Third Follow up | | | 8/24/2012 | | DONE |
Tisha Gallop
|
|
|
received fv
|
Third Notice | | 6/20/2012 | 7/18/2012 | | DONE |
|
|
|
returned mail...put GC on hold for FV
|
Third Notice | | 5/21/2012 | 6/6/2012 | | DONE |
|
|
|
Mailed to Carl Funk Const at the Main St address
|
Second Notice | | 5/6/2012 | 5/16/2012 | | DONE |
|
|
|
|
First Notice | | 4/1/2012 | 4/26/2012 | | DONE |
|
|
|
ok to sign off per Rita, no good contact info for the GC and job is fairly small
|
Permanent Occupancy | | | 3/22/2012 | | DONE |
|
|
|
|
BLD-Final | 3/19/2012 | 3/20/2012 | 3/20/2012 | P | PASS |
Mike Jordan
|
|
|
CARL Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 3/19/2012 | 3/20/2012 | 3/20/2012 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 3/20/2012 | | DONE |
|
|
|
|
BLD-Final | 3/9/2012 | 3/12/2012 | 3/12/2012 | P | NR |
Mike Jordan
|
|
|
Carl Phone #: ###-####
|
FIRE-Final Inspection | 3/8/2012 | 3/9/2012 | 3/9/2012 | A | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for the existing fire sprinkler system, provide verification of monitoring and power up the fire alarm system, provide fire extinguishers with current inspection tags place within 75' of travel mounted in a normal path of travel between 5' and 4: A.F.F., provide exit discharge lighting and the missing exit sign per the plans, remove the dead bolt from the rear door, repair the hole in the riser room wall (one hour separation required) and resubmit plans showing the door/wall assembly in the exit corridor and add exit sign/emergency lighting as shown.
|
Routing - Addressing | 3/9/2012 | | 3/9/2012 | | PASS |
April Wing
|
|
|
Address was changed from 1549 N Cormorant Pl to 10959 W Fairview Ave.
|
BLD-Framing/Rough-in | 2/16/2012 | 2/17/2012 | 2/17/2012 | A | PASS |
Jim Sly
|
|
|
carl Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
(F) Reprint permit | | | 2/9/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (TLW) | 1/25/2012 | | 2/8/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 2/8/2012 | | DONE |
Christina Prado
|
|
|
Received one response letter along with one engineering letter with calcs. Routed to Tim for review
|
Routing - PLAN CHECK | 2/8/2012 | | 2/8/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved with resubmitted structural calculations. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 2/8/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 2/8/2012 | | DONE |
|
|
|
|
Telephone call | | | 2/8/2012 | | DONE |
Christina Prado
|
|
|
Left message for Carl giving fees due
|
Permit Ready to Issue | | | 2/8/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 1/25/2012 | | 1/31/2012 | | FAIL |
Tim L. Woodard
|
|
|
Refer to attached Plan Review Report. TLW
|
1st review completed | | | 1/31/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | 1/25/2012 | 1/25/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/25/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/25/2012 | | DONE |
Tisha Gallop
|
|
|
|