First Notice | | 7/4/2013 | 6/24/2013 | | DONE |
|
|
|
Taken to Rita
|
DOC - Permit Finaled | | | 6/4/2013 | | DONE |
|
|
|
Building constructed under permit # BLD12-00342
|
BLD-Final | 3/6/2013 | 3/7/2013 | 3/8/2013 | P | PASS |
Tony Young
|
|
|
Jesus Phone #: ###-####
|
FIRE-Final Inspection | 1/17/2013 | 1/17/2013 | 1/17/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Foundation | 4/12/2012 | 4/13/2012 | 4/13/2012 | A | PART |
Tony Young
|
|
|
jesus Phone #: ###-####,, ok pending special inspection
|
BLD-Footing | 3/29/2012 | 3/30/2012 | 3/30/2012 | A | PART |
Tony Young
|
|
|
jeus Phone #: ###-####,, stem walls,, ok pending special inspection report,, point load footings already poured at the approval of engineer and the S.I.,, pending report
|
BLD-Footing | 3/28/2012 | 3/29/2012 | 3/30/2012 | P | PART |
Tony Young
|
|
|
jeus Phone #: ###-####,, work in progress,, pending special inspection report,, NOTE: point load footings already poured,, engineer and special inspector verified,, pending report
|
Plan assigned to (JCM) | 3/22/2012 | 3/22/2012 | 3/27/2012 | | PASS |
John Menard
|
|
|
plan mod per jason and angie
|
Plan Reviewer's activity | | | 3/27/2012 | | PASS |
John Menard
|
|
|
Reviewed and approved structural plan modifiction. JCM
|
Routing - PLAN CHECK | 3/23/2012 | | 3/27/2012 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2012 | | DONE |
John Menard
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/27/2012 | | DONE |
Rita DeYoung
|
|
|
plan mod is complete and batched stamped in project dox. No fees due.
|
Permit Ready to Issue | | | 2/28/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 2/28/2012 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 2/28/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 2/28/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 2/28/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 2/23/2012 | | DONE |
Rita DeYoung
|
|
|
email sent to Brian regarding permit issuance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/15/2012 | | |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 2/10/2012 | | 2/15/2012 | | PASS |
John Menard
|
|
|
Received an e-mail from consulting structural engineer approving resubmitted revissions. JCM
|
Plan assigned to (JCM) | 1/20/2012 | | 2/15/2012 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 2/9/2012 | | 2/13/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 1/25/2012 | | FAIL |
John Menard
|
|
|
Fire
|
Routing - FIRE | 1/20/2012 | | 1/25/2012 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal items to architect.
|
Routing Off Site - STRUCTURAL | 1/20/2012 | | 1/25/2012 | | FAIL |
John Menard
|
|
|
|
Routing - PLAN CHECK | 1/20/2012 | | 1/23/2012 | | PASS |
John Menard
|
|
|
Approved with attached informational note and change mark. JCM
|
Routing - PLUMBING | 1/20/2012 | | 1/23/2012 | | PASS |
Daryl Spivey
|
|
|
Per plans and 2003 UPC.
|
Pending Assignment by JCM | 1/20/2012 | | 1/20/2012 | | DONE |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 1/20/2012 | | 1/20/2012 | | PASS |
Barbara Moore
|
|
|
|
Routing - Addressing | 1/20/2012 | | 1/20/2012 | | PASS |
John Menard
|
|
|
|
Routing - PLANNING | 1/20/2012 | | 1/20/2012 | | PASS |
Cody Riddle
|
|
|
|
Routing - PLANNING Land Div | 1/20/2012 | | 1/20/2012 | | PASS |
Dave Abo
|
|
|
Parcel over 5 acres in size.
|
Route to Impact Fee Review | 1/20/2012 | | 1/20/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Drainage | 1/20/2012 | | 1/20/2012 | | PASS |
Brian Murphy
|
|
|
|
Intake Approval | | | 1/19/2012 | | PASS |
John Menard
|
|
|
|
Intake Approval | | | 1/18/2012 | | FAIL |
John Menard
|
|
|
After review of the subimitted construction documents for the permit application for the new porposed Public Works Post-Aeration Building (Foundation Only), there are a couple of items that need to be addressed before the application can be accepted.
1. It appears that the electronic application form will only allow me to see the first four lines of the Description of the Scope of Work. The current description that I can read is unclear. Please revise the description to clearly indicate the proposed scope of work to be done under the requested permit (please just use the first four lines).
2. Please submit a site plan that clearly indicates the access streets and shows the required fire department access roadway to the new proposed building.
3. Please resubmit the structural calculation, to just include the calculation for the Post-Aeration building.
4. Please resubmit Special Inspection Form #310, to just include the required special inspections for the Post-Aeration building.
5. Please revise the plans to delete reference to any building construction other than that proposed under this permit for the Post-Aeration building.
6. Please delete any plan sheets that are beyond the scope of the building foundation and underground utility work within the buildng envelope. If plumbing, mechanical or electrical sheets show additional work beyond the underground work, please add a note that these plans are for underground utility information only and all other work shown is for reference only.
|
Application received | | | 1/12/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 12 2012 3:03PM
|