Second Notice | | 5/14/2015 | 6/9/2015 | | DONE |
|
|
|
sent in mail
|
First Notice | | 3/28/2015 | 5/4/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed 5-4-15
|
Permanent Occupancy | | | 3/18/2015 | | DONE |
|
|
|
|
BLD-Final | 3/13/2015 | 3/13/2015 | 3/17/2015 | P | DONE |
Bob Archibald
|
|
|
Exit at rear corrected. project may be issued a certificate of occupancy.
|
BLD-Conference | 2/26/2015 | 3/16/2015 | 3/16/2015 | P | PASS |
Mike Jordan
|
|
|
Status of 11 day N&O?. Rear door has been repaired and is now code compliant per bob archibald.
|
FIRE-Final Inspection | 3/16/2015 | 3/17/2015 | 3/16/2015 | A | DONE |
Bob Archibald
|
|
|
passed per Bob Archibald
|
Print Occupancy Form | | | 3/16/2015 | | DONE |
|
|
|
|
BLD-Conference | 3/4/2015 | 3/4/2015 | 3/4/2015 | A | DONE |
Bob Archibald
|
|
|
Conference with Mr. Duncley on exit door requirements.
|
BLD-Conference | 2/26/2015 | 2/26/2015 | 2/26/2015 | P | DONE |
Mike Jordan
|
|
|
Served 11 day N&O and example of citation.
|
BLD-Conference | 6/4/2014 | 6/5/2014 | 6/5/2014 | P | PEND |
Tom Arcoraci
|
|
|
Site visit to confirm status of permit and scheduled completion? advised owner/agent to complete job and call for finals
|
BLD-Other | 4/22/2014 | 5/1/2014 | 5/1/2014 | A | CANC |
Tom Arcoraci
|
|
|
follow up
|
BLD-Aging Inspection | 4/23/2014 | 4/23/2014 | 4/24/2014 | P | CANC |
Tom Arcoraci
|
|
|
|
Case Summary (BLD) | | | 4/23/2014 | | DONE |
Christina Prado
|
|
|
|
Meeting | | | 4/23/2014 | | DONE |
Sam Zahorka
|
|
|
Met with the building owner in the PDS lobby. Answered his questions concerning the building permit, gave him a set of the approved plans and all documents. Helped set up a sight meeting with the owner and Bob Archibald. Gave the building owner Bob Archibalds business card and requested him to contact Bob Archibald to schedule the onsite meeting to identify uncompleted work. I then called Bob Archibald and explained the building owner would be calling him and what it was about. The building owner was unaware of any building permits going on and was upset.
|
Telephone call | | | 4/23/2014 | | DONE |
Sam Zahorka
|
|
|
Called the architect and let him know about the owners visit to the city. Stan Cole said he has only dealt with the tenant and never the owner. Explained that the owner was going to set up an appointment with Bob Archibald for tomorrow to identify any outstanding work left to complete so they could final out the permit.
|
BLD-Conference | 4/10/2014 | 4/11/2014 | 4/11/2014 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 4/10/2014 | 4/10/2014 | 4/11/2014 | A | FAIL |
Tom Arcoraci
|
|
|
Issue 15 day Notice to complete scope of work and obtain CO or new permit will be required and citation issued. issued 15 day notice to owner
|
BLD-Footing | 10/1/2013 | 10/2/2013 | 10/2/2013 | P | CANC |
Tom Arcoraci
|
|
|
james Phone #: ###-####
|
BLD - Request for Extension | 9/9/2013 | 9/10/2013 | 9/10/2013 | A | PASS |
Tom Arcoraci
|
|
|
waiting for tenanat funds // call Dan to discuss Phone #: ###-####
|
BLD-Conference | 6/6/2013 | 6/7/2013 | 6/7/2013 | A | PASS |
Tom Arcoraci
|
|
|
10 am
|
BLD-Conference | 6/5/2013 | 6/5/2013 | 6/5/2013 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 6/4/2013 | 6/5/2013 | 6/5/2013 | A | PEND |
Tom Arcoraci
|
|
|
Check status of permit per Bob A talked to contractor he will call bob a. to give full staus
|
OVERRIDE | | | 2/11/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/11/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 2/11/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 2/11/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 2/8/2013 | | DONE |
Christina Prado
|
|
|
called architect as well as left voicemail with store and owners cell phone advising permit must be picked up prior to Monday 2/11 at 5pm or else legal action will be taken.
