Second Notice | | 5/26/2012 | 6/7/2012 | | DONE |
|
|
|
|
First Notice | 4/9/2012 | 4/9/2012 | 5/16/2012 | | DONE |
Tom Arcoraci
|
|
|
faxed 5-16-12
|
BLD-Final | 4/6/2012 | 4/9/2012 | 4/9/2012 | P | PASS |
Tom Arcoraci
|
|
|
Tony Phone #: ###-####
|
DOC - Permit Finaled | 4/9/2012 | 4/9/2012 | 4/9/2012 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 4/6/2012 | 4/9/2012 | 4/9/2012 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Letter of compliance/Occupancy | | | 4/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Framing/Rough-in | 3/9/2012 | 3/12/2012 | 3/12/2012 | A | PART |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Interior steel stud walls at new demissing wall for stockroom and all interior walls in stockroom area ok.
|
Telephone call | | | 2/28/2012 | | DONE |
Tisha Gallop
|
|
|
called Kent Fahey and told him permit is ready, fees, and need GC to sign form and provide RCE#.
|
Issue PAID IN FULL permit | | | 2/28/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 1/10/2012 | | 2/27/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/26/2012 | | 2/27/2012 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Inspection Record Card- Bld | | | 2/27/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/27/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 1/24/2012 | | 1/26/2012 | | PASS |
Scott Arellano
|
|
|
Application indiates storage not to exceed 12 feet in height. Plan sheet A5.0 shows rack/shelving layout. No seperate review comments attached to plans.
|
1st review completed | | | 1/26/2012 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 1/24/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/11/2012 | | 1/24/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Sewer Rating | 1/10/2012 | | 1/11/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 1/10/2012 | | 1/11/2012 | | PASS |
|
|
|
|
Routing - Addressing | 1/10/2012 | | 1/10/2012 | | PASS |
Terry Records
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/10/2012 | | DONE |
Barbara Stitt
|
|
|
|
Pending Assignment by JCB | 1/10/2012 | | 1/10/2012 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 1/10/2012 | | PASS |
|
|
|
|
Plan resubmittals received | | | 1/9/2012 | | DONE |
Christina Prado
|
|
|
Received two copies of form 310; form 304; one copy of signed checklist; one copy of engineered shelving calcs and two sets of plans marked SH1.0 & SH2.0. PLans and documents given to Carl Westfall for review
|
Intake Approval | | | 12/30/2011 | | FAIL |
Carl Westfall
|
|
|
|
Application received | | 12/29/2011 | 12/29/2011 | | DONE |
Barbara Stitt
|
|
|
|