISLAND WITH A PRE-ENGINEERED CANOPY STRUCTURE TO BE USED TO FUEL RENTAL AUTOMOBILES. WORK TO INCLUDE: ADD A 24' X 24' CONCRETE PAD; A 4' X 6' CONCRETE ISLAND FOR FUTURE PUMP MOUNTING; AND A 24' X 24' X 3' PRE-ENGINEERED CANOPY STRUCTURE RESTING ON TWO STEEL COLUMNS AT 14'-6" ABOVE GRADE. ALL WORK PER THE APPROVED PLANS, ENGINEERING AND ALL OTHER REVIEWING AGENCIES APPROVALS. SRZ*** To construct a total of 1,384 additional square feet to an existing 9,528 square foot, two story, commercial building to include a 41'-4" X 30', 1,240 square foot, one story, two lane carwash bay and a 12' X 12', 144 square foot, one story equipment room. The two lane carwash bay extension will be added to the South East corner and the equipment room will be added to the North West corner. The additions will be constructed of 8" CMU exterior walls and pre-engineered roof trusses with membrane roofing. This permit also includes related site improvements. All construction per the approved plans, attached plan review comments, engineering, and conditions of all reviewing agencies for this project. A new Certificate of Occupancy with the new occupant load total is to be issued when completed and approved. This building includes a non-required /partial Fire Sprinkler system. ANY ALTERATIONS TO THE SPRINKLER SYSTEM WILL REQUIRE A SEPARATE PERMIT, and shall comply and be installed per the applicable code; as regulated by the fire department. **SRZ** (DRH11-00287 per Planning and Zoning)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  3/5/2013 DONE
DetailsBarbara Stitt
Per phone call from Michael Hillman requested the statement sent to him at 3201 Airport way Ste 220 Boise ID 83705///BAS
Print Statement  2/28/2013 DONE
First Notice 12/14/201212/19/2012 DONE
Print Statement  12/19/2012 DONE
Permanent Occupancy  12/4/2012 DONE
DetailsBarbara Stitt
BLD-Final12/3/201212/3/201212/3/2012PPASS
DetailsJim Storey
Phil Phone #: ###-####
FIRE-Final Inspection11/26/201211/27/201211/27/2012APASS
DetailsTroy Cobbley
Life safety passed
PubWorks Occupancy Approval11/26/201211/26/201211/26/2012 DONE
DetailsTiffany Lowery
FIRE-Final Inspection11/20/201211/21/201211/21/2012AFAIL
DetailsTroy Cobbley
All items except for the underground fuel tank sign off (by fire dept.) have been corrected.
Zoning Approval11/21/201211/21/201211/21/2012 DONE
DetailsAndrea Tuning
FIRE-Final Inspection10/31/201210/31/201210/31/2012PFAIL
DetailsTroy Cobbley
Provide final approval of the underground fuel storage tanks through the Boise Fire Dept., replace all of the painted sprinkler uprights in the wash bay (24 of them) and remove the existing horizontal sidewalls that were left when the overhead doors were removed (they are too far from the deck), reverse door hardware at the passage between the washbay and the shop, provide signage per fire review note #22 at the emergency stop button, provide signage for "partially sprinkler building and zone map" at the fire dept. connection as discussed. Two emergency lights repaired as I waited. Emergency stop of gas pump passed, fire extinguisher at pump as well as signage. Per Romeo Gervais final life safety not to be given until the fire dept. sign off on the fuel tanks. Per Scott Arellano the new additions are not required to have the existing fire protection extended into them.
BLD-Framing/Rough-in8/20/20128/20/20128/20/2012PPASS
DetailsJim Storey
Jared Phone #: ###-#### heatter support instaled to roof per engineering ok to cover.
BLD-Energy code compliance7/11/20127/11/20127/11/2012PPASS
DetailsJim Storey
jared Phone #: ###-####
BLD-Energy code compliance7/2/20127/2/20127/2/2012PPASS
DetailsJim Storey
Jarod Phone #: ###-####
BLD-Other6/19/20126/20/20126/20/2012APASS
DetailsJim Storey
phil Phone #: ###-#### canopy ok blots and grout to ft// wall ok to cover upon ele aproval// restarooms ok to cover.
BLD-Wall Bracing5/31/20126/1/20126/1/2012PPASS
DetailsJim Storey
Phill Phone #: ###-#### roof nailling and straps @48" ok to roof.
BLD-Footing5/9/20125/11/20125/11/2012APASS
DetailsJim Storey
Harold- call mins prior for access Phone #: ###-####
Telephone call  4/23/2012 DONE
DetailsSam Zahorka
Verified New Tank below the permitted addition is known by structural inspector Jim Story. He stated Fire is aware and being handled by them.
