First Notice | | 3/24/2012 | 4/2/2012 | | DONE |
|
|
|
This permit finaled on the web by Scott Asin
|
Permanent Occupancy | | | 3/14/2012 | | DONE |
|
|
|
|
BLD-Final | 3/12/2012 | 3/13/2012 | 3/13/2012 | A | PASS |
Tom Arcoraci
|
|
|
Scott Asin Phone #: ###-#### >> Inspection requested via web by Scott Asin
|
FIRE-Final Inspection | 3/9/2012 | 3/12/2012 | 3/12/2012 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Conference | 2/10/2012 | 2/13/2012 | 2/13/2012 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Asin
|
BLD-Conference | 2/8/2012 | 2/9/2012 | 2/9/2012 | A | PASS |
Tom Arcoraci
|
|
|
leave grid as it was
|
BLD-Framing/Rough-in | 2/7/2012 | 2/8/2012 | 2/8/2012 | A | PART |
Tom Arcoraci
|
|
|
Plumbing and electrical inspections have been done. The only HVAC work will be above the grid ceiling. I am looking to get approval to start sheetrocking. Thank you. Phone #: ###-#### >> Inspection requested via web by Scott Asin
|
Issue PAID IN FULL permit | | | 1/17/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing PW Sewer Rating | 1/13/2012 | | 1/13/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 1/12/2012 | | 1/13/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLAN CHECK | 1/13/2012 | | 1/13/2012 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 1/13/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/13/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 1/13/2012 | | DONE |
Tisha Gallop
|
|
|
called Gary Asin and left vm permit is ready and fees.
|
Plan assigned to (TLW) | 1/5/2012 | | 1/12/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/12/2012 | | 1/12/2012 | | PASS |
Tim L. Woodard
|
|
|
Plans approved with with redlines about rated penatrations. TLW
|
CHANGE STATUS TO (REV) | | | 1/12/2012 | | DONE |
Tim L. Woodard
|
|
|
Was never routed to PW. TLW
|
Routing - Addressing | 1/12/2012 | | 1/12/2012 | | PASS |
Terry Records
|
|
|
|
Plan resubmittals received | | | 1/11/2012 | | DONE |
Christina Prado
|
|
|
Received two copies of plans marked 1. Given to Tim Woodard for review
|
1st review completed | | | 1/9/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/5/2012 | | 1/9/2012 | | FAIL |
Tim L. Woodard
|
|
|
Refer to attached plan review report. TLW
|
Application received | | 1/5/2012 | 1/5/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/5/2012 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/5/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 1/4/2012 | | PASS |
Tim L. Woodard
|
|
|
|