|
Meeting | | | 1/29/2013 | | DONE |
Tisha Gallop
|
|
|
tenant in office, told him need GC form, cert of value from GC, RP and ACHD, then will know fees due.
|
Expiration Notice | 1/22/2013 | 2/12/2013 | 1/22/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 2/7/2012 | 2/7/2012 | 1/17/2013 | | PASS |
Sam Zahorka
|
|
|
ePlanReview case - 3/6/12 1st review deadline
1st review completed. waiting for corrections
|
Routing - PLAN CHECK | 1/17/2013 | | 1/17/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/17/2013 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 1/10/2013 | | DONE |
Sam Zahorka
|
|
|
Telephoned Stan Cole to check the status of the requested permit corrections per the 12/18/12 meeting discussions. Left a message for him to return my telephone call.
|
Meeting | | | 12/18/2012 | | DONE |
Sam Zahorka
|
|
|
Meeting held with the architect, applicant(s), building official, building division manager, city attorney, and myself. Discussed remaining plan review corrections and requested resubmittals. The architect stated he would complete the resubmittals and resubmit electronically within the next weel.
|
Routing - PLAN CHECK | 11/1/2012 | | 11/1/2012 | | FAIL |
Sam Zahorka
|
|
|
|
Extend Review Timeline | | | 7/10/2012 | | DONE |
Jason Blais
|
|
|
|
Routing - PLAN CHECK | 2/21/2012 | | 6/12/2012 | | FAIL |
Sam Zahorka
|
|
|
Waiting for response from the design professional.
|
Plan Reviewer's activity | | | 5/2/2012 | | DONE |
Sam Zahorka
|
|
|
Responded in writing to Stan Cole concerning his clients hardship letter concerning items required due to the change of occupancy. Waiting for resubmittals.
|
Telephone call | | | 4/11/2012 | | DONE |
Sam Zahorka
|
|
|
The architect called and is having difficulty downloading the Building Plan Review corrections/comments. I offered to download and email to him.
|
1st review completed | | | 2/21/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 2/7/2012 | | 2/21/2012 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Erosion and Sediment | 2/7/2012 | | 2/21/2012 | | PASS |
|
|
|
|
Routing - Design Review | 2/7/2012 | | 2/9/2012 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - Exterior accessible parking, signage, curb ramp, uncovering exterior exit doors to provide required second exit
I spoke with Stan Cole. I am going to go ahead and sign off on this one through the building permit. He said for the doors he is removing a sheet of plywood which was put up illegally anyway. The striping of the accessible stalls is fine through this permit as well.
|
Routing - FIRE | 2/7/2012 | | 2/8/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Telephone call | | | 2/7/2012 | | DONE |
Tisha Gallop
|
|
|
called Stan Cole about pln chk fee still not paid. He said owner was unable to pay by link online so will come down today to pay by check.
|
Intake Approval | | | 2/7/2012 | | PASS |
Jason Blais
|
|
|
Plan Review Fees paid.
|
Plan Reviewer's activity | | | 2/3/2012 | | DONE |
Sam Zahorka
|
|
|
Fees due prior to Intake passing.
|
Telephone call | | | 2/3/2012 | | DONE |
Sam Zahorka
|
|
|
Left message for Stan Cole. Fee total email sent on 1/26/12. I will have permit tech re-email fee total.
|
Telephone call | | | 1/26/2012 | | DONE |
Tisha Gallop
|
|
|
sent Stan Cole e-mail to pay plan chk fee.
|
Intake Approval | | | 1/17/2012 | | FAIL |
Sam Zahorka
|
|
|
1/17/2012 Please provide application #520. Please refer to the circled items on the submittal checklist located under the agency comments folder.
|
Intake Approval | | | 1/13/2012 | | FAIL |
Sam Zahorka
|
|
|
Wrong application and checklist submitted for Pre-screen ePlan Review.
|
Application received | | | 1/12/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 12 2012 4:56PM
|