BLD-Footing4/17/20124/18/20124/18/2012PPASS
DetailsTom Arcoraci
Richard
Phone #: ###-####
Issue PAID IN FULL permit  4/17/2012 DONE
DetailsChristina Prado
OVERRIDE  4/16/2012  
BLD-Footing4/12/20124/16/20124/16/2012APASS
DetailsJim Storey
richard Phone #: ###-#### per richard this inspection has nothing to do with the plan mod,ok per Sam Z if plan mod not affected
Print Occupancy Form  4/16/2012 DONE
DetailsBarbara Stitt
Telephone call  4/16/2012 DONE
DetailsBarbara Stitt
Called Michael and told him permit is ready & fees due on 4-16-12 @ 10:35am also faxed him a copy of fees sheet//BAS
Override - Parcel Holds  4/16/2012  
Permit Ready to Issue  4/16/2012 DONE
DetailsBarbara Stitt
Plan assigned to (SRZ)2/14/20122/14/20124/13/2012 PASS
DetailsSam Zahorka
Plan Modification. Outsource structural failed.
PLANS/APPL TAKEN TO FRONT DESK  4/13/2012 DONE
DetailsSam Zahorka
Routing Off Site - STRUCTURAL4/9/2012 4/13/2012 PASS
DetailsSam Zahorka
Routing - PLAN CHECK3/9/2012 4/13/2012 PASS
DetailsSam Zahorka
Plan Reviewer's activity  4/9/2012 DONE
DetailsSam Zahorka
Received strcutural corrections and routed them to the Outsource Plan reviewer. Waiting for them to pass.
Plan resubmittals received  4/6/2012  
Received 1 cover transmittal, 1 response letter to Sam Zahorka dated 4-6-12 from Jeffrey Griffin, 3 copies of structural calcs for canopy, 3 copies of sheets F1 of 1, E1 of 1 and taken to Sam Zahorka's desk
Routing Off Site - STRUCTURAL3/14/2012 3/20/2012 FAIL
DetailsSam Zahorka
Called Action Couriers for pick-up on 3-14-12 @ 2:45pm//BAS
Corrections needed. Emailed out-source structural reviewers plan review corrections to the architect.
Plan resubmittals received  3/13/2012  
Received 1 copy of of response comments list dated 3-9-12 to Sam Zahorka, 1 copy of comment list from Sam Zahorka to Thomas Zabala dated 2-21-12, 3 copies of structural calcs for canopy, 3 copies of sheet E1 of 1, 3 copies of sheet F1 of 1 and all taken to Sam Zahorka's desk
Routing - FIRE3/7/2012 3/9/2012 PASS
DetailsScott Arellano
See attached Fire Code review comments. Additional requirements for the unattended fuel dispensing station have been added. Final approval will be subject to satisfactory field inspection by the PDS Fire inspector.
Routing - PLAN CHECK3/1/2012 3/7/2012 FAIL
DetailsSam Zahorka
Failed structural review.
Routing PW Environmental3/1/2012 3/1/2012 PASS
DetailsWalt Baumgartner
1500 Flamm Incpt noted on plans, ok
Routing - PUBLIC WORKS2/27/2012 2/28/2012 PASS
DetailsConnie Baumgartner
Routing PW Drainage2/28/2012 2/28/2012 PASS
DetailsBrian Murphy
Routing - PLAN CHECK2/24/2012 2/27/2012 PEND
DetailsSam Zahorka
resubmittals received, routed to PW
Plan resubmittals received  2/27/2012 DONE
DetailsTisha Gallop
received five copies of A-101; inserted into plans at Sam's desk by permit tech. and rerouted to PW.
Routing PW Drainage2/21/2012 2/24/2012 FAIL
DetailsBrian Murphy
NEEDS HYDROCARBON CATCH BASIN INSERT
Routing - PUBLIC WORKS2/21/2012 2/24/2012 FAIL
DetailsConnie Baumgartner
Plan Modification - Failed by Brian Murphy contact at ###-####
Routing - Erosion and Sediment2/24/2012 2/24/2012 PASS
DetailsClint A Smith
Plan Modification does not effect ESC.
Routing Off Site - STRUCTURAL2/17/2012 2/21/2012 FAIL
DetailsSam Zahorka
Plan Modification
Plan Reviewer's activity  2/21/2012 DONE
DetailsSam Zahorka
Emailed the structural plan review report to the architect for the plan modification.Corrections were needed prior to approval.
Routing PW Sewer Rating2/21/2012 2/21/2012 PASS
DetailsConnie Baumgartner
Routing - PLANNING2/17/2012 2/17/2012 PASS
DetailsAndrea Tuning
Plan Modification - 0.5 hours
Telephone call  2/17/2012 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Override - Parcel Holds  2/16/2012  
Issue PAID IN FULL permit  2/16/2012 DONE
DetailsTisha Gallop
CHANGE STATUS TO (REV)  2/16/2012 DONE
DetailsTisha Gallop
change status back to REV because of plan modification
OVERRIDE  2/13/2012  
Plan assigned to (SRZ)12/28/201112/28/20112/13/2012 PASS
DetailsSam Zahorka
2-1-2012
1st review completed.
2nd review completed. waiting for Public Works and Fire review to pass.
