BLD-Final | 9/6/2012 | 9/7/2012 | 9/7/2012 | A | PASS |
Dave Hannah
|
|
|
Clint Phone #: ###-####
|
DOC - Permit Finaled | 9/7/2012 | 9/7/2012 | 9/7/2012 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 7/2/2012 | 7/3/2012 | 7/3/2012 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 7/2/2012 | 7/2/2012 | 7/2/2012 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall all c/n items completed
|
BLD-Framing/Rough-in | 6/28/2012 | 6/29/2012 | 6/29/2012 | P | FAIL |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall,, correction posted,, ok to insulate
|
BLD-Wall Bracing | 6/13/2012 | 6/13/2012 | 6/13/2012 | P | PASS |
Dave Hannah
|
|
|
ok to cover grond level ext walls
|
BLD-Wall Bracing | 6/4/2012 | 6/5/2012 | 6/5/2012 | A | PART |
Dave Hannah
|
|
|
Bob Phone #: ###-#### ok to cover second floor and ground level fire walls
|
Plan resubmittals received | | | 6/4/2012 | | DONE |
|
|
|
new acca report
|
Routing - MECHANICAL | 6/4/2012 | | 6/4/2012 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
BLD-Foundation | 5/1/2012 | 5/1/2012 | 5/1/2012 | P | PASS |
Dave Hannah
|
|
|
Eduardo Phone #: ###-####
|
BLD-Footing | 4/30/2012 | 4/30/2012 | 4/30/2012 | P | PASS |
Dave Hannah
|
|
|
ALVARO Phone #: ###-####
|
BLD-Final | 4/23/2012 | 4/23/2012 | 4/23/2012 | P | NR |
Dave Hannah
|
|
|
garage code is 1212 or 1400 or 1968 sorry for the 3 diffrent codes. want to make sure u can get in. Phone #: ###-#### >> Inspection requested via web by John Dyche
|
Issue PAID IN FULL permit | | | 2/27/2012 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 1/26/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/26/2012 | | DONE |
|
|
|
|
Telephone call | | | 1/26/2012 | | DONE |
Christina Prado
|
|
|
Left message diving fees due for permit
|
Permit Ready to Issue | | | 1/26/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 1/9/2012 | 1/9/2012 | 1/25/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 1/13/2012 | | 1/25/2012 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 1/25/2012 | | DONE |
|
|
|
|
1st review completed | | | 1/25/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2012 | | |
|
|
|
|
Route to Impact Fee Review | 1/9/2012 | 1/12/2012 | 1/18/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 1/10/2012 | | 1/13/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/10/2012 | | 1/10/2012 | | PASS |
Joshua Johnson
|
|
|
|
Routing - Addressing | 1/9/2012 | | 1/10/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 1/9/2012 | | 1/10/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 1/9/2012 | 1/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 1/9/2012 | | PASS |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2012 | | DONE |
Tisha Gallop
|
|
|
|