BLD-Final | 9/21/2012 | 9/21/2012 | 9/21/2012 | P | PASS |
Dave Hannah
|
|
|
plans will be in the garage by furnace. Please leave plans and C of O in garage when done. Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 9/21/2012 | 9/21/2012 | 9/21/2012 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 9/20/2012 | 9/21/2012 | 9/21/2012 | A | NR |
Dave Hannah
|
|
|
plans will be in the garage by furnace. Please leave plans and C of O in garage when done. Phone #: ###-#### >> Inspection requested via web by Clint Wall everything is ok butt needs to get the fire olace finaled
|
BLD-Energy code compliance | 7/23/2012 | 7/24/2012 | 7/24/2012 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 7/19/2012 | 7/20/2012 | 7/23/2012 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall ok to insulate c/n on site
|
BLD-Wall Bracing | 6/25/2012 | 6/26/2012 | 6/26/2012 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Leonard Dooms both first and second floors ok to cover ext walls
|
BLD-Wall Bracing | 6/22/2012 | 6/25/2012 | 6/25/2012 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Leonard Dooms
|
BLD-Foundation | 5/31/2012 | 5/31/2012 | 6/1/2012 | P | PASS |
Dave Hannah
|
|
|
Wes Phone #: ###-####
|
BLD-Footing | 5/30/2012 | 5/30/2012 | 5/31/2012 | P | PASS |
Dave Hannah
|
|
|
wes Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/26/2012 | | DONE |
Tisha Gallop
|
|
|
paid for and picked up modification
|
OVERRIDE | | | 4/23/2012 | | |
|
|
|
|
Plan assigned to (CDM) | | 4/16/2012 | 4/23/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 4/18/2012 | | 4/23/2012 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 4/23/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/23/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/23/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 4/16/2012 | | 4/18/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/16/2012 | | 4/16/2012 | | PASS |
Joshua Johnson
|
|
|
|
Plan resubmittals received | | | 4/16/2012 | | DONE |
Christina Prado
|
|
|
Received two complete new sets of plans and documents. House plan changed from original "Sunflower" design it was approved under to "Sunflower B" design. Re-route to Planning, Mechanical & Plan Review needed.
|
Issue PAID IN FULL permit | | | 2/27/2012 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 2/14/2012 | | |
|
|
|
|
Route to Impact Fee Review | 1/27/2012 | 2/1/2012 | 2/14/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (CDM) | 1/27/2012 | 1/27/2012 | 2/14/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/3/2012 | | 2/14/2012 | | PASS |
Carl D Madsen
|
|
|
|
Telephone call | | | 2/14/2012 | | DONE |
Tisha Gallop
|
|
|
called Tahoe Homes and left vm permit is ready and fees.
|
1st review completed | | | 2/14/2012 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/14/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/14/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/14/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 1/31/2012 | | 2/3/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/30/2012 | | 1/31/2012 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - PUBLIC WORKS | 1/27/2012 | | 1/30/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 1/27/2012 | 1/27/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 1/27/2012 | | 1/27/2012 | | PASS |
Terry Records
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/27/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 1/27/2012 | | PASS |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/27/2012 | | DONE |
Tisha Gallop
|
|
|
|