Routing - PUBLIC WORKS2/9/2012 2/13/2012 PASS
DetailsConnie Baumgartner
Routing - PLAN CHECK2/13/2012 2/13/2012 PASS
DetailsSam Zahorka
Case Summary (BLD)  2/13/2012 DONE
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  2/13/2012 DONE
DetailsSam Zahorka
Print Occupancy Form  2/13/2012 DONE
Telephone call  2/13/2012 DONE
DetailsChristina Prado
Left message for Thomas at ZGA Architects giving fees due and advising GC?RCE and Rp are required
Permit Ready to Issue  2/13/2012 DONE
DetailsChristina Prado
Plan Modification Accepted  2/13/2012  
Plan modification accepted to add a fuel island with canopy between the south side of the existing facility and the property line. The fuel island with canopy is to be constructed in an area that is currently asphalt. The additions will consit of a 24'x24' concrete pad, a 4' wide x6" high concrete island for future pump mounting, a 24'x24'x3'-0" pre-engineered canopy structure resting on two steel columns at 14'6" above grade. The canopy fascia band is to be white pre-finished metal and the steel columns are to be painted white to match. The function of the addition will be to fuel rental automobiles. The future fuel tank and fuel pump are by others and will be installed after retaining a seperate permit. DR approval of this modificiation has been obtained (DRH12-00020). Submitted 3 copies of sheets G-001, A-101, A-211, E-1, F-1, 3 copies of structural design calcs and a new certificate of value. Everything given to Sam Zahorka
Routing PW Drainage2/9/2012 2/10/2012 PASS
DetailsBrian Murphy
Routing - FIRE2/7/2012 2/9/2012 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing - PLAN CHECK2/9/2012 2/9/2012 PASS
DetailsSam Zahorka
Routing - PLAN CHECK2/6/2012 2/7/2012 PEND
DetailsSam Zahorka
Plan resubmittals received  2/6/2012 DONE
DetailsChristina Prado
Received two sets of response letter addressed to Scott Arellano and two sets of plans marked A-111 & A112. PLans routed back to Sam Z for review
Routing - PLAN CHECK1/31/2012 2/6/2012 PEND
DetailsSam Zahorka
Building Plan Review pending the resubmittal of the Statement of Special Inspection application #310 being stamped and signed by the Engineer. Contacted the architect Thomas Zabala. He will email to me. Fire plan review and Public Records corrections/resubmittals still not received.
Plan resubmittals received  2/1/2012 DONE
DetailsChristina Prado
Received two copies of response letter addressed to Sam Z; two copies of form 310 for special inspections;two copies of plans marked G-001, A-111, A-211, A-311, P-3, E-2 & E-4. Plans inserted by arch rep and givin to Sam Z for further review
1st review completed  1/31/2012 FAIL
Failed Public Works, Plan Check, Fire
Routing - FIRE1/24/2012 1/31/2012 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Routing - PLAN CHECK1/11/2012 1/24/2012 FAIL
DetailsSam Zahorka
1st review completed. Corrections are needed.
Case Summary (BLD)  1/24/2012 DONE
DetailsSam Zahorka
Routing - PLUMBING1/10/2012 1/11/2012 PASS
DetailsDaryl Spivey
Per plans and 2003 UPC.
Routing - PLANNING1/11/2012 1/11/2012 PASS
DetailsAndrea Tuning
DRH11-00287-Andrea Tunning
Routing - Erosion and Sediment1/6/2012 1/10/2012 PASS
DetailsClint A Smith
ESC11-00902 plan waiver approved with conditions attached to the permit.
Routing - PUBLIC WORKS12/30/2011 1/6/2012 FAIL
DetailsConnie Baumgartner
Failed by Brian Murphy contact at ###-#### for drainage issues.
Routing Off Site - STRUCTURAL12/28/2011 1/6/2012 PASS
DetailsBarbara Stitt
Called Action Courier for pick up @ 10:20am
Routing PW Drainage1/3/2012 1/5/2012 FAIL
DetailsBrian Murphy
NEEDS O AND M AND MORE INFO ON WHERE STORMWATER GOES
Plan resubmittals received  1/5/2012 DONE
DetailsTisha Gallop
received two copies of O & M and five copies of plan sheet 1 (Storm Water O & M Exhibit); inserted by permit tech. and taken back to Erosion.
Routing PW Sewer Rating1/3/2012 1/3/2012 PASS
DetailsConnie Baumgartner
Routing - Addressing12/30/2011 12/30/2011 PASS
DetailsTerry Records
Routing PW Environmental12/30/2011 12/30/2011 PASS
DetailsWalt Baumgartner
new 1500 gal flammable interceptor noted for existing and new wash bay drains and existing trenchdrain in main floor area
Routing - PLANNING Land Div12/28/2011 12/30/2011 PASS
DetailsTodd Tucker
Pending Assignment by JCB12/27/2011 12/28/2011 DONE
DetailsJason Blais
Application received 12/27/201112/27/2011 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  12/27/2011 DONE
DetailsBarbara Stitt
Intake Approval  12/27/2011 PASS
DetailsSam Zahorka
Recd Pcfee & Taken To Pln CK  12/27/2011 DONE
DetailsBarbara Stitt