BLD-Final | 8/16/2012 | 8/16/2012 | 8/16/2012 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
DOC - Permit Finaled | 8/16/2012 | 8/16/2012 | 8/16/2012 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 8/14/2012 | 8/15/2012 | 8/16/2012 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
Zoning Approval | 8/16/2012 | 8/16/2012 | 8/16/2012 | | DONE |
Matthew A Halitsky
|
|
|
|
BLD-Final | 8/13/2012 | 8/13/2012 | 8/15/2012 | A | PEND |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
Zoning Approval | 8/8/2012 | 8/8/2012 | 8/8/2012 | | FAIL |
Matthew A Halitsky
|
|
|
Conditions of approval not met - gravel on sides of home.
|
BLD-Final | 8/3/2012 | 8/6/2012 | 8/6/2012 | A | NR |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger Need Mechanical final.
|
BLD-Energy code compliance | 4/2/2012 | 4/3/2012 | 4/3/2012 | P | PASS |
Tony Young
|
|
|
Please inspect later in the afternoon Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
BLD-Framing/Rough-in | 4/2/2012 | 4/2/2012 | 4/2/2012 | P | PASS |
Tony Young
|
|
|
Please inspect later in the afternoon Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
BLD-Wall Bracing | 3/21/2012 | 3/21/2012 | 3/21/2012 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
BLD-Foundation | 2/16/2012 | 2/17/2012 | 2/17/2012 | A | PASS |
Tony Young
|
|
|
Please call ken @ ###-#### 1/2 hour before inspection. Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
BLD-Footing | 2/16/2012 | 2/16/2012 | 2/16/2012 | P | PASS |
Tony Young
|
|
|
Please call ken @ ###-#### 1/2 hour before inspection. Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
Telephone call | | | 2/16/2012 | | DONE |
|
|
|
t/c w ken - permit ready and fees given
|
Permit Ready to Issue | | | 2/16/2012 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/16/2012 | | DONE |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 1/24/2012 | 1/27/2012 | 2/13/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Inspection Record Card- Bld | | | 2/13/2012 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 1/24/2012 | 1/24/2012 | 2/11/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/11/2012 | | 2/11/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2012 | | |
|
|
|
|
1st review completed | | | 2/7/2012 | | FAIL |
|
|
|
|
Case Summary (BLD) | | | 2/7/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/2/2012 | | 2/7/2012 | | FAIL |
Carl D Madsen
|
|
|
Emergency escape window for the master suites is to small. 2-7-12 CDM Window could be increased in height by 1 to 2" and be compliant as well as meet historic requirements per Sarah and Matt.
|
Routing - MECHANICAL | 2/1/2012 | | 2/2/2012 | | FAIL |
Troy James
|
|
|
emailed geoff to address condenser size
|
Routing - MECHANICAL | 2/2/2012 | | 2/2/2012 | | PASS |
Troy James
|
|
|
|
Telephone call | | | 2/1/2012 | | DONE |
Christina Prado
|
|
|
*****Please call Jake at ###-#### when permit ready
|
Routing - PLANNING | 2/1/2012 | | 2/1/2012 | | PASS |
Matthew A Halitsky
|
|
|
Route to mechanical.
|
Plan resubmittals received | | | 1/31/2012 | | DONE |
Tisha Gallop
|
|
|
received revised site plan reduced size and two copies of revised site plan full size and elevations (signed by SMS on 1/31/12). Taken to Matt Halitsky where plans are.
|
Routing - PLANNING | 1/25/2012 | | 1/26/2012 | | FAIL |
Matthew A Halitsky
|
|
|
Pending updated site plan.
|
Routing - Addressing | 1/24/2012 | | 1/25/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 1/25/2012 | | 1/25/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 1/17/2012 | 1/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 1/24/2012 | | PASS |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 1/17/2012 | | FAIL |
Tisha Gallop
|
|
|
see attached checklist
|