BLD-Aging Inspection | 5/13/2020 | 5/13/2020 | 5/14/2020 | | PEND |
Tell Riley
|
|
|
|
BLD-Aging Inspection | 5/12/2020 | 5/12/2020 | 5/12/2020 | | PEND |
Tell Riley
|
|
|
|
BLD-Wall Bracing | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | CANC |
Tell Riley
|
|
|
We are pouring the two short return walls and the building face of the utility trench in the future building. Nothing too structural. The pour is scheduled for 11 am with MTI and and RSCI quality control both present. Phone #: ###-#### Inspection requested via web by John Cloninger
|
BLD-Conference | 1/8/2020 | 1/8/2020 | 1/8/2020 | P | DONE |
Tell Riley
|
|
|
previous inspection on 12/30/2019 was on wrong permit number and inspection is invalid//inspection was intended for permit numberBLD19-03422//
|
BLD-Foundation | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | CANC |
Tell Riley
|
|
|
I (John Cloninger) will be out of town. Rusmir Civic will be the onsite contact - his number is listed above. The 10 am pour will include the east wall and the north wall. If weather permits the slab on grade for the tank bases will also be poured. If there is any trouble my number is ###-####. Phone #: ###-#### Inspection requested via web by John Cloninger//this is the wrong permit number and previous footing inspection under this permit number is not correct//
|
BLD-Concrete | 12/28/2019 | 12/30/2019 | 12/30/2019 | A | PART |
Tell Riley
|
|
|
A pour is planned for 9 am this is not a footer pour. The pour is for the base of the overflow containment trough that runs around two sides of the external storage tank pad. A rebar inspection was performed and passed by MTI. MTI and RSCI QC will be onsite to collect cylinders and to monitor concrete specifications. It would be a good time to visit about what kind of inspections the City wants to perform. This is a small job but there will be numerous small pours. This pour is 6cy. Phone #: ###-#### Inspection requested via web by John Cloninger//met onsite with GC//specials onsite rebar approved per specials, ok pending all specials//blankets and ground heater onsite//
|
Permit Ready to Issue | | | 3/1/2012 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 3/1/2012 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 3/1/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (JCM) | 2/13/2012 | 2/13/2012 | 2/24/2012 | | PASS |
John Menard
|
|
|
ePlanReview Major TI
|
Routing - PLAN CHECK | 2/23/2012 | | 2/24/2012 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/2012 | | DONE |
John Menard
|
|
|
|
Telephone call | | | 2/24/2012 | | DONE |
Rita DeYoung
|
|
|
plans stamped email sent regarding permit issuance.
|
Routing - PLAN CHECK | 2/22/2012 | | 2/23/2012 | | FAIL |
John Menard
|
|
|
|
Routing - Erosion and Sediment | 2/22/2012 | | 2/23/2012 | | FAIL |
Clint A Smith
|
|
|
|
Plan resubmittals requested | | | 2/23/2012 | | DONE |
John Menard
|
|
|
Requested structural plan sheet that was not submitted with second sibmittal package - ProjectDox. JCM
|
Routing - Erosion and Sediment | 2/23/2012 | | 2/23/2012 | | PASS |
Clint A Smith
|
|
|
ESC12-00028 plan approved with conditions attached to the permit.
|
Routing - PLAN CHECK | 2/13/2012 | | 2/17/2012 | | FAIL |
John Menard
|
|
|
|
1st review completed | | | 2/17/2012 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 2/13/2012 | | 2/16/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached,
|
Routing - PLUMBING | 2/13/2012 | | 2/16/2012 | | PASS |
Bill VanDegrift
|
|
|
Per plans and 2003 UPC.
|
Routing - Erosion and Sediment | 2/13/2012 | | 2/15/2012 | | FAIL |
Clint A Smith
|
|
|
|
Routing - PUBLIC WORKS | 2/13/2012 | | 2/14/2012 | | PASS |
Beverly Mountain
|
|
|
|
Meeting | | | 2/13/2012 | | DONE |
Rita DeYoung
|
|
|
Sent Jackie H in PW an email asking who is doing the JV.
|
Routing - Addressing | 2/13/2012 | | 2/13/2012 | | PASS |
April Wing
|
|
|
|
Telephone call | | | 2/13/2012 | | |
|
|
|
e-mail sent to David giving fees due for intake ///dld
|
Intake Approval | | | 2/13/2012 | | PASS |
John Menard
|
|
|
Approve with question on whether ESC permit required. Should route to ESC for determination. JCM
|
Intake Approval | | | 1/31/2012 | | FAIL |
John Menard
|
|
|
1. Please submit Erosion and Sediment Control Permit Application and waiver letter.
2. Please submit structural calculations for project.
3. Please have the project engineer sign and date the plans or indicate that a copy of the signed and dated plans are on file in their office.
|
Intake Approval | | | 1/13/2012 | | FAIL |
|
|
|
Submittal standards were not followed. Could not do the plan intake. Waiting for re-submission.
|
Application received | | | 1/12/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 12 2012 2:01PM
|