Permanent Occupancy | | | 2/28/2012 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 2/17/2012 | 2/17/2012 | 2/17/2012 | P | PASS |
Jim Storey
|
|
|
Jane Phone #: ###-####
|
FIRE-Final Inspection | 2/14/2012 | 2/14/2012 | 2/14/2012 | P | PASS |
Forrest France
|
|
|
Previous C/N items completed. Occupant load amended per plan review. Fire life safety finaled.
|
Plan Reviewer's activity | | | 2/2/2012 | | DONE |
Tim L. Woodard
|
|
|
Approved a revised floor plan submitted by tenant to reduce occupant load by 16 making the maximum occupancy 48 occupants. Post occupant load and install accessible thumbturn. TLW
|
BLD-Final | 1/26/2012 | 1/27/2012 | 1/30/2012 | P | FAIL |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
FIRE-Final Inspection | 1/26/2012 | 1/27/2012 | 1/27/2012 | A | FAIL |
Forrest France
|
|
|
Noted items include door hardware at the second exit, overdue annual inspection for the existing fire sprinkler system, post "door to remain...." signage at the main entry/exit. See list of general requirements attatched to the permit documents for details.
|
Plan assigned to (TLW) | 1/20/2012 | | 1/26/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/20/2012 | | 1/26/2012 | | PASS |
Tim L. Woodard
|
|
|
Tim Woodard
|
1st review completed | | | 1/26/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/26/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Permit Ready to Issue | | | 1/26/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 1/26/2012 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 1/26/2012 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 1/20/2012 | 1/20/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/20/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 1/20/2012 | | PASS |
Tim L. Woodard
|
|
|
|
First Notice | | 3/9/2012 | | | |
|
|
